Turiello v. City of Revere

443 N.E.2d 1357, 15 Mass. App. Ct. 185, 1983 Mass. App. LEXIS 1182
CourtMassachusetts Appeals Court
DecidedJanuary 20, 1983
StatusPublished

This text of 443 N.E.2d 1357 (Turiello v. City of Revere) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Turiello v. City of Revere, 443 N.E.2d 1357, 15 Mass. App. Ct. 185, 1983 Mass. App. LEXIS 1182 (Mass. Ct. App. 1983).

Opinion

Armstrong, J.

The plaintiff performed architectural services for the city of Revere in connection with the construction of a high school during the years 1972-1974. For his work the plaintiff has been paid $523,616.98, and in this action he claims to be owed certain additional sums. The case was tried to a master under a nonjury action reference in accordance with the procedure in effect prior to the recent revision of Mass.R.Civ.P. 53. See 386 Mass. 1236 (1982). The city appeals from a judgment entered on the master’s findings, awarding the plaintiff $75,414.17 with interest from September 5, 1974, and $25,382.40, with interest from September 12, 1972.

After the master filed his report, the plaintiff moved for its adoption. The city filed seventeen objections to the report, requested summaries of the evidence, and moved for recommittal of the report to the master. The judge entered an order of recommittal requiring the master to prepare summaries of the evidence relative to the findings which were the subject of five of the objections. The city made no objection to the limited scope of that order. Rather, it filed a motion to amend the order of reference so as to require the master to report a full record of the proceedings had before him, including the transcripts of the testimony. That motion was denied, a ruling that lay within the judge’s discretion. See Michelson v. Aronson, 4 Mass. App. Ct. 182, 184-187 (1976); Miller v. Winshall, 9 Mass. App. Ct. 312, 313-314 (1980).

The city, in its original objections to the report, requested that the master summarize the testimony relative to certain findings that were objected to, and designated by transcript reference the testimony to be summarized. The city later prepared summaries of the testimony which had been designated as bearing on the five objections which were the subject of the recommittal order. The testimony thus designated tended to contradict the findings in question. In preparing his own summaries the master declined to include therein [187]*187the evidence which had been requested by the city. In this there was no error. The master was not required to summarize all the evidence bearing on the findings in question, Morin v. Clark, 296 Mass. 479, 483 (1937), but only “‘so much of the evidence as shall be necessary’ to show that there was evidence ‘sufficient in law to support a finding,’ care being taken to see that the summary of so much as is summarized is ‘accurate and fair’ and that it does not by reason of omissions present a distorted picture.” Id., quoting from Rule 90 of the Superior Court (1932) (the quoted material also appears in Rule 49[7] of the Superior Court which was in effect until January 1, 1983). The purpose of a summary under the practice in effect prior to the recent revision of rule 53 was not to permit the court to weigh the evidence for and against the master’s finding. Rather, rule 49(7) declared that a summary was “for the sole purpose of enabling the court to determine such question of law” and “plainly forb[ade] any attempt to use it for any other purpose.” Minot w. Minot, 319 Mass. 253, 261 (1946). Bearing that in mind, we turn to the summaries made by the master in response to the order of recommittal and the action taken by the judge in overruling the objections and confirming the report.

Four of the objections related to the plaintiff’s performance of his obligations under a written contract entered into in 1969, the standard agreement between owner and architect prepared by the American Institute of Architects (AIA Document B131). The contract designated five phases of basic services to be performed by the architect, one of which was supervision of construction. The master found that the plaintiff “satisfactorily completed in an architecturally professional manner all the five phases of [bjasic [s]ervices under the [cjontract by the date of occupancy namely, September 5, 1974.” The contention of the city seems to have been that the plaintiff failed in the supervision stage by permitting a change in the method of securing the roof underlayment, known as “Carey Board”, to the metal decking. The result, the city contended, was that the board failed to [188]*188adhere properly, creating hills and valleys in the roof and, in turn, ponding during storms, necessitating later replacement of some areas of the roof.

The finding quoted was obviously general in nature, despite being labeled subsidiary. In response to the requirement that he summarize the evidence on which the finding was based, the master reported that supervision was the only issue contested with respect to the basic contract and that his general finding of satisfactory supervision was based on eleven designated subsidiary findings. That response was not improper and did not require further recommittal. See Morin v. Clark, 296 Mass. at 481-482; Miller v. Winshall, 9 Mass. App. Ct. at 316. It put the judge in the position of being able to evaluate whether the general finding had adequate support in the stated subsidiary findings. Bills v. Nunno, 4 Mass. App. Ct. 279, 281-283 (1976). Those findings were to the effect that the change in the method of adhering the Carey board to the metal decking by substituting “over-sized massive staples put down with a machine gun for the self-tapping screws” was not the result of inadequate supervision by the plaintiff but was a conscious design change insisted on by a clerk of the works appointed by the mayor of the city, a man with twenty-five years of experience as Supervisor of Plans in the Commonwealth’s Department of Public Works,1 for the purpose of reducing the likelihood of eventual leakage through the larger screw holes. The change was agreed to by the plaintiff and by the roofing and flashing sub-contractor, who was “a General Electric Qualified Applicator of GE Roofing Systems.” (The roof was a so called “urethane roof,” consisting of “Carey Asbestos-Seal Base Material [the Carey board], urethene spray foam, and General Electric Roof Coating, consisting of a silicone weatherproof rubber membrane.”) The subcontractor issued a “General Electric Company Roofing [189]*189Systems Warranty,” which was “also executed on behalf of General Electric Company on May 3, 1974.” The master concluded that the staples were an appropriate substitute for the self-tapping screws and held the Carey board underlayment to the metal decking equally securely. Rejecting the city’s contention that the substitution was the cause of the problems later encountered, he found that the real cause was “negligent maintenance of the roof by the [city], by excessive passage on the roof, by the use of mechanical snow clearing devices, and manual clearance of snow, vandalism, and also by hurricane winds . . . .”

One of the objections was directed at the finding which indicated the position taken by the city’s clerk of the works with respect to the substitution of staples. The clerk of the works had died before the master’s hearing, and the city’s contention, relying on Old Colony Trust Co. v. Shaw, 348 Mass. 212 (1964), appears to be that his declarations were inadmissible as hearsay. While it is true that his declarations would be hearsay if offered to prove the truth of his view that stapling was a preferable method of adhesion, they were also relevant for the nonhearsay purposes of showing the origin of the substitution and the fact that it was the product of a considered decision rather than neglectful supervision by the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Winshall
400 N.E.2d 1306 (Massachusetts Appeals Court, 1980)
Uloth v. City Tank Corp.
384 N.E.2d 1188 (Massachusetts Supreme Judicial Court, 1978)
Arthur R. Murphy, AIA, & Associates, Inc. v. City of Brockton
305 N.E.2d 103 (Massachusetts Supreme Judicial Court, 1973)
Michelson v. Aronson
344 N.E.2d 423 (Massachusetts Appeals Court, 1976)
Perkins School for the Blind v. Rate Setting Commission
423 N.E.2d 765 (Massachusetts Supreme Judicial Court, 1981)
Jenney v. Town of Mattapoisett
141 N.E.2d 517 (Massachusetts Supreme Judicial Court, 1957)
Old Colony Trust Co. v. Shaw
202 N.E.2d 785 (Massachusetts Supreme Judicial Court, 1964)
Bills v. Nunno
346 N.E.2d 718 (Massachusetts Appeals Court, 1976)
City of Marlborough v. Cybulski, Ohnemus & Associates, Inc.
346 N.E.2d 716 (Massachusetts Supreme Judicial Court, 1976)
Morin v. Clark
6 N.E.2d 830 (Massachusetts Supreme Judicial Court, 1937)
Minot v. Minot
66 N.E.2d 5 (Massachusetts Supreme Judicial Court, 1946)
Adalian Bros. v. City of Boston
84 N.E.2d 35 (Massachusetts Supreme Judicial Court, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
443 N.E.2d 1357, 15 Mass. App. Ct. 185, 1983 Mass. App. LEXIS 1182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/turiello-v-city-of-revere-massappct-1983.