Tualatin Valley Builders Supply, Inc. v. TMT Homes of Oregon, Inc.

41 P.3d 429, 179 Or. App. 575, 2002 Ore. App. LEXIS 296
CourtCourt of Appeals of Oregon
DecidedFebruary 20, 2002
DocketC98147CV; A110171
StatusPublished
Cited by5 cases

This text of 41 P.3d 429 (Tualatin Valley Builders Supply, Inc. v. TMT Homes of Oregon, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tualatin Valley Builders Supply, Inc. v. TMT Homes of Oregon, Inc., 41 P.3d 429, 179 Or. App. 575, 2002 Ore. App. LEXIS 296 (Or. Ct. App. 2002).

Opinion

*578 LINDER, J.

ORS 87.076 allows the owner of land against which a construction lien has been perfected, or any other interested party, to purchase a bond in order to secure payment of the construction lien and to free the property from that lien. If, after purchasing the bond, the owner or other interested party notifies the lien claimant that it has secured the bond, the lien attaches to the bond. Once the lien attaches to the bond, the property is freed from the lien and the claimant must proceed with any foreclosure action against the bond only. In this case, the other interested party, TMT Homes of Oregon, Inc. (TMT), did not give notice to the lien claimant, Tualatin Valley Builders Supply, Inc. (TVBS) and, as a result, the trial court concluded that TVBS could either foreclose its lien on the property or could recover against the bond. TVBS 1 elected to recover against the bond, and the trial court entered judgment in the amount of the lien against the bond surety, Cumberland Casualty & Surety Co. (Cumberland). Cumberland appeals from that judgment, arguing that the trial court, in giving TVBS such a remedy, construed the lien bond statutes incorrectly. We agree, and reverse.

The facts are undisputed. TMT was the general contractor on a construction project on land located in Washington County, designated as “Lot 11, Holding Grove.” TMT hired TVBS to be a subcontractor on that project. TMT, for whatever reason, failed to pay TVBS for the materials and labor that it provided on the project. Consequently, TVBS perfected a construction lien on Lot 11 and, within the statutory time period, filed an action in which, among other claims for relief, TVBS sought to foreclose the lien claim on the real property.

After TVBS perfected its lien claim, TMT purchased a bond from Cumberland to secure the lien’s payment. The bond identified TMT and Cumberland as joint obligors. TMT *579 recorded the bond but failed to notify TVBS that it had secured the bond. Nevertheless, TVBS became aware of that fact and amended its complaint. In the amended complaint, TVBS continued to seek to foreclose against the real property. TVBS also, however, added an additional claim in which it named Cumberland as a defendant. That claim was designated an “action on release of lien bond.” In support of that claim, TVBS pleaded that the bond had not been properly served on TVBS as required by ORS 87.078(1) and that the real property therefore was not released from the lien. TVBS nevertheless asserted a right to recover on the bond by alleging: “Nevertheless the bond serves as defendant Cumberland’s undertaking to pay any sum which the plaintiff may recover on the lien claim, together with its costs and attorney fees.”

Cumberland then moved for summary judgment, arguing that, because TMT had not given statutory notice of the bond purchase, the lien had not attached to the bond and, consequently, Cumberland was not liable to TVBS for its lien on Lot 11. In response, TVBS argued that, even if the hen did not attach to the bond, TVBS could recover the amount of its lien from the bond because it was an intended third-party beneficiary of the bond contract between TMT and Cumberland. The trial court denied the motion for summary judgment, concluding that the lien bond statutes allowed the lien claimant to foreclose on the property or to recover against the bond, even if the lien had not attached to the bond. The trial court expressly declined to reach or address TVBS’s third-party beneficiary theory.

On appeal, Cumberland renews its argument. We first address whether the trial court erred in its conclusion that the lien bond statutes, ORS 87.076 to 87.088, give a lien claimant in these circumstances the option to recover the amount of its lien either from the bond or the property to which the lien is attached. We begin by examining the text and the context of the statutes, pursuant to the interpretative methodology outlined in PGE v. Bureau of Labor and Industries, 317 Or 606, 610-11, 859 P2d 1143 (1993).

The trial court based its ruling on Cumberland’s motion for summary judgment on three principal conclusions: (1) TVBS’s lien did not attach to the bond because TMT *580 did not give notice of the bond purchase as ORS 87.078(1) requires; (2) because the notice provisions of “ORS 87.078 [were] intended to benefit the person who purchased the bond, and the lien claimant,” the lien claimant could proceed against the bond as though notice was given “even though the lien d[id] not attach to the bond”; and (3) because the lien did not attach to the bond, the real property was not freed from the lien, and, “therefore, TVBS [could] elect to pursue either the bond * * * or to foreclose on the real property.” In effect, the trial court concluded that the statutory scheme gives the lien claimant an action against the bond as well as the right to foreclose the lien on the real property. As we describe below, however, neither ORS 87.078(1) nor any of the other statutes that apply to construction liens and lien bonds creates that dual remedy for a lien claimant.

The plain language of three of the lien bond statutes, and the relationship of those statutes to one another, leads us to our conclusion. First, ORS 87.076 prescribes when and how a bond or deposit of money may serve as the object against which a construction lien attaches, in lieu of the real property or improvement on which that lien has been perfected. Specifically, the “owner of an improvement or land against which” a perfected construction lien is claimed, or “other interested person,” may obtain a bond or may deposit a sum of money with the county treasurer any time after a claimant has perfected his or her lien. ORS 87.076. If the owner or interested person chooses to obtain a bond, the bond must be purchased from a corporation authorized to issue surety bonds in Oregon and must be recorded in the county where the lien was filed. ORS 87.076(1). Alternatively, the owner or interested person may deposit with the county treasurer money as specified in ORS 87.076(2)(a) (150 percent of the lien, or $1,000, whichever is greater).

ORS 87.083

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mannex Corp. v. Bruns
279 P.3d 278 (Court of Appeals of Oregon, 2012)
Griffin v. Unocal Corp.
990 So. 2d 291 (Supreme Court of Alabama, 2008)
Cline v. Ashland, Inc.
970 So. 2d 755 (Supreme Court of Alabama, 2007)
Mountain Ranch Corp. v. Amalgam Enterprises, Inc.
143 P.3d 1065 (Colorado Court of Appeals, 2005)
Valencich v. TMT Homes of Oregon, Inc.
88 P.3d 300 (Court of Appeals of Oregon, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
41 P.3d 429, 179 Or. App. 575, 2002 Ore. App. LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tualatin-valley-builders-supply-inc-v-tmt-homes-of-oregon-inc-orctapp-2002.