Turner v. Georgia River Network, Grady County Board of Commissioners v. Georgia River Network

CourtSupreme Court of Georgia
DecidedJune 15, 2015
DocketS14G1780, S14G1781
StatusPublished

This text of Turner v. Georgia River Network, Grady County Board of Commissioners v. Georgia River Network (Turner v. Georgia River Network, Grady County Board of Commissioners v. Georgia River Network) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turner v. Georgia River Network, Grady County Board of Commissioners v. Georgia River Network, (Ga. 2015).

Opinion

297 Ga. 306 FINAL COPY

S14G1780. TURNER v. GEORGIA RIVER NETWORK et al. S14G1781. GRADY COUNTY BOARD OF COMMISSIONERS v. GEORGIA RIVER NETWORK et al.

BENHAM, Justice.

This appeal arises from our grant of petitions for certiorari filed by

appellants Judson H. Turner, the Director of the Environmental Protection

Division (EPD) of the Georgia Department of Natural Resources (DNR), and the

Grady County Board of Commissioners (Grady County), requesting our review

of the Court of Appeals’s decision in Georgia River Network v. Turner, 328 Ga.

App. 381 (762 SE2d 123) (2014). Appellees Georgia River Network and

American Rivers are both non-profit organizations. The relevant facts show that

in 2010, Grady County received federal approval to construct a 960-acre fishing

lake.1 The project also entailed building a large dam and inundating 129 acres

of wetlands and nine miles of streams to create the lake. To proceed with the

project, Grady County was required to apply for a buffer variance through the

EPD in order to disturb the stream waters that would be affected by the project.

1 See Georgia River Network v. Turner, supra, 328 Ga. App. at 383-384 for a full recitation of the facts. Appellees challenged the variance, arguing that Grady County’s application was

deficient because it failed to address buffers for the wetlands that would also be

affected by the project. The Director granted the variance over appellees’

objections. In a separate letter, the EPD advised appellees that wetlands did not

require buffers because they generally lack wrested vegetation and were not

subject to a variance request. Appellees sought review of the Director’s decision

from an administrative law judge (ALJ) in the Office of State Administrative

Hearings. The ALJ overturned the variance, reasoning that OCGA § 12-7-6 (b)

(15) (A) of the Erosion and Sedimentation Act requires a buffer for all state

waters, including wetlands. The Director and Grady County filed appeals

challenging the ALJ’s decision in the superior courts of Fulton County and

Grady County, respectively. On the substantive issue of the construction and

interpretation of OCGA § 12-7-6 (b) (15) (A),2 both trial courts determined that

the Director’s construction of the statute was correct and that the buffer

requirement only applies to state waters that have wrested vegetation.

2 There were also issues concerning whether the appellees had a statutory right and standing to seek review of the Director’s decision, but those issues are not before us in this appeal.

2 Accordingly, the trial courts reversed the judgment of the ALJ. Appellees then

appealed to the Court of Appeals.

OCGA § 12-7-6 (b) (15) (A) states as follows: “There is established a 25

foot buffer along the banks of all state waters, as measured horizontally from the

point where vegetation has been wrested by normal stream flow or wave action.

. . .” Citing to principles of statutory construction, the Court of Appeals

concluded that this buffer requirement applies to state waters3 whether or not

their banks have wrested vegetation. The Court of Appeals explained that the

language regarding how the buffer is to be measured did not create an additional

exception to OCGA § 12-7-6 (b) (15) (A),4 but merely explained the location of

the buffer. 328 Ga. App. at 391. In addition, the Court of Appeals reasoned that

the statute was internally inconsistent and that its finding that the buffer applied

to all state waters, without regard to the existence of wrested vegetation, would

avoid any absurd or unintended result contrary to the legislature’s purpose in

enacting the legislation. Id. at 392. Based on this analysis, the Court of

3 The Court of Appeals noted that the parties did not dispute that “wetlands” fall within the statutory definition of “state waters” and stated that it would not reach that issue as it had not been fully litigated. Id. at 390, n. 4. We likewise do not address this issue on appeal. 4 There are six statutory exceptions to the buffer requirement which appear at OCGA § 12-7-6 (b) (15) (A) (i)-(vi). These exceptions are not at issue in this appeal.

3 Appeals found the ALJ had not erred and reversed the decisions of the trial

courts. We granted certiorari to determine whether the Court of Appeals erred

in its construction of OCGA § 12-7-6 (b) (15) (A). Because we find that it did

err, its judgment is reversed.

The cardinal rule of statutory construction requires this Court to look diligently for the intention of the General Assembly (OCGA § 1-3-1), and the golden rule of statutory construction requires us to follow the literal language of the statute unless it produces contradiction, absurdity, or such an inconvenience as to [e]nsure that the legislature meant something else. Absent clear evidence that a contrary meaning was intended by the legislature, we assign words in a statute their ordinary, logical, and common meanings.

(Citations and punctuation omitted.) Judicial Council of Georgia v. Brown &

Gallo, LLC, 288 Ga. 294, 296-297 (702 SE2d 894) (2010). Here, the Court of

Appeals erred because the literal language of the statute does not require a

buffer for state waters alongside banks without wrested vegetation. The

language at issue states in pertinent part: “There is established a 25 foot buffer

along the banks of all state waters, as measured horizontally from the point

where vegetation has been wrested. . . .” Had the legislature placed a period

after the word “waters” rather than a comma and had gone no further, then there

would be no other conclusion but that buffers are established along the banks

4 of all state waters, regardless of the existence of wrested vegetation. But that is

not what the legislature did. By adding the phrase “as measured horizontally

from the point where vegetation has been wrested,” the General Assembly

expressly defined how the buffer “is established.” Since the legislature offered

no other method for the buffer to be established but for measuring it horizontally

from the point of wrested vegetation, the buffer necessarily cannot be applied

to state waters that are adjacent to banks without wrested vegetation. No further

interpretation or analysis is required.

Our plain reading of OCGA § 12-7-6 (b) (15) (A) is in keeping with

longstanding tenets of statutory construction: “expressio unius est exclusio

alterius (expression of one thing implies exclusion of another) and expressum

facit cessare tacitum (if some things are expressly mentioned, the inference is

stronger that those not mentioned were intended to be excluded). . . .” See

Hammock v. State, 277 Ga.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen v. Wright
644 S.E.2d 814 (Supreme Court of Georgia, 2007)
Hammock v. State
592 S.E.2d 415 (Supreme Court of Georgia, 2004)
Judicial Council of Ga. v. BROWN & GALLO
702 S.E.2d 894 (Supreme Court of Georgia, 2010)
Georgia River Network v. Turner
762 S.E.2d 123 (Court of Appeals of Georgia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Turner v. Georgia River Network, Grady County Board of Commissioners v. Georgia River Network, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turner-v-georgia-river-network-grady-county-board--ga-2015.