True North Construction Group, Inc. v. D6 Structural Group, LLC

CourtCourt of Appeals of Georgia
DecidedFebruary 13, 2026
DocketA25A1967
StatusPublished

This text of True North Construction Group, Inc. v. D6 Structural Group, LLC (True North Construction Group, Inc. v. D6 Structural Group, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
True North Construction Group, Inc. v. D6 Structural Group, LLC, (Ga. Ct. App. 2026).

Opinion

FIFTH DIVISION MCFADDEN, P. J., HODGES and PIPKIN, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

February 13, 2026

In the Court of Appeals of Georgia A25A1967. TRUE NORTH CONSTRUCTION GROUP, INC. v. D6 STRUCTURAL GROUP, LLC.

HODGES, Judge.

Following a bench trial, True North Construction Group, Inc. (“True North”)

appeals from the trial court’s judgment finding D6 Structural Group, LLC (“D6”)

not liable for walking off a job that it had contracted with True North to complete.

The trial court determined that True North was liable for damages for breaching the

contract with D6, and only awarded nominal damages to True North for D6’s failure

to properly identify other subcontractors in its subcontractor affidavit , which resulted

in a lien being filed against the property. True North contends that the trial court

erred in its valuation of the contract, its calculation of damages, and in finding no

evidence of anything other than nominal damages resulting from the false affidavit that D6 submitted. For the following reasons, we affirm the trial court’s judgment on

liability, reverse the trial court’s order on the amount of damages, and remand the

case to the trial court with direction.

While we apply a de novo standard of review to any questions of law decided by the trial court, factual findings made after a bench trial shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of witnesses. Because the clearly erroneous test is in effect the same standard as the any evidence rule, appellate courts will not disturb fact findings of a trial court if there is any evidence to sustain them.

Memar v. Jebraeilli, 303 Ga. App. 557, 558 (694 SE2d 172) (2010) (citation omitted).

So viewed, the following facts are supported by the record.

True North was the general contractor for a project to build a 160-unit senior

living facility, and subcontracted with D6 to do the framing on the project. While D6

originally sent True North a higher bid, True North encouraged D6 to come down to

the round number of $2.3 million. D6 negotiated with a lumber supplier, Shelter

Products, for the costs of materials to get its bid down to that amount. D6 then

contracted with Shelter Products to pay for all of the materials on the project, with the

locked-in price contingent on D6 taking delivery of the materials by May 1, 2017. If D6

2 failed to take delivery of the materials by that date, it would be subject to cancellation

of the contract or monetary penalties.

Because of delays, True North did not allow D6 to begin work on the site or

take delivery of the materials until October of 2017; for example, there was a delay

because the slabs were not completed timely. None of the delays, however, were

caused by D6. Since D6 did not take delivery of the material as required by the

contract, D6 was liable to Shelter Products for $120,000 in penalties. D6 met with the

project manager and other officials from True North to discuss the consequential

price increases, and D6 and True North agreed to split the extra costs. Additionally,

in order to control the cost, True North agreed to pay Shelter Products directly for the

materials. Because of the increase in material costs, and additional expenses the

project required, the total value of the contract increased by more than $94,552.50,

for a total contract value of $2,394,552.50. 1

1 Both True North and D6 contend that the trial court’s valuation of the entire contract, after incorporating the value of the change orders, is incorrect by approximately $300. The allegedly incorrect total was the product of the trial court relying on a document prepared by True North, which asserted the value of the change orders was $94,552.50. Because the document the trial court relied on is in the record, we will continue to use the valuation employed by the trial court. Memar, 303 Ga. App. at 558. 3 True North paid Shelter Products directly for the materials, worth

$1,168,940.61. For the remainder of the contract, True North paid D6 for its labor,

subject to retainage. Retainage under the contract allowed True North to hold back

ten percent of the money due to D6 to ensure the work was completed and issues were

resolved before the full amount was paid. After D6 was allowed to begin work, it

submitted bi-monthly pay applications for periodic progress payments for its labor. D6

submitted eight pay applications that True North paid, totaling $932,743.95, which

was the value of the work D6 had completed minus the ten percent retainage for its

labor. Despite having no issues with the work done by D6, on March 16, 2018, True

North determined it would not be making any further payments to D6 because it

believed that D6 was not entitled to any further payment under the contract. Instead,

True North told D6 that it would need to finish the job without any further payment.

D6 worked for another ten days on the project in the hope that the parties could work

out the payment issue. D6 was unsuccessful in resolving the dispute and walked off

the job site on March 26, 2018. At the time D6 walked off the job, its work was

roughly 90 percent complete.

4 Under the parties’ contract, D6 agreed “to continue to perform the [w]ork

despite the existence of disputes. The existence of a dispute shall not be grounds for

any failure to perform by [D6] nor limit the rights of [True North] to proceed, in good

faith, to remedy any default by [D6].” D6 and True North, however, also agreed that

D6 would not have to continue performance if timely payments were not made.

Specifically, the contract provided that

[D6] shall be paid bi-monthly progress payments on or before the 1st & 15th of each month for the value of work completed minus 10% for retainage. [True North] will make all payments for stored materials monthly directly to [Shelter Products]. No provision of this agreement shall serve to void [D6’s] entitlement to payment for properly performed work or suitably stored materials or to require [D6] to continue performance if timely payments are not made to [D6] for suitably performed work or stored materials or to void [D6’s] right to file a lien or claim on its behalf in the event that any payment to [D6] is not timely made.

After walking off the project, D6 sought to exercise its rights under the agreement and

filed a lien against True North.

True North subsequently contracted with others to finish the work, resulting

in $92,792.43 in additional labor charges. True North also spent $85,674.00 in bond

5 premiums because of the liens on the project. Seeking these expenses and other

damages, True North filed suit against D6 for breach of contract. D6 answered the

complaint and sought payment for the work it completed.2 The case proceeded to a

bench trial, where the trial court found that D6 did not breach the contract by walking

off the job as True North had failed to make timely payments that it owed. The trial

court set forth the following calculations:

Total contract value:

$2,394,552.50

Minus payments to Shelter Products:

$1,168,940.61

Equals contract value to D6:

$1,225,611.90

90 percent of contract value for the work completed:

$1,103,050.70

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Memar v. Jebraeilli
694 S.E.2d 172 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
True North Construction Group, Inc. v. D6 Structural Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/true-north-construction-group-inc-v-d6-structural-group-llc-gactapp-2026.