Tudor Construction Co. v. Core Tech Int'l Corp

Superior Court of Guam·Decided November 7, 2014·No. CV0513-12·Unknown

Opinion

6 IN THE SUPERIOR COURT OF GUAM

7 TUDOR CONSTRUCTION CO., INC., )

8 )

9 Plaintiff, ) CIVIL CASE NO. CV0513-12 )

10 vs. )

) FINDINGS OF FACT AND 11 CORE TECH INTERNATIONAL ) CONCLUSIONS OF LAW 12 CORPORATION and FIDELITY AND )

DEPOSIT COMPANY OF MARYLAND, )

13 )

Defendants. )

14 --------------------------~)

15

16 INTRODUCTION

17 This matter came before the Honorable James L. Canto II on Plaintiff Tudor 18 Construction Co., Inc.'s complaint for breach of contract against Defendants Core Tech 19 International Corporation and Fidelity and Deposit Company of Maryland, filed on May 3, 20 2012. A bench trial was held from September 22, 2014 through September 26, 2014. Attorney 21 Thomas M. Tarpley appeared on behalf of Plaintiff, Attorney Anita P. Arriola represented Core 22 Tech International Corporation, and Attorney David W. Dooley represented Defendant Fidelity 23 and Deposit Company of Maryland. Having considered the parties' evidence, oral arguments, 24 and the applicable law, the Court now issues the following findings of fact and conclusions of 25 law pursuant to Guam R. Civ. P. 52 (a).

26 Ill

27

28

ORIGINAL

BACKGROUND

2 On May 3, 2012, Plaintiff Tudor Construction Co., Inc. (hereinafter "Tudor") filed a 3 complaint to allege nonpayment for work completed in two construction projects as a 4 subcontractor to Defendant Core Tech International Corporation (hereinafter "CTI"), where 5 one project was guaranteed by a payment bond executed with Defendant Fidelity and Deposit 6 Company of Maryland (hereinafter "Fidelity"). Tudor alleges that CTI owes $103,525.15 plus 7 interest for its work on the first project for the U.S. Navy (hereinafter "Navy Potable Water 8 Project"). (Compl., 2, May 3, 2012). Tudor also alleges that CTI owes $232,502.49 plus 9 interest for its work on the second project for the Guam Waterworks Authority (hereinafter 10 "GWA Tank Project'). /d. at 2-3. The amount owed for work completed on the GWA Tank 11 Project is fully insured by Fidelity's payment bond pursuant to 5 GCA § 5304. !d. In addition 12 to the amounts owed under the two projects, Tudor seeks: (a) prejudgment interest on all sums 13 the Court determines CTI wrongfully withheld and owes to Plaintiff; and (b) attorney's fees to 14 the prevailing party pursuant to the contract between the parties. (Tudor's Trial Brief, 6, Sept. 15 15, 2014). 16 On November 7, 2012, Tudor moved to supplement its complaint with an additional 17 claim that Fidelity has refused to pay undisputed debts in violation of a surety's good faith duty 18 to process claims. Tudor's proposed supplemental complaint alleges that the parties agreed 19 upon undisputed amounts of liability in August 2012 but that Fidelity withheld payment in bad 20 faith, causing further damages related to creditor claims, and causing the emotional distress and 21 hospitalization of Tudor's President. (Mot. to Add Supplemental Claims, 5-6, Nov. 7, 2012). 22 On January 23, 2013, CTI and Fidelity moved to amend their answers to allege a set-off 23 defense and a breach of contract counterclaim for the GWA Tank Project. Tudor argued that 24 paragraphs nine and ten of the counterclaim did not state plausible claims for relief and were 25 therefore futile or alleged in bad faith. The proposed amended answers also denied the prior 26 admission that $232,502.49 plus interest was owed to Tudor for the GWA Tank Project. 27 Defendants asserted that the prior admission was made in error and Tudor objected that the 28 correction was made in bad faith and with delay that shall cause prejudice.

On April 16, 2013, the Court issued a Decision & Order granting Tudor's motion to 2 amend the complaint in part, but denied Tudor's motion to supplement a claim for emotional 3 distress damages. (Dec. & Order, Apr. 16, 2013). The Court also granted CTI's motion to 4 amend their answer. !d. 5 On January 29, 2014, the Court issued a Decision and Order recognizing a cause of

). 6 action for bad faith claims against a surety. (Dec. & Order, 4-6, Jan. 29, 2014).

7 On September 22, 2014, a bench trial commenced on Tudor's complaint. 8

9 FINDINGS OF FACT 10 In a bench trial, "the judge weighs the evidence, determines the credibility of the 11 witnesses, and finds the facts." United States v. Bales, 813 F.2d 1289, 1293 (4th Cir. 1987). By 12 a preponderance of the evidence, the Court makes the following findings of fact: 13 1. Philip Ahn (hereinafter "Ahn") is the President and founder of Tudor. 14 2. Myong Lee (hereinafter "Lee") is the owner oflron Boy. He is a certified welder. 15 3. Thomas Camacho (hereinafter "Camacho") is the Vice President of Duenas Camacho 16 & Associates (hereinafter "DCA"). He is a structural engineer involved in 17 construction. 18 4. Won Joo Na (hereinafter "Na") is the head of the mechanical department at CTI. He is 19 a mechanical engineer. Previously, he worked as a mechanical engineer for 20 years in 20 Korea and worked on five to six tank projects. He was the Project Manager for the 21 GW A Tank Project and he became involved with the project after CTI issued a stop 22 work order to Tudor. 23 5. David Alan Barnhouse ("hereinafter "Barnhouse") is a certified weld inspector 24 qualified to do visual inspections, and he is an API 653 tank inspector qualified to 25 inspect above ground storage tanks. He is the owner of Island CERTS, a company that 26 conducts safety training for heavy equipment and on-site inspections for structures. 27 He conducted visual inspections of the tank shell welds for Astumbo-1 tank.

6. Dencio Mostoles (hereinafter "Mostoles") is a civil engineer working as a quality 2 control manager at Overland Federal, a construction firm. He previously worked at 3 CTI for 6 years as a project manager for the Navy Potable Water Project. As a project 4 manager, he managed, monitored and controlled the scope of the project. Before 5 working at CTI, he worked at Guam Construction Co. as a project engineer for 6 years 6 on 2 projects at Leo Palace Hotel and Andersen Air Force Base, respectively. 7 The GWA Tank Project 8 7. The formal name of this project is "Phase 1 Inspection & Maintenance Repairs to 9 Guam Waterworks Authority (GWA) Islandwide Steel Water Tank Reservoirs; Project 10 No. IFB-02-ENG-2009." 11 8. In March 2010, the Guam Waterworks Authority (hereinafter "GWA'') hired CTI as 12 the prime contractor to inspect, maintain and repair thirty (30) steel water tank 13 reservoirs located throughout Guam. 14 9. On April 9, 2010, Tudor and CTI entered into a construction subcontract for the Phase 15 1 Inspection and Maintenance Repairs to GWA Island-wide Steel Water Tank 16 Reservoirs, Project No. IFB-02-ENG-2009. Under this contract, Tudor was to be paid 17 $344,750.00 by CTI for its work. 18 10. Tudor hired Iron Boy and !-Construction as its subcontractors. Iron Boy was hired to 19 conduct welding work on the tanks. !-Construction was hired to conduct painting, 20 priming, and other miscellaneous work upon the tanks. 21 11. Na testified that the subcontract price of $344,750.00 included the work on three tanks 22 and start-up and mobilization costs of thirty tanks. 23 12. Na testified that when a project has numerous phases, it is not a common practice to 24 pay the start-up and mobilization costs in advance. 25 13. Iron Boy has yet to be paid in full for its work related to the GWA Tank Project. Iron 26 Boy sought payment from CTI for the amount due from Tudor for its work on the 27 GWA Tank Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Tudor Construction Co. v. Core Tech Int'l Corp, (superctguam 2014).

Tudor Construction Co. v. Core Tech Int'l Corp (Tudor Construction Co. v. Core Tech Int'l Corp) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Noble v. National American Life Insurance
624 P.2d 866 (Arizona Supreme Court, 1981)
CHATEAU CHAMBERAY HOA v. Associated Internat. Ins. Co.
108 Cal. Rptr. 2d 776 (California Court of Appeal, 2001)
Wilson v. 21st Century Insurance
171 P.3d 1082 (California Supreme Court, 2007)