Tulsa Excavation, Inc. v. Pinalto

1984 OK CIV APP 30, 684 P.2d 571, 1984 Okla. Civ. App. LEXIS 138
CourtCourt of Civil Appeals of Oklahoma
DecidedJune 19, 1984
DocketNo. 60082
StatusPublished

This text of 1984 OK CIV APP 30 (Tulsa Excavation, Inc. v. Pinalto) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tulsa Excavation, Inc. v. Pinalto, 1984 OK CIV APP 30, 684 P.2d 571, 1984 Okla. Civ. App. LEXIS 138 (Okla. Ct. App. 1984).

Opinion

STUBBLEFIELD, Judge.

This case involves an action for money due under a contract and for foreclosure of a mechanics’ and materialmen’s lien upon real property. The trial court sustained the defendants’ special demurrer to the plaintiff’s petition upon the basis that the plaintiff had not properly perfected its lien prior to filing suit. The plaintiff appeals.

This case was assigned by order of the Oklahoma Supreme Court to the Accelerated Docket for early disposition. Oral argument was had on May 22, 1984.

I

On June 24, 1982, the defendants, Gary and Alice Pinalto, entered into a contract with the plaintiff, Tulsa Excavation, Inc., under the terms of which the plaintiff agreed to perform certain excavation work upon a building site owned by the Pinaltos in Tulsa County. By July 27, 1982, Tulsa Excavation had performed all of its requirements under the contract. Within four months of the last furnishing of material and labor to the improvements on the Pinalto property, Tulsa Excavation commenced this action in the Tulsa County district court. It had not previously filed a lien statement in the office of the county clerk as required by 42 O.S.1981 § 142. The plaintiff’s failure to comply with these provisions formed the basis of the defendants’ special demurrer which was later sustained by the trial court. It is from this order the plaintiff has perfected its appeal to this court. The crucial issue for determination involves the appropriate construction to be given to the requirements of 42 O.S.1981 § 142, which encompass the 1977 amendments.

[572]*572II

Prior to 1977, section 142 provided that any person claiming a lien “shall file in the office of the clerk of the district court of the county in which the land is located” a verified statement setting forth the amount claimed, the names of the owner, contractor, and claimant, and a description of the property subject to the lien. The 1977 amendments substituted the place in which the statement was to be filed from the office of the “clerk of the district court” to the “office of the county clerk” in the county in which the land is situated. The 1977 changes also included the adoption of section 143.1, which provided for notice by the county clerk to the property owners on which the lien attached. Also adopted in 1977 was section 141.1, which provided for the transfer of the records, funds, and powers and duties relating to the filing of mechanics’ and materialmen’s liens from the office of the clerk of the district court to the office of the county clerk. Prior to these statutory changes, the filing of a petition in the district court in the county in which the property was located within the time limits prescribed for the filing of a lien statement was viewed as sufficient to perfect a lien upon the property even in the absence of the filing of a lien statement in accordance with the requirements of the statute. Bank of Earlsboro v. J.E. Crosbie, Inc., 182 Okl. 327, 77 P.2d 547 (1938); Newman v. Kirk, 164 Okl. 147, 23 P.2d 163 (1933); Wass v. Vickery, 137 Okl. 52, 278 P. 336 (1929); Key v. Hill, 93 Okl. 64, 219 P. 308 (1923); South Texas Lumber Co. v. Epps, 48 Okl. 372, 150 P. 164 (1915); Peaceable Creek Coal Co. v. Jackson, 26 Okl. 1, 108 P. 409 (1910).

Where a suit to foreclose a lien is filed in the office of the court clerk in the county where the property sought to be charged is located, and summons issued thereon and service had upon the defendants, there is no necessity for filing a lien claim in addition thereto.

Key v. Hill, 219 P. at 311.

The primary issue on appeal pertains to the effect of the 1977 amendments upon this well established case law. It is the position of the Pinaltos that the amendments have impliedly repealed former case law, because the plaintiff can no longer substantially comply with the provisions of the act by filing his petition in the same office in which he would have been required to file his lien statement. Defendants also contend that the amendments were enacted primarily to protect the rights of property owners and that the plaintiff should not be permitted to subvert the new notice requirements by filing a petition in the district court. Plaintiff, on the other hand, contends that the 1977 amendments did not in any way abrogate pre-existing case law.

To determine which argument shall prevail, an analysis of the underlying rationale of the case law, holding that the filing of a lawsuit substantially complies with the lien filing statute, is necessary to ascertain if that rationale still applies in light of the statutory changes. The case that first espoused the rule in Oklahoma was Peaceable Creek Coal Co. That case relied upon a holding in a similar Arkansas case which concluded that:

“It is true that this is a statute remedy, but it is one enacted for the protection of the mechanics, laborers, and furnishers of supplies to those desiring to erect buildings or to make improvements upon real estate, and that the statute which requires that the mechanic, or other claimant of a lien, should verify and file his account to entitle him to a lien was intended, not alone to identify and fix his right of lien upon the particular property upon which his labor and materials had been bestowed, but also to give notice to others who may contract for liens upon the same property of the nature and extent of his claim. And in cases in which there is a contest between lien claimants the mechanic should be held to such strict performance of the requirements of the statute as to entitle him to its benefits. But in an issue between the mechanic and the owner of the property upon which the labor has been bestowed we apprehend that less strictness in com[573]*573plying with the statute would be required, because, as he is a party to the contract, the owner of the property upon which the labor is bestowed, and may be presumed to know the character of the work performed, as well as the materials furnished, constructive record notice is not so necessary, indeed, scarcely at all necessary, for his protection.”

Peaceable Creek, 108 P. at 411 (quoting Murray v. Rapley, 30 Ark. 568, 571-2 (1875)). The Oklahoma Supreme Court, relying upon this rationale, continued, stating:

Under the foregoing authorities we do not think the filing of such statement was necessary, in view of the commencement of the proceedings within the four months, and all parties within such time being brought in, and having the same legal notice thereby of such claim as they would have had, had such claims been filed ex parte by the lien claimants within the required time with the clerk of the district court. These claims and proceedings in this case were filed and had in the district court; such filings being with the clerk thereof, the same officer with whom the ex parte lien claim or statement was required to be filed. Under such status we think that the statute was sufficiently complied with.

Peaceable Creek, 108 P. at 411. Thus, a distinction was drawn between cases in which the contest was between competing lien claimants, and cases in which the contest arose between the lien claimant and owner of the property against which the lien was claimed. In the latter instance, the filing of a lawsuit to impose and foreclose a lien constituted “sufficient compliance” with the lien filing statute.

The rationale running through the case law descendent from Peaceable Creek

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riffe Petroleum Co. v. Great Nat. Corp., Inc.
1980 OK 112 (Supreme Court of Oklahoma, 1980)
Republic Bank & Trust Co. of Tulsa v. Bohmar Minerals, Inc.
661 P.2d 521 (Supreme Court of Oklahoma, 1983)
Wass v. Vickery
1929 OK 235 (Supreme Court of Oklahoma, 1929)
South Texas Lumber Co. v. Epps
1915 OK 507 (Supreme Court of Oklahoma, 1915)
Newman v. Kirk
1933 OK 405 (Supreme Court of Oklahoma, 1933)
Key v. Hill
1923 OK 421 (Supreme Court of Oklahoma, 1923)
Peaceable Creek Coal Co. v. Jackson
1910 OK 85 (Supreme Court of Oklahoma, 1910)
Bank of Earlsboro v. J. E. Crosbie, Inc.
1938 OK 48 (Supreme Court of Oklahoma, 1938)
Murray v. Rapley
30 Ark. 568 (Supreme Court of Arkansas, 1875)

Cite This Page — Counsel Stack

Bluebook (online)
1984 OK CIV APP 30, 684 P.2d 571, 1984 Okla. Civ. App. LEXIS 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tulsa-excavation-inc-v-pinalto-oklacivapp-1984.