Turner Construction Company v. Eppoliti, Inc., No. 32 31 18 (Nov. 3, 1997)
This text of 1997 Conn. Super. Ct. 11287 (Turner Construction Company v. Eppoliti, Inc., No. 32 31 18 (Nov. 3, 1997)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
2. As of August 31, 1989, Eppoliti, Inc. had completed construction of the masonry wall around the perimeter of the Bacon Field House of the Freeman Athletic Center at CT Page 11288 Wesleyan University.
Answer: Denied only insofar as it could be inferred that the construction was correctly completed, otherwise, admitted.
12. As of January 13, 1990, Eppoliti, Inc. had completed construction of the masonry wall around the perimeter of the Bacon Field House of the Freeman Athletic Center at Wesleyan University.
Answer: Denied.
Moreover, the plaintiff submitted an affidavit and other documents which indicate that Eppoliti did not complete its work on the Bacon Field House until sometime after January 26, 1990. These pleadings and this documentation frame a genuine issue of fact.
The motion for summary judgment is, accordingly, denied.
Moraghan, J.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
1997 Conn. Super. Ct. 11287, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turner-construction-company-v-eppoliti-inc-no-32-31-18-nov-3-1997-connsuperct-1997.