T.S.I., Inc., Cross-Appellant v. Metric Constructors, Inc., Cross-Appellee

817 F.2d 94, 1987 U.S. App. LEXIS 6304
CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 14, 1987
Docket86-8218
StatusPublished

This text of 817 F.2d 94 (T.S.I., Inc., Cross-Appellant v. Metric Constructors, Inc., Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T.S.I., Inc., Cross-Appellant v. Metric Constructors, Inc., Cross-Appellee, 817 F.2d 94, 1987 U.S. App. LEXIS 6304 (11th Cir. 1987).

Opinion

LYNNE, Senior District Judge:

Proceeding as third-party beneficiary of a subcontract between Metric Constructors, Inc. (Metric), and Pro-Tech Corporation (Pro-Tech), dated September 22, 1981, T.S.I., Inc. (TSI), brought suit to recover from Metric 1 the invoice price of barrels of “Thermo-lag” delivered to Metric’s job site. The case was referred to a Special Master for a report and recommendation. The Master conducted extensive hearings which appear in the record, and on November 6, 1985, he recommended that judgment be entered in favor of TSI in the amount of $195,480, without prejudgment interest. By order entered February 20, 1986, the district court approved and adopted the Special Master’s Findings of Fact and Conclusions of Law in their entirety and directed the entry of a judgment in favor of TSI and against Metric in the recommended amount. Final judgment was entered February 20, 1986, and this appeal ensued. TSI cross-appealed from the disallowance of pre-judgment interest. We REVERSE and REMAND with direction on the direct appeal, and DISMISS the cross-appeal as moot.

FACTS

TSI is the exclusive manufacturer of spray fireproofing material marketed under the trade name “Thermo-lag”. Metric is a building contractor. It was the principal contractor for the construction of a pharmaceutical plant in Augusta, Georgia, for G.D. Searle and Company (owner).

Pro-Tech is an applicator of fire resistant sprayable coatings. Metric entered into a contract with Pro-Tech, dated September 22, 1981, to supply and install spray fireproofing materia] on such project. In the prime contract, the owner specified Thermo-lag as the chemical fire resistant system to be utilized.

Metric solicited Pro-Tech to submit a bid for applying such materials. Because of *96 Pro-Tech’s perilous financial condition, TSI refused to ship such materials on credit. Prior to the signing of the subcontract, Pro-Tech informed Metric that TSI would not agree to supply materials unless one of four alternatives for assuring payment to TSI was adopted: (1) that Metric buy the fire resistant material from TSI and supply it directly to Pro-Tech; (2) that the owner purchase the materials in advance; (3) that Pro-Tech assign to TSI its accounts receivable from Metric for payment for the materials, or (4) that Metric pay for the materials separately by joint check issued to Pro-Tech and TSI.

There were no direct negotiations between TSI and Metric. Pro-Tech acted as an intermediary in seeking an arrangement which would induce TSI to ship the materials on credit. It is undisputed that Metric explicitly rejected alternatives (1), (2), and (3). It informed Pro-Tech that it could communicate to TSI its agreement to insert a joint check provision in the subcontract. 2 Thereafter, through Pro-Tech, TSI proposed the language of such provision which appears in Schedule C of the subcontract as follows:

PAYMENT OF $405,000.00 FOR FIREPROOFING MATERIAL 3 TO BE MADE BY JOINT CHECK TO PRO-TECH AND TSI BASED ON NET 30 INVOICE BILLING FROM TSI TO PRO-TECH. SUPPORTED BY RECEIVING REPORTS FOR MATERIAL BILLED

Also added to the joint check provision at Pro-Tech’s request was:

Material F.O.B. St. Louis, Mo.

After the subcontract was signed by the parties, Pro-Tech commenced performance of the work in November, 1981, and worked through the middle of December, 1981. One shipment of material was received in November, 1981. When it was received, it was counted, signed for, and stored by Metric. This material was paid for by Metric by a joint check to Pro-Tech and TSI in the amount of $66,970, and was based upon an invoice from TSI to Pro-Tech, dated November 16, 1981.

Pro-Tech returned to the project in March, 1981, and subsequently received a joint check from Metric made to the order of Pro-Tech and TSI, dated May 4, 1982, in the amount of $125,795. This check was based upon TSI invoices of March 15, 1982, in the amount of $66,970, and March 30, 1982, in the amount of $58,825. These were the only two checks issued by Metric. No checks were issued by either Metric or Pro-Tech for the shipments of Thermo-lag delivered to the job site on June 9, July 2, and July 23, 1982. Invoices relating to these three shipments aggregated the sum of $195,480.

In late May or early June, 1982, Metric began to be dissatisfied with Pro-Tech’s performance. Their relationship deteriorated to the point that Pro-Tech left the job on July 28, 1982, and Metric proceeded to terminate the subcontract and contracted with another applicator to finish the fireproofing.

While Metric took possession of all equipment and material left on the job by Pro-Tech in accordance with Paragraph 21 of the contract, it later demanded that TSI remove such material from the job site, and when TSI declined to do so and the shelf life of the Thermo-lag had nearly or totally expired, Metric took such material to the Richmond County dump for disposal.

DISCUSSION

We agree that TSI was a third-party beneficiary of the subcontract and had standing to sue for a breach thereof, but we must first determine the obligation as *97 sumed by Metric which inured to the benefit of TSI. It seems obvious that if Metric had issued a check for Thermo-lag payable only to Pro-Tech, TSI could have prevailed on a cause of action for breach of the joint check provision. However, that is not this case.

The Master concluded as a matter of law that the joint check provision was ambiguous. Thereupon, he proceeded to receive and consider voluminous parole evidence in an effort to arrive at the intention of the parties with regard to such provision. Strangely enough, in Paragraph 6 of his report, the Master referred to only two of the alternatives proposed by TSI through its intermediary, Pro-Tech, to Metric. He discussed only assignment of accounts receivable and the joint check provision. Then, by circular reasoning, he concluded that the language of the joint check provision which TSI had proposed through Pro-Tech, bound Metric to buy the fire retardant materials from TSI, an obligation which it had flatly refused to assume.

The facts in Sentry Engineering & Construction, Inc. v. American Olean Tile Company, 172 Ga.App. 769, 324 S.E.2d 591 (1984), are strikingly similar to those in the case sub judice. We regard any distinctions to be without significant difference. There American Olean Tile Company, Inc. (American), brought an action against Sentry Engineering & Construction, Inc. (Sentry), a general contractor, seeking to recover the balance due for materials sold to C.A. Newman (Newman), a subcontractor. Newman had agreed to install tile in the buildings of the construction project. He subsequently contacted American in order to purchase tile on credit. Having determined that Newman was unworthy of credit, American requested Sentry to enter into a “general contractor’s agreement” whereby Sentry would agree to the terms of the sale of the tile to Newman. Sentry refused to enter into such an agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sentry Engineering & Construction, Inc. v. American Olean Tile Co.
324 S.E.2d 591 (Court of Appeals of Georgia, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
817 F.2d 94, 1987 U.S. App. LEXIS 6304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tsi-inc-cross-appellant-v-metric-constructors-inc-cross-appellee-ca11-1987.