Triple Cities Construction Co. v. State

150 Misc. 2d 654, 569 N.Y.S.2d 563, 1991 N.Y. Misc. LEXIS 168
CourtNew York Court of Claims
DecidedApril 4, 1991
DocketClaim No. 67682
StatusPublished

This text of 150 Misc. 2d 654 (Triple Cities Construction Co. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triple Cities Construction Co. v. State, 150 Misc. 2d 654, 569 N.Y.S.2d 563, 1991 N.Y. Misc. LEXIS 168 (N.Y. Super. Ct. 1991).

Opinion

OPINION OF THE COURT

Louis C. Benza, J.

By order to show cause, defendant has moved for summary judgment dismissing this claim pursuant to CPLR 3212 (b) on the grounds that claimant failed to comply with section 145 of the State Finance Law.

State Finance Law § 145 provides that if a contractor accepts final payment under the contract, his claim will be waived unless (1) he serves a verified statement of claim upon the public body concerned (here, the New York State Department of Transportation [hereinafter DOT]) not later than 40 days after the mailing of the final payment, and (2) he institutes an action within six months of the mailing of the final payment.

Paragraph 5 of the claim asserts that a verified statement of claim was served upon DOT on September 21, 1982, "within forty (40) days after the mailing of the final payment by the State to claim [sic], which occurred on August 13, 1982”. The claim was personally served upon the Attorney-General and filed with the court on February 16, 1983. Thus, the State argues, the claim was filed more than six months after mailing of the final payment check and is, therefore, untimely pursuant to State Finance Law § 145. The court takes judicial notice of the fact that February 13, 1983 was a Sunday, and thus, claimant had until Monday, February 14, to file and timely serve its claim if the check mailed on August 13, 1982 indeed represented final payment.

In opposition to defendant’s motion, claimant’s president, Louis D’Angelo, Jr., submitted an affidavit in which he states that the claim erroneously sets forth that the final payment check was mailed on August 13, 1982 and was received by [656]*656claimant on August 16, 1982. Mr. D’Angelo asserts claimant received two checks subsequent to August 13, 1982, and thus the August 13 check was not the final payment check. Mr. D’Angelo avers that a $2,500 check was received from the State on August 27, 1982 as a result of completing contract item "Planting Obligations”. This sum claimant placed on deposit with the State pursuant to the terms of a completion contract. The return of said deposit was mandated upon the successful completion of the work.

Mr. D’Angelo further avers that he received a check on March 21, 1983 in the sum of $1,377.89, which represents interest on the final payment which had been mailed on August 13, 1982. Mr. D’Angelo states his belief that this check was mailed on March 18, 1983. It is Mr. D’Angelo’s belief that this check represents the final payment by the State to claimant. Thus, says Mr. D’Angelo, the claim served and filed February 16, 1983 was timely commenced as it was served and filed within six months of the mailing of the final payment check.

State Finance Law § 139 (3) provides that in order to obtain the total amount of estimated payments, a contractor, in lieu of having a retainage deducted from his contract payments, may deposit sufficient securities with the Comptroller or, if so directed by the Comptroller, with a bank or trust company which has entered into an agreement with the Comptroller and which will act as agent for the State.

In his supplemental affidavit, Mr. D’Angelo states that pursuant to State Finance Law § 139, claimant exercised this option and provided securities to be held by the State Bank of Albany as agent for the State, said items to be held in lieu of retainage.

In his affidavit, Mr. D’Angelo also stated his belief that said securities were returned to claimant after August 13, 1982, and that this payment may have constituted final payment under the contract pursuant to this court’s decision in Commander Elec. v State of New York (Ct Cl, Dec. 6, 1990, Benza, J., claim No. 79314, mot No. M-43003). Neither Mr. D’Angelo nor claimant’s counsel were able to provide the date said funds were mailed to claimant by the bank.

The issues presented for the court’s determination are: (1) whether the return of moneys deposited with the State pursuant to a completion contract is considered part of the final payment; (2) whether the payment of interest on the late [657]*657payment of final payment pursuant to section 38 (7) (g) of the Highway Law is considered part of that final payment for determining when the six-month Statute of Limitations under State Finance Law § 145 starts to run; and (3) whether the return of securities deposited pursuant to State Finance Law § 139 (3), in lieu of retainage, with a bank acting as agent for the State is considered part of the "final payment” for determining when the six-month period of limitations under State Finance Law § 145 starts to run.

I. MONEYS DEPOSITED PURSUANT TO A COMPLETION CONTRACT

As this court stated in Commander Elec. v State of New York (supra), section 109-12 of the Standard Specifications to the contract does not specifically define "final payment” but does define "final estimate” as follows: "The Commissioner will approve a final estimate for final payment based on the final agreement as prepared and approved by the Regional Director, less previous payments and any and all deductions authorized to be made by the Commissioner under the contract. Payment pursuant to such final estimate less any deductions authorized to be made by the Comptroller under the contract shall constitute the final payment and shall be made by the Comptroller.”

Thus, pursuant to claimant’s contract, the payment made pursuant to the final estimate constitutes final payment.

The State asserts, and it is not controverted by claimant, that the $2,500 check was the return of funds deposited pursuant to an uncompleted work agreement. Section 109-10 of the Standard Specifications provides as follows: "Whenever a contract shall in the judgment of the Commissioner of Transportation be substantially completed and in his judgment the withholding of the retained percentage would be an injustice to the Contractor, the Commissioner of Transportation may, provided the Regional Director certifies that the essential items in the contract have been completed in accordance with the terms of the contract and the provisions of Section 109-11, Final Agreement, direct the Regional Director to include in the final account such uncompleted items and pay therefor at the item prices in the contract upon the Contractor’s depositing with the Commissioner of Transportation a certified check drawn upon a legally incorporated bank or trust company equal to at least double the value of such [658]*658uncompleted work. The deposit may be used by the Commissioner of Transportation to complete the uncompleted portion of the contract and shall be returned to the Contractor if he completes the uncompleted portions with a specified number of working days after he has been notified to proceed with the work.” (Emphasis added.)

The court does not accept claimant’s counsel’s argument, presented in his supplemental affidavit in opposition that the specifications are contradictory. We find them clear and precise and, based on said finding, conclude that pursuant to claimant’s contract, the work to be completed under the uncompleted work agreement was considered completed work and was included in the final estimate and payment of August 13, 1982.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SNYDER CONSTR. CO., INC. v. State
420 N.E.2d 978 (New York Court of Appeals, 1981)
Triple Cities Construction Co. v. State
161 A.D.2d 868 (Appellate Division of the Supreme Court of New York, 1990)
Fowler Electric Co. v. State
144 Misc. 2d 110 (New York State Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
150 Misc. 2d 654, 569 N.Y.S.2d 563, 1991 N.Y. Misc. LEXIS 168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triple-cities-construction-co-v-state-nyclaimsct-1991.