Trunkline LNG Co. v. Federal Energy Regulatory Commission

921 F.2d 313, 287 U.S. App. D.C. 273
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 14, 1990
DocketNos. 89-1492, 89-1610
StatusPublished
Cited by1 cases

This text of 921 F.2d 313 (Trunkline LNG Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trunkline LNG Co. v. Federal Energy Regulatory Commission, 921 F.2d 313, 287 U.S. App. D.C. 273 (D.C. Cir. 1990).

Opinion

Opinion for the Court filed PER CURIAM.

PER CURIAM:

In these consolidated cases, petitioners seek review of different aspects of two orders issued by the Federal Energy Regulatory Commission (“FERC”). Petitioner Panhandle Customer Group — an assemblage of natural gas distribution companies — challenges FERC’s decision not to rule on the prudence of Trunkline LNG’s acceptance of an amendment to a contract for importation of liquified natural gas (“LNG”). The amendment escalated the price paid for the gas. We remand this issue to FERC for further consideration. Petitioner Trunkline LNG Company seeks review of FERC’s resolution of various accounting issues. We deny this petition.

I.

We have described the gas importation project involved in these cases in a previous encounter with this subject matter, see Association of Businesses Advocating Tariff Equity v. Hanzlik, 779 F.2d 697 (D.C.Cir.1985) (“ABATE”), and accordingly will limit our discussion of it here. In 1973, Trunkline agreed to import LNG from a state-owned Algerian gas company. It then began constructing a facility in Lake Charles, Louisiana at which to unload the LNG, to convert it back into a gas, to store it, and ultimately to transport it to its sole purchaser. The Federal Power Commission (“FPC”), the predecessor to FERC, approved the import arrangement as well as construction of the Lake Charles facility. 58 F.P.C. 726 (1977).

On August 7, 1981, Trunkline informed the Algerians that it was ready to receive gas shipments. The Algerians, in reply, claimed that construction problems at their facility prevented immediate delivery. Trunkline ultimately secured performance from the Algerians by agreeing to a contract amendment increasing the price it would pay for the imported gas (Amendment No. 1). The parties. further agreed that Amendment No. 1 would not go into effect until they obtained regulatory approval of the contract modification. In the interim, the Algerians agreed to begin deliveries of gas under the terms of the original agreement. The first shipment arrived at the Lake Charles facility on September 25, 1982.

After Trunkline announced that it would commence deliveries of gas, distributors asked the Economic Regulatory Administration (“ERA”) and FERC to suspend or revoke Trunkline’s import authorization. The price of Algerian gas had risen dramatically since the mid-1970’s, and the distributors wished to slip their obligation to purchase the Algerian gas from Trunkline. Trunkline subsequently filed applications with ERA and FERC for approval of Amendment No. 1. Both agencies declined to suspend or revoke Trunkline’s import authorization. See ABATE, 779 F.2d at 699. While they were considering Amendment No. 1, however, Trunkline suspended deliveries from Algeria in December, 1983 under the force majeure clause of the contract because of the unmarketability of the gas. This caused FERC to transfer Trunk-line’s application to ERA, which in turn refused to review Amendment No. 1 because it considered the question to have [277]*277been mooted by the suspension of the parties’ contractual arrangement. See id. at 699-700. We affirmed this determination by ERA. See id. at 702.

The issues raised in this appeal stem from three separate matters which FERC ultimately consolidated for resolution. First, natural gas customers alleged (in the context of an application for a rate increase filed by Trunkline before it suspended imports) that Trunkline’s acceptance of Amendment No. 1 was imprudent. Second, the FERC staff conducted an audit of the cost of constructing the Lake Charles facility and proposed correcting entries that reduced Trunkline’s rate base. Trunkline objected to several of these correcting entries. Third, the FERC staff contended that certain shipping payments made by Trunkline to Lachmar Shipping, a 40 percent affiliate of Trunkline, were not prudent and therefore should not be part of the rate base. FERC ordered a hearing on these matters.

The AU ruled in Trunkline’s favor on the prudence of accepting Amendment No. 1, on many (but not all) of the correcting entries, and on the shipping costs. 38 FERC ¶ 63,022 (Feb. 17, 1987) (“AU Opinion ”). On review, FERC declined to exercise jurisdiction over the issue of the prudence of Amendment No. 1 and ruled against Trunkline on all of the correcting entries and on the shipping costs. 45 FERC IT 61,256 (Nov. 22, 1988). FERC denied all requests for reconsideration. 48 FERC ¶ 61,182 (Aug. 2, 1989) (“Reconsideration Order”). Panhandle and Trunk-line have petitioned for review of these FERC orders.

II.

Panhandle challenges FERC’s decision that it does not have jurisdiction to assess the prudence of Amendment No. 1. FERC now agrees that its rationale for its finding that it lacked jurisdiction was erroneous and asks us to remand the prudence issue to it for further consideration. Trunkline nevertheless contends, on grounds different from those relied on below by FERC, that FERC has no jurisdiction over this issue and that a remand is consequently inappropriate. We believe that FERC should have the first word concerning its jurisdiction and accordingly grant its request for a remand.

As we have recently explained in detail, jurisdiction over the regulation of imported natural gas is controlled by the Secretary of Energy, who is free to delegate responsibilities in this area to FERC, to ERA, or to other officers or employees of the Department of Energy. See TransCanada Pipelines Ltd. v. FERC, 878 F.2d 401, 405-06 (D.C.Cir.1989). In guidelines issued in 1984, the Secretary granted ERA the authority under § 3 of the Natural Gas Act to determine whether to permit importation of natural gas as consistent with the public interest and FERC the authority under §§ 4, 5, and 7 of the Act to regulate the rates charged for imported gas. See id. at 405. The guidelines, however, limit FERC’s ratemaking jurisdiction to regulation “consistent[ ] with the determinations made by the [ERA] Administrator and the policy considerations reflected in the [ERA] authorization.” See id. (quotation omitted).1

Trunkline’s principal argument focuses on this limitation. It contends that ERA already implicitly determined the prudence of Amendment No. 1 by refusing to revoke Trunkline’s import authorization and that any FERC reevaluation of the matter would be inconsistent with that determination and consequently beyond FERC’s jurisdiction.

In our view, Trunkline has presented nothing that would justify departure from the well-settled rule that agencies are generally to be given the first word in determining whether a matter falls within their jurisdiction, see, e.g., Federal Power Comm’n v. Louisiana Power & Light Co., 406 U.S. 621, 647, 92 S.Ct. 1827, 1842, 32 L.Ed.2d 369 (1972); Myers v. Bethlehem [278]*278Shipbuilding Corp., 303 U.S. 41, 50-51, 58 S.Ct. 459, 463-464, 82 L.Ed. 638 (1938). True, in TransCanada,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
921 F.2d 313, 287 U.S. App. D.C. 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trunkline-lng-co-v-federal-energy-regulatory-commission-cadc-1990.