Trucking Specialists Inc v. Inland Lakes Landscaping Corp

CourtMichigan Court of Appeals
DecidedNovember 25, 2014
Docket316641
StatusUnpublished

This text of Trucking Specialists Inc v. Inland Lakes Landscaping Corp (Trucking Specialists Inc v. Inland Lakes Landscaping Corp) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trucking Specialists Inc v. Inland Lakes Landscaping Corp, (Mich. Ct. App. 2014).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

TRUCKING SPECIALISTS, INC. d/b/a TKMS, UNPUBLISHED LTD., and LOU’S TRANSPORT, INC., November 25, 2014

Plaintiffs-Appellants,

v No. 316641 Oakland Circuit Court INLAND LAKES LANDSCAPING LC No. 2012-127989-CK CORPORATION, ROGER CANTELON, and RLI INSURANCE COMPANY,

Defendants-Appellees.

Before: HOEKSTRA, P.J., and WILDER and FORT HOOD, JJ.

PER CURIAM.

Plaintiffs appeal as of right from the circuit court’s order granting defendants’ motion for summary disposition under MCR 2.116(C)(10) (no genuine issue of material fact). We affirm.

I

This case arises out of the parties’ conflicting interpretations of a contract to haul and dispose of sediment dredged from Quarton Lake in Birmingham, Michigan. In 2011, defendant Inland Lakes Landscaping Corporation (“Inland”) entered into a contract with the City of Birmingham (the “Main Contract”) to haul and dispose of sediment dredged from Quarton Lake. Inland entered into a subcontract with plaintiff Lou’s Transport, Inc. (“Lou’s”) to haul and dispose of the dredged sediment at a price of $17.50 per cubic yard, and plaintiff Trucking Specialists, Inc. d/b/a TKMS, Ltd. (“TKMS”) provided the trucking services for Lou’s. Defendant Roger Cantelon personally guaranteed payment to TKMS through an individual personal guaranty, and defendant RLI Insurance Company was the surety under a payment bond.

Regarding payment for “[t]he proposed dredging,” § 36 of the Main Contract provided as follows: “Payment shall be made by cubic yards removed with the quantity to be determined by a post dredging survey of the cross sections in the plans, on-site inspections, and haul/disposal tickets. It is assumed that dredging materials are 50% water by volume.” Regarding payment for “trucking dewatered dredge spoils to a . . . landfill and disposal in said landfill,” § 37 of the Main Contract provided that “[t]he cubic yard price paid will be based on the amount of material transported, not number of truck yards. This will be determined by on-site inspections and load tickets.” The subcontract incorporated the terms of the Main Contract, and Inland agreed to pay -1- “$17.50 per Cubic Yard.” (Emphasis omitted.) The subcontract further provided that “[p]ayment will be made according to the actual Cubic Yards of Material that are disposed of.” (Emphasis omitted.)

In 2012, between April 2 and 11, plaintiffs hauled away 43 truckloads of material. In determining plaintiffs’ pay, Inland calculated the cubic yards of the material hauled by multiplying its weight by its density. According to Inland, weight tickets showed that plaintiffs hauled material weighing a total of 1,138.8 tons. In determining the density of the material, Inland relied on a soil density test, performed on April 2, 2012, by engineering consultants as the dredged material was being placed into the trucks. The engineers’ report explained that the test “was accomplished by placing the soils in one of [the engineers’] standard compaction molds, and providing a small amount of mechanical compaction to simulate a backhoe dumping the materials into a truck box.” As a result, the engineers estimated that the dredged material had a low-end volume of 0.919 cubic yards. Thus, Inland determined that plaintiffs hauled a total of 1,047 cubic yards of material (1,138.8 tons x 0.919 cubic yards per ton, rounded up), and paid them at the contractual rate of $17.50 per cubic yard for a total of $18,322.50.

Plaintiffs claimed that each of the 43 truckloads contained 40 cubic yards of material, as evidenced by TKMS’s invoices and load and time tickets, as well as weight tickets from Veolia Environmental Services, the disposal facility. Accordingly, plaintiffs claimed that they were entitled to payment for 1,720 cubic yards of material (43 x 40), plus a 3% fuel surcharge, for a total of $30,525.70. Plaintiffs filed their complaint, alleging that they were entitled to payment as a result of a breach of contract, a violation of the Michigan Builders Trust Fund Act, MCL 570.151 et seq., a breach of the personal guaranty, and the payment bond.

Defendants moved for summary disposition under MCR 2.116(C)(10) on plaintiffs’ claims for breach of contract, breach of the personal guaranty, and payment under the bond, and for summary disposition under MCR 2.116(C)(8) on plaintiffs’ claim under the Builders Trust Fund Act. Plaintiffs agreed that their claim under the Builders Trust Fund Act should be dismissed. Otherwise, plaintiffs argued that they were entitled to summary disposition under MCR 2.116(I)(2) because the invoices, load and time tickets, and weight tickets showed that they hauled 43 truckloads of material at 40 cubic yards each, for a total of 1,720 cubic yards. Further, plaintiffs argued that defendants’ calculation of cubic yardage based on the post-dredging survey was impermissible under the Main Contract. According to plaintiffs, a post-dredging survey could be used to calculate the payment owed for dredging the lake under § 36 of the Main Contract, but payment for hauling and disposing of dredged material under § 37 was to be determined solely by on-site inspections and load tickets.

In their reply brief, defendants argued that the load and time tickets relied upon by plaintiffs were signed by defendants’ independent contractors, who were not authorized to act on behalf of defendants. Further, defendants argued that the soil density testing was an on-site inspection because it tested the material on-site before it was loaded into plaintiffs’ trucks. Defendants also argued that the weight tickets plaintiffs attached to their response brief were not actually weight tickets, and only established the origin, truck size, and time and date for each of

-2- the loads. Defendants asserted that the weight tickets attached to its reply brief measured the actual weight of the truck loads, specifying the difference between the gross weight of the truck when fully loaded and the tare1 weight upon being emptied, and demonstrated that plaintiffs hauled a total net weight of 1,138.8 tons. The weight tickets also showed that that truck loads each carried varying degrees of weight, ranging from roughly 45,000 to 69,000 pounds.

The circuit court granted defendants’ motion following a hearing, holding that it agreed with defendants’ interpretation of the contracts. Specifically, the circuit court found that the calculation method through which plaintiffs sought payment, a calculation of the amount of material hauled based on the number of truck yards, was expressly prohibited by the Main Contract, and that the soil density test, from which defendants calculated payment, constituted an on-site inspection as permitted under § 37 of the Main Contract.

II

This Court reviews de novo matters of contract interpretation and a decision to grant or deny a motion for summary disposition. Klapp v United Ins Group Agency, 468 Mich 459, 463; 663 NW2d 447 (2003). Summary disposition under MCR 2.116(C)(10) is appropriate when, considering “the evidence and all legitimate inferences in the light most favorable to the nonmoving party,” Coblentz v Novi, 475 Mich 558, 567-568; 719 NW2d 73 (2006), “there is no genuine issue as to any material fact, and the moving party is entitled to judgment or partial judgment as a matter of law,” MCR 2.116(C)(10). In presenting a motion for summary disposition, the moving party has the initial burden of supporting its position with evidence, Smith v Globe Life Ins Co, 460 Mich 446, 455; 597 NW2d 28 (1999), and then the burden shifts to the opposing party to establish a genuine issue of material fact, id.; MCR 2.116(G)(4).

“The primary goal in the construction or interpretation of any contract is to honor the intent of the parties.” Klapp, 468 Mich at 473 (citation and quotation marks omitted). “[U]nambiguous contracts .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re EGBERT R SMITH TRUST
745 N.W.2d 754 (Michigan Supreme Court, 2008)
Coblentz v. City of Novi
719 N.W.2d 73 (Michigan Supreme Court, 2006)
Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
Smith v. Globe Life Insurance
597 N.W.2d 28 (Michigan Supreme Court, 1999)
Grinnell Bros. v. Brown
171 N.W. 399 (Michigan Supreme Court, 1919)
Bronson Methodist Hospital v. Michigan Assigned Claims Facility
298 Mich. App. 192 (Michigan Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Trucking Specialists Inc v. Inland Lakes Landscaping Corp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trucking-specialists-inc-v-inland-lakes-landscaping-corp-michctapp-2014.