Turley v. Montana Power Co.

534 P.2d 1254, 167 Mont. 39, 1975 Mont. LEXIS 523
Montana Supreme Court·Decided May 8, 1975·No. No. 12755·Published·Cited by 2 cases

Opinion

MR. JUSTICE JOHN C. HARRISON

delivered the Opinion of the Court.

[40] Defendant Montana Power Company brings this appeal from a judgment entered in a personal injury action in tbe district court, Gallatin County, in favor of plaintiff Sam Turley. Three additional defendants, William H. Heiser, Sigrid M. Burrell and Wallace McHenry were originally named, but were dismissed midtrial on their motion without objection of plaintiff. The jury awarded plaintiff damages in the amount of $30,000. Defendant appeals from this verdict and judgment.

Turley was an employee of the Big Sky Model Homes of Livingston, Montana, when he received serious injuries while working on the roof of a Big Sky Home belonging to one Sam Heiser. He came into contact with high voltage wires which passed over the roof of the Heiser home.

The home in question was purchased by Heiser in October 1970, from a business known as Premier Homes, a dealer for the Big Sky brand mobile homes. On October 26, 1970, Premier Homes moved the mobile home onto property owned by Wallace McHenry, at a location known as the four corners area in Gallatin County. The McHenry property consisted of about three acres and was principally used by McHenry to operate a grocery store and a filling station. There were a number of trailer parking areas on the acreage which had been used many years before and McHenry in 1969 allowed Heiser, his brother-in-law, to set up his mobile home on the property. When he sold his original trailer on the site, Heiser was permitted to move a new one on the acreage. The original trailer was 55 feet long, the Big Sky trailer was 66 feet long.

In approximately 1954, defendant Montana Power Company constructed an electrical transmission line running north and south across the property now owned by McHenry. The poles for the lines were located along the property fence lines. One pole was at the north end of the fence line, along with several other poles constituting a switching station. The pole at the south end of the property was some 290 feet from the north end pole. At the time of this construction the Power Com[41] pany received two right-of-way easement deeds, one 50 feet in width, for the operation of its lines.

While there is disagreement on whether the original Heiser trailer was under the power lines, there is no question but that the Big Sky trailer was some 11 feet under the lines. The power lines were originally constructed at a height whereby the lower four lines transmitting 7200/12470 volts, known as the 12 KV system, were seventeen feet, six inches from ground level. The upper three wires, transmitting 50,000 volts, were higher. This height was well within the National Electric Safety Code.

After the Heiser Big Sky trailer was moved under the lines the lower four lines, the 12 KTV lines, extended only five feet, seven inches over the roof of the trailer. The upper lines were eight feet higher. The National Electric Safety Code prescribes that the clearance height over buildings be constructed at a minimum height of eight feet, and with the length of the span here, the height should have been nine feet, four inches.

At the time of moving the trailer onto the property, no one notified Montana Power Company that the trailer was being moved under its lines; nor did anyone ask to put the trailer on its easement. Premier Homes personnel did all of the necessary sewer and electrical hook-ups, when it moved the trailer onto the site.

Immediately after setting up the Big Sky trailer, Heiser began having problems with it and he requested Premier Homes to come out and fix the deficiencies he had found —such as carpeting, panelling, plumbing, the water system, the floor and windows. Premier Homes passed these complaints on to Big Sky Company at Livingston and Turley was sent out by the company to fix them. He first arrived there on November 5 and worked that day through the 7th, making necessary repairs. After a weekend, he returned on the 9th, arriving about 1 p.m., to fix the roof. On that day he was ac[42] companied by another Big Sky Company employee, a Mr. Sparr.

Turley testified he and Heiser went up on the roof of the trailer where Heiser pointed out the problems he saw on the roof. Turley decided that it would be necessary to seal the roof to prevent leakage, Heiser agreed this would be satisfactory. At the time the men were on the roof Turley observed the wires running over the trailer and was aware they were high voltage wires.

Following the roof inspection the two men went down off the roof and Turley worked with his co-employee for an hour or so fixing windows. During this time, he testified, he again observed the power poles and the wires above him. Turley then took his roof repair equipment and went back on the roof and began applying sealer to the roof. At that time he again observed the wires, but did not think they would bother him, even though he is six feet, three inches tall and the wires were only five feet, seven inches over the roof. Sometime during this period his forehead came into contact with the most easterly transmission line resulting in severe injuries.

Appellant Power Company raises six issues on appeal, however due to our finding that issue one, the failure of the trial court to grant defendant’s motions for dismissal and a directed verdict, is controlling, only that issue will be discussed herein.

Appellant Power Company and respondent Turley recognize that issue one is the controlling issue and devote much of their argument to this point.

Appellant relies on a recent opinion of the Court, Sprankle v. DeCock, 165 Mont. 274, 530 P.2d 457, 459, 460 and authorities cited therein as controlling.

Bespondent Turley argues that this is a case where the Court must consider the evidence in a light most favorable to the party against whom the motion is directed and that every reasonable inference to such evidence will be given in that party’s favor. Also, that a cause should never be withdrawn from a [43] jury unless the conclusion from the facts necessarily follows as a matter of law that recovery cannot be had on any view which can be reasonably drawn from the facts which the evidence tends to establish. Parini v. Lanch, 148 Mont. 188, 418 P.2d 861; McIntosh v. Linder-Kind Lumber Co., 144 Mont. 1, 393 P.2d 782.

Respondent cites three Montana eases, Mize v. Rocky Mountain Bell Telephone Co., 38 Mont. 521, 100 P. 971; Bourke v. Butte Electric & Power Co., 33 Mont. 267, 83 P. 470, and Farnum v. Montana-Dakota Power Co., 99 Mont. 217, 43 P.2d 640, in support of his position that because appellant was in violation of the standards set by the National Electrical Safety Code as to the height from the roof of the trailer to the wires, it cannot escape liability by pleading it did not know of the violations. Respondent argues there was a legal duty on the part of appellant to inspect its lines and to know when they crossed places of habitation. Anderson v. Northern States Power Co., 236 Minn. 196, 52 N.W.2d 434, 439.

Free access — add to your briefcase to read the full text and ask questions with AI

Turley v. Montana Power Co., 534 P.2d 1254, 167 Mont. 39, 1975 Mont. LEXIS 523 (Mo. 1975).

534 P.2d 1254 (Turley v. Montana Power Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sizemore v. Montana Power Co.
803 P.2d 629 (Montana Supreme Court, 1990)