Tucker v. Schumacher

202 P.2d 327, 90 Cal. App. 2d 71, 1949 Cal. App. LEXIS 938
CourtCalifornia Court of Appeal
DecidedFebruary 10, 1949
DocketCiv. 13947
StatusPublished
Cited by13 cases

This text of 202 P.2d 327 (Tucker v. Schumacher) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tucker v. Schumacher, 202 P.2d 327, 90 Cal. App. 2d 71, 1949 Cal. App. LEXIS 938 (Cal. Ct. App. 1949).

Opinion

WARD, J.

This is an action by a contractor for the foreclosure of a mechanic’s lien. Plaintiff contracted to erect a market building on land owned by defendant. All of the defendants named as having some right, title or interest in the premises appeal from the judgment in favor of plaintiff.

The complaint alleges a verbal contract to erect the building ; that all materials were furnished and the labor performed between January and December, 1946, at the request of Harry C. Schumacher; that the reasonable value of the materials and labor agreed to be paid is $39,858.85; that $30,000 of this amount has been paid, and that $9,858.85 remains unpaid.

In a cross-complaint defendants allege that a written contract by plaintiff and Henry C. and Charles H. Schumacher was executed in the amount of $25,300, to be paid in four installments. This written contract dated November 9, 1945, provided that plaintiff should furnish all materials and labor to construct the building according to certain plans.

The cross-complaint also alleged that the written contract provided that plaintiff should purchase and install a neon sign. The neon sign was installed but it is alleged that the contractor plaintiff and cross-defendant refused to pay for *73 its purchase and that this necessitated the cross-complainants procuring a loan, to their damage in the sum of $2,500.

Plaintiff’s answer to the cross-complaint alleges that the written contract was terminated and rescinded prior to the commencement of the work specified in the complaint and that the plans referred to in the cross-complaint are of a different nature and kind than those referred to in the complaint. In brief, the main question presented is whether there was an abandonment of the written contract and a subsequent “verbal” agreement to erect the building on a cost plus basis.

The first three points presented by defendants are in substance : (1) There is no competent legal evidence to sustain the plaintiff’s complaint of abandonment of the original written contract and performance of the work on a cost plus agreement; (2) Plaintiff’s own oral testimony and documentary evidence does not sustain plaintiff’s complaint for the amount of money prayed for, nor is the judgment sustained by the evidence; (3) The evidence does not support the findings of fact and conclusions of law, and the judgment entered accordingly. Two other points are presented: One of them will be disposed of in the final paragraph of this opinion; the other is the claim that there was error of the trial court in denying defendants’ motion for a new trial. The latter contention, in addition to a discussion of the duty of the trial court to have ruled on the motion in favor of defendants, is merely a résumé of the first three points. The real question involved is the sufficiency of the evidence.

There is evidence in the record to sustain the findings. Plaintiff testified that he was and had been a licensed general contractor for 10 years, that in November, 1945, he and Henry C. Schumacher discussed the construction of a store building on defendants’ property, and that during that month the contract—a copy of which was attached to defendants’ pleadings—was signed by Henry C. Schumacher, his father, Charles H. Schumacher, and plaintiff providing for a total contract price of $25,300 to be paid as follows: 25 per cent upon roughing in, 25 per cent when the roof was on, 25 per cent on completion, and the balance in full 35 days after filing notice of completion. Plaintiff further testified that in December, 1945, he had put in the foundation and laid the four corners. With defendants’ consent there was a delay of from four to six months, and when work was resumed the plans were discarded. Plaintiff testified that Mr. Henry C. Schumacher had said, *74 “I have a contract to do this job in order to borrow money from the bank. Regardless of what it costs I have to go ahead anyway, but if it don’t cost that much you will give me the money back and charge me ten percent.” Plaintiff continued, “ So I went ahead on that basis. I had bids from different subcontractors for the whole job. Well, the job was delayed so long that prices went up and Mr. Schumacher got a letter about the price of bricks going up and I said, ‘We can’t go through for that amount of money,’ and he said, ‘All right, go ahead on a cost plus basis and we will get the money.’ ” Plaintiff and his son, who was a carpenter foreman on the job, testified that all items of labor and materials included in the above bill actually went into the construction of the building, and that the amount billed for each such item was fair and reasonable. There is evidence from other contractors that the various items of money paid for labor and material were “fair,” “reasonable,” “approximately right,” or “much lower than usual.” Plaintiff testified that Schumacher never protested any item though the building as erected was 5 feet larger and had numerous changes made under the direction of Schumacher. This testimony was corroborated by several of the foremen for the plumbing, painting and other subcontractors. Plaintiff introduced into evidence the notice of completion filed by Henry and Charles Schumacher on December 11, 1946. It was brought out in cross-examining defendants that the allegations in the answer to the effect that the notice of completion was signed before the building was completed because plaintiff threatened to padlock the building unless it was done were untrue. The evidence established the reasonable value of the work and materials at $39,858.85, and the payment of $30,000, leaving a balance of $9,858.85 due. This is the end of the case unless the parties were legally bound by the written contract.

The court found, ‘ ‘ That it is true that thereafter, and before commencement of construction of the building described in the complaint herein, all parties to said last-mentioned written agreement mutually abandoned and rescinded the said agreement. ’’ The written agreement was the contract first executed. This is not a ease involving the alteration of a contract in writing by the execution of an oral agreement. (Civ. Code, § 1698.) Where parties do not modify but agree upon new terms it has the effect of ending prior agreements. In other words, an oral novation may extinguish a written contract. (Pearsall v. Henry, 153 Cal. 314 [95 P. 154, 159].),

*75 The question here is whether the old contract was mutually abandoned. It was not necessary to meet and state either in writing or orally that the contract was rescinded. (Cincotta v. Catania, 95 Cal.App. 99 [272 P. 330].) If the intent to abandon can be ascertained from the acts and conduct of the parties the same result will be attained. Abandonment may be implied from surrounding facts and circumstances. (Treadwell v. Nickel, 194 Cal. 243 [228 P. 25]; Lohn v. Fletcher Oil Co., 38 Cal.App.2d 26 [100 P.2d 505].) Defendants do not deny that a written contract may be abandoned by a subsequent agreement, but deny that an inference of such abandonment may be drawn from the conduct of the parties herein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flynn v. Sun Life Assurance Co.
809 F. Supp. 2d 1175 (C.D. California, 2011)
Fanucchi & Limi Farms v. United Agri Products
414 F.3d 1075 (Ninth Circuit, 2005)
Hunt v. Smyth
25 Cal. App. 3d 807 (California Court of Appeal, 1972)
Patek & Co. v. Vineberg
210 Cal. App. 2d 20 (California Court of Appeal, 1962)
Schertzinger v. Williams
198 Cal. App. 2d 242 (California Court of Appeal, 1961)
Preszler v. Dudley
314 P.2d 138 (California Court of Appeal, 1957)
Tele-King Distributing Co. of Los Angeles v. Wyle
218 F.2d 940 (Ninth Circuit, 1955)
J. A. Folger & Co. v. Williamson
276 P.2d 645 (California Court of Appeal, 1954)
Unger v. Isaacs
266 P.2d 869 (California Court of Appeal, 1954)
Stamler v. Kissinger
251 P.2d 709 (California Court of Appeal, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
202 P.2d 327, 90 Cal. App. 2d 71, 1949 Cal. App. LEXIS 938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tucker-v-schumacher-calctapp-1949.