Truss Works v. Oswood Construction

2022 MT 42, 504 P.3d 1116, 408 Mont. 27
Montana Supreme Court·Decided March 1, 2022·No. DA 21-0185·Published·Cited by 2 cases

Opinion

03/01/2022

DA 21-0185

Case Number: DA 21-0185

IN THE SUPREME COURT OF THE STATE OF MONTANA 2022 MT 42

TRUSS WORKS, INC., a Montana corporation, Plaintiff and Appellee,

v.

OSWOOD CONSTRUCTION COMPANY, a Montana corporation, Defendant and Appellant,

and

TRAVELER’S CASUALTY AND SURETY COMPANY OF AMERICA, a Connecticut corporation, VOYAGEUR APARTMENTS, LP, a Minnesota Limited Partnership, and HUB INTERNATIONAL MOUNTAIN STATES LIMITED, a Montana corporation,

Defendants.

APPEAL FROM: District Court of the Eighth Judicial District, In and For the County of Cascade, Cause No. DDV-16-405 Honorable John W. Parker, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

Maxon R. Davis, Davis, Hatley, Haffeman & Tighe, P.C., Great Falls, Montana

For Appellee:

Kirk D. Evenson, Marra, Evenson & Levine, P.C., Great Falls, Montana

Submitted on Briefs: January 12, 2022 Decided: March 1, 2022

Filed:

c .,.--.

6-- 4f

Clerk

Justice Beth Baker delivered the Opinion of the Court.

¶1 Oswood Construction Company (Oswood) appeals the Eighth Judicial District Court’s decision and final judgment in favor of Truss Works, Inc. (Truss Works), to foreclose a construction lien against Oswood. Oswood contends that the District Court erred by failing to make findings of fact or to otherwise address Oswood’s counterclaim. We affirm.

FACTUAL AND PROCEDURAL BACKGROUND

¶2 Oswood is a commercial building contractor in Great Falls owned and operated by Douglas (Doug) Oswood and his two sons, Nicholas (Nick) and Troy. In 2015, Voyageur Apartments, LP, awarded Oswood a contract to construct the Voyageur Apartments, a senior living apartment building in Great Falls. Owned and operated by Ron Beeler and his son Greg, Truss Works designs and fabricates trusses. Truss Works submitted a bid to Oswood for the Voyageur Apartments, and Oswood selected Truss Works as the truss supplier. The parties entered into a purchase order contract (Purchase Order) for the design and fabrication of wood trusses totaling $87,548.

¶3 Throughout the course of the project, Oswood and Truss Works had numerous disagreements regarding Truss Works’s obligations under the contract, including its submission of truss drawings, its design of the trusses, and its design and supply of truss hangers. The disputes culminated in January 2016 when Oswood refused to make payment of $25,831 to Truss Works for the last set of trusses. Oswood further did not pay Truss Works $6,821 for the balance of the contract and additional change orders due May 7, 2016.

¶4 Truss Works filed a construction lien against the Voyageur Apartments on January 14, 2016. Oswood obtained a construction lien release bond through HUB International Mountain States Limited and Traveler’s Casualty and Surety Company of America. Truss Works filed an action in the Eighth Judicial District Court to foreclose on its construction lien, and Oswood counterclaimed, alleging that delays attributable to Truss Works caused Oswood $118,571 in damages.

¶5 The District Court held a bench trial over four non-consecutive days. Truss Works presented testimony that it designed and fabricated the roof trusses but was not paid for them or for the contract balance. Oswood argued that Truss Works was not entitled to the remaining payments because Truss Works’s failures to submit complete shop drawings, to timely deliver trusses, and to design and supply the connections for the trusses were breaches of the Purchase Order and caused Oswood to incur additional costs. Each party called numerous witnesses and introduced voluminous exhibits.

¶6 The District Court issued its findings of fact and conclusions of law eighteen months after the trial concluded. The court found that Oswood did not cooperate with Truss Works during the submission process, resulting in a ripple effect throughout the project’s timeline. The court acknowledged that Truss Works had improperly designed the second-floor trusses and had produced the truss designs “on a piecemeal basis”; it concluded, however, that Oswood’s refusal to pay Truss Works its last installment constituted a “full[ ] breach” of contract. Following additional proceedings on attorney fees, the District Court entered judgment in Truss Works’s favor, awarding it $32,662 for the unpaid installment under the

Purchase Order, the balance of the contract, and the change orders, together with $39,113.23 in attorney fees.

STANDARDS OF REVIEW

¶7 When a district court sits without a jury, we review the court’s findings of fact for clear error and its conclusions of law for correctness. Norwood v. Service Distrib., Inc., 2000 MT 4, ¶¶ 21-22, 297 Mont. 473, 994 P.2d 25 (citing M. R. Civ. P. 52(a)) (other citations omitted). A finding of fact is clearly erroneous if it is “not supported by substantial credible evidence,” if the district court “misapprehended the effect of the evidence,” or if our review of the record convinces us that the district court made a mistake. Norwood, ¶ 21 (citation omitted). “[I]n determining whether the trial court’s findings are supported by substantial credible evidence, this Court must view the evidence in the light most favorable to the prevailing party.” Norwood, ¶ 21 (citation omitted).

DISCUSSION

¶8 Did the District Court make sufficient findings of fact and conclusions of law in granting judgment to Truss Works without ruling on Oswood’s counterclaim?

¶9 Oswood argues that the District Court’s findings of fact are clearly erroneous because the court never addressed its counterclaim and failed to mention the “virtually unchallenged” evidence supporting it. Truss Works asserts that the District Court implicitly rejected Oswood’s counterclaim when it ruled that Oswood “fully breached” the contract. Truss Works urges us to apply the doctrine of implied findings to uphold the District Court’s judgment.

¶10 Under M. R. Civ. P. 52(a)(1), when a district court acts as the fact-finder in an action tried without a jury, “the court must find the facts specially and state its conclusions of law separately.” “The litmus test [under Rule 52(a)(1)] is whether a district court’s order sets forth reasoning, based upon its findings of fact and conclusions of law, in a manner sufficient to allow informed appellate review.” State v. Baty, 2017 MT 89, ¶ 13, 387 Mont. 252, 393 P.3d 187 (quoting Snavely v. St. John, 2006 MT 175, ¶ 11, 333 Mont. 16, 140 P.3d 492).

¶11 Oswood is correct that the District Court did not include the word “counterclaim” or make an explicit ruling on the counterclaim. But the court did address the evidence Oswood presented at trial in support of its claim for damages. Oswood’s counterclaim alleged that Truss Works breached the Purchase Order and failed to timely perform its obligations, causing Oswood $118,571 in damages. At trial, Oswood asserted that Truss Works breached the Purchase Order by (1) failing to submit full, engineer-stamped and approved shop drawings, (2) improperly designing and failing to timely deliver trusses, and (3) failing to provide or design truss hangers as required under the Purchase Order. Testimony on these three topics comprised most of the trial.

¶12 The first issue, the submission of truss drawings, hinged on two conflicting provisions in the Purchase Order. Schedule A, Section 2(E) of the Purchase Order states: “All submittals, shop drawings, samples, and other submittal material must be transmitted through Contractor’s office for approval. No submittals shall be submitted directly to the Owner, Architect, Engineers, or Agents without written authorization from

Contractor.” The contract specifications for “Wood Trusses” referenced in the Purchase Order state conversely that the “Truss supplier shall submit shop drawings to the engineer for approval[.]”

Free access — add to your briefcase to read the full text and ask questions with AI

Truss Works v. Oswood Construction, 2022 MT 42, 504 P.3d 1116, 408 Mont. 27 (Mo. 2022).

2022 MT 42 (Truss Works v. Oswood Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Parenting of H.B.-S.
Montana Supreme Court, 2026
Faber v. Raty
2023 MT 227 (Montana Supreme Court, 2023)
Marriage of Hedstrom and Peters
2022 MT 140N (Montana Supreme Court, 2022)