Trussway, Inc. v. Wetzel

928 S.W.2d 174, 1996 WL 354643
CourtCourt of Appeals of Texas
DecidedAugust 20, 1996
Docket09-94-264 CV
StatusPublished
Cited by3 cases

This text of 928 S.W.2d 174 (Trussway, Inc. v. Wetzel) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trussway, Inc. v. Wetzel, 928 S.W.2d 174, 1996 WL 354643 (Tex. Ct. App. 1996).

Opinion

OPINION

NYE, 1 Justice (Assigned).

This appeal arises from an action filed by homeowners Don and Pamela Wetzel for the inadequate construction of their residence, resulting in over one million dollars worth of damage. The central issue remains whether Appellant Trussway, Inc., the sole defendant held liable for the damages, has waived its right to complain of the trial court’s judgment in light of a settlement agreement it reached with the Wetzels after the final judgment had been entered. We answer this question affirmatively. The judgment of the trial court is affirmed.

Don A. and Pamela G. Wetzel contracted with a multitude of architects and construction companies to build a home in The Woodlands, Texas. Appellant Trussway, Inc. was assigned to provide and employ the trusses necessary to support the structure. Ultimately, the trusses failed to provide adequate support, causing heavy damage to the residence. On July 13, 1992, the Wetzels sued the appellant Trussway, the numerous appellees, and several other entities not parties to this appeal. By their Third Amended Original Petition, the Wetzels alleged breach of contract and warranty, deceptive trade practices, misrepresentation, negligent misrepresentation, negligence, gross negligence, and strict liability. Trussway filed cross-claims for contribution and indemnity against all of the appellees for negligently failing to supply the proper information necessary to design trusses that would adequately support the construction of the home.

At the conclusion of the trial, the jury found Trussway and the appellees negligent in varying degrees, thus causing the damages suffered by the Wetzels. The jury also found liability on the part of Trussway for deceptive trade practices. The trial court, in its judgment, made a finding that this case was founded solely in contract and deceptive trade practices, and found the jury’s answers with regard to negligence and gross negligence should be disregarded. The trial court entered judgment for the Wetzels and against appellant Trussway for $1,052,500.00 (one million fifty-two thousand and five hundred dollars) for actual damages, $125,000.00 for attorney’s fees (pre-trial and trial), $137,-000.00 in attorney’s fees for appeal, and ten percent interest on the award. The court entered a take-nothing judgment against Trussway on its cross-claims for contribution and indemnity filed against Appellees. Trussway perfected its appeal.

Appellant filed its brief contending in six points of error the trial court erred by disregarding the jury’s findings of negligence against the appellees, thereby depriving appellant of its purported right to contribution and indemnity.

On September 12, 1994, appellant Truss-way and the Wetzels, the original complainants in this suit, signed a “Release of Judgment” as well as an “Agreement to Settle and Release,” both of which were filed with the trial court on December 27, 1994. The terms of the agreement and release are set *176 out hereinafter. Appellant’s brief was filed in mid-December 1994, following the Release of Judgment and the Agreement to Settle and Release.

Appellees contend appellant Trussway has waived any complaints it may have with regard to the trial court’s judgment, and in particular the take-nothing judgments entered against Trussway and in favor of its cross-defendants (appellees), as Trussway has settled its claims with the Wetzels post-trial. We agree.

The judgment in this ease specifically provides in pertinent part,

IT IS FURTHER ORDERED that Trussway take nothing on its cross-claims against Anderson & Associates, W. Anderson, Gatewood, Gatewood & Associates, Johnson, Gouehe, and Deerfield. All other relief not expressly granted or denied herein is denied.

Post-trial, the Wetzels accepted $1,325,-000.00 from Trussway in settlement of its claims against the truss maker. (The judgment required Trussway to pay $1,314,500.00 plus interest). In exchange, the Wetzels agreed to “ACQUIT, DISCHARGE AND RELEASE TRUSSWAY, INC., JAMES K. MEADE and THEIR INSURERS, os well as other parties for whom they may be vicariously or otherwise liable_” (emphasis added).

As evidence of the agreement between the Wetzels and Trussway, a “Release of Judgment” was signed by the Wetzels and Truss-way on September 12, 1994 and filed in the court’s record on December 27, 1994. The document provides, in pertinent part,

... Don A Wetzel and Pamela C. [sic] Wetzel, judgment creditors, recovered a judgment against Trussway, Inc., judgment debtor, for the sum of ... $1,052,-500.00, pretrial and trial attorneys’ fees in the amount of ... $125,000.00, and appellate attorneys’ fees in the amount of ... $137,000, together with costs of court and pre-judgment and post-judgment interest; and
WHEREAS, such judgment has been compromised and settled and the consideration for the same has been fully paid to the judgment creditors;
NOW, THEREFORE, we, DON WET-ZEL and PAMELA WETZEL, acknowledge full payment for the compromise and settlement of such judgment and hereby DISCHARGE and RELEASE TRUSS-WAY, INC., ... from such judgment_

(emphasis added).

As further evidence of the negotiation between the parties, an “Agreement to Settle and Release” was signed by the Wetzels and Trussway on September 12, 1994, and filed December 27, 1994. This document provides, in pertinent part,

The plaintiffs filed suit against the defendants, and other parties who are not specifically identified in the agreement, and sought compensatory, exemplary and treble damages....
The plaintiffs and the defendants recognize that bona fide disputes exist concerning the issues that may be raised in the appeal of the judgment. In order to resolve (1) all known and unknown claims and disputes that exist between the plaintiffs and the defendants as a result of the known and unknown defects and damages to the residence produced and/or proximately caused by the defendants, (2) the judgment and (3) the appeal, the plaintiffs and defendants have agreed to compromise and settle all known and unknown claims and disputes between them as well as the underlying judgment from which the appeal has been perfected.

The execution of this settlement agreement post-trial precludes Trussway from now complaining of the trial court’s judgment, which entered a take-nothing judgment against Trussway on its cross-claims for indemnity against all of the appel-lees. First, Trussway, having satisfied and accepted the trial court’s judgment, cannot now attempt to attack it on appeal. Further, the contribution scheme which would otherwise be applicable to the facts of this case does not provide for indemnity in favor of Trussway. Additionally, a defendant that is party to a settlement agreement cannot then seek indemnity from its co-defendants.

*177 JUDGMENT SATISFIED

A party cannot treat a judgment as both right and wrong.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Beaumont Heritage Society
339 S.W.3d 893 (Court of Appeals of Texas, 2011)
Hendricks v. Thornton
973 S.W.2d 348 (Court of Appeals of Texas, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
928 S.W.2d 174, 1996 WL 354643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trussway-inc-v-wetzel-texapp-1996.