Triple Cities Construction Co. v. Maryland Casualty Co.

4 N.Y.2d 443
CourtNew York Court of Appeals
DecidedJune 25, 1958
StatusPublished

This text of 4 N.Y.2d 443 (Triple Cities Construction Co. v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triple Cities Construction Co. v. Maryland Casualty Co., 4 N.Y.2d 443 (N.Y. 1958).

Opinions

Fuld, J.

The plaintiff, maintaining that defendant Maryland Casualty Company had lulled it into inactivity to induce it to continue settlement negotiations until its lien had expired, [446]*446asserted an estoppel against the defendant. The jury returned a verdict for the plaintiff, but the Appellate Division reversed the judgment and dismissed the complaint. We are called upon simply to determine whether sufficient evidence was presented to justify a finding of estoppel.

Dan-Bar Contracting Co., Inc., had an agreement, as general contractor, with the State of New York for the construction of certain public highways. The defendant had executed and delivered to the State of New York a bond guaranteeing Dan-Bar’s prompt payment of moneys due to persons supplying labor and materials in carrying out the contract. The plaintiff was such a subcontractor. In September of 1953, it filed a lien with the State Comptroller and the Department of Public Works for more than $60,000, the balance allegedly due from Dan-Bar. Such a lien, the Lien Law (§18) provides, remains valid and effective for six months unless an action is commenced to foreclose the lien within that time or an order is made by the court continuing and extending it.

Two weeks after filing the lien, actually worthless because of other liens and a prior assignment by Dan-Bar, far in excess of the amount due Dan-Bar from the State, plaintiff’s attorneys wrote to Maryland referring to its bond and informing it of Dan-Bar’s indebtedness. Some time later, the attorneys sent a letter to Dan-Bar, despatching a, copy to Maryland, advising of the sum due their client and <r0itheir intention, if payment was not made, to bring suit a,-^nst both Dan-Bar and Maryland. A reply, received on b^fAlf of Dan-Bar from its attorneys, suggested that there was a yhgjscrepancy ’ ’ in the amount said to be due, requested an itemi*Fstatement and expressed a willingness to “ discuss ” the mat'Hand make payment when final payment was received from themsate. Plaintiff’s counsel thereupon furnished Dan-Bar’s attonews with a copy of the lien showing computation of the amoiKt due. When, however, more than a month went by without aWord, the plaintiff brought this action against Dan-Bar on its contract and against Maryland on its undertaking.

The same attorneys who had written on behalf of Dan-Bar appeared for both defendants and, in a letter accompanying the answer filed on behalf of both, suggested a conference looking toward an “ amicable settlement”. A meeting, scheduled for [447]*447the following week, was put off at the request of defendants’ lawyers. When the conference was finally held, the attorney who appeared for the defendants, expressing a desire to settle the matter as promptly as possible, declared that the only problem, ‘ ‘ the only real controversy ’ ’, was over a relatively small item of excavation yardage and that, except for this, payment would be made “promptly.” Determination of the matter, this lawyer stated, depended upon consultation with an officer of Dan-Bar. Thereafter, when plaintiff’s attorney inquired concerning the delay, he was told either that the officer ‘1 had been away ’ ’ or that ‘ ‘ they had not as yet had an opportunity to examine the records at the state engineer’s office, but that they were going to do it shortly ’ ’.

However, nothing happened. Or, more precisely, nothing happened until plaintiff’s lien expired. Nine days after that occurred, defendants’ attorneys wrote, “with deep regret,” that they ‘ ‘ were unable to raise any funds ’ ’ and that, as Maryland had previously suggested, they would now make a motion to dismiss the complaint on the ground that, “ Once a lien was filed, a direct contract action was precluded ”, the only action maintainable being ‘1 a lien foreclosure ’ ’ suit. Their not making the motion to dismiss earlier, the attorneys expressly acknowledged, ‘ ‘ was not an oversight ’ 1

Thereupon, following its expressed plan, Maryland moved for judgment on the pleadings because of plaintiff’s failure to allege that it had perfected and foreclosed its lien, a condition precedent to suit on the bond (State Finance Law, § 137). The Appellate Division, granting the motion, dismissed the complaint with leave to the plaintiff to serve an amended complaint (285 App. Div. 299) and this court affirmed (309 N. Y. 665).

After obtaining a judgment against Dan-Bar for $52,920.33, plus interest and costs, which proved uncollectible, the plaintiff amended its complaint by alleging that Maryland had waived enforcement of the lien as a condition precedent to liability on its bond and that it was estopped from asserting such nonenforcement as a defense. Upon the trial, the court submitted the issues of waiver and of estoppel to the jury which returned a [448]*448verdict in favor of the plaintiff. The Appellate Division, however, reversed the judgment and dismissed the complaint, stating that there was 11 no basis in the record ’ ’ for a finding of either estoppel or waiver.

We do not agree. Although there may be some question as to whether there was adequate proof of waiver, there can be no doubt that the evidence adduced amply supported a finding that the defendant was estopped from asserting as a defense the plaintiff’s failure to foreclose its lien.

An estoppel, this court has said, “ rests upon the word or deed of one party upon which another rightfully relies and so relying changes his position to his injury. ’ ’ (Metropolitan Life Ins. Co. v. Childs Co., 230 N. Y. 285, 292; Lynn v. Lynn, 302 N. Y. 193, 205.) Indeed, “ A party may not, even innocently, mislead an opponent and then claim the benefit of his deception. ’ ’ (Romano v. Metropolitan Life Ins. Co., 271 N. Y. 288, 293; see, also, Syracuse Light. Co. v. Maryland Cas. Co., 226 N. Y. 25, 36.) And, more to the point, it has been at least twice held, in actions against this very same defendant, that an estoppel may be predicated upon evidence that the defendant, by resort to settlement negotiations, intended “ to lull the plaintiff into inactivity,” to “induce it to continue negotiations until after the expiration of the * * * time within which an action” could be maintained. (See Syracuse Light. Co. v. Maryland Cas. Co., 226 N. Y. 25, 36, supra; Rego Bldg. Corp. v. Maryland Cas. Co., 151 Misc. 801, 803-805.)

The proof in the case before us unquestionably permitted the jury to find that the defendant had misled the plaintiff, that it had lulled it into inactivity and that it was thereby estopped from urging that the plaintiff had not perfected its lien. Concededly, Maryland knew that the plaintiff could not prevail if it failed to procure an order continuing its lien. Saying nothing of this, admittedly not through oversight, but deliberately, the defendant, through its attorneys, engaged in protracted settlement negotiations, in the course of which it informed the plaintiff and its lawyers that the only “ real controversy ”, the only “ real question ”, was “ over some excavation yardage ” and that, if “ the amount to be paid ” could be agreed upon, payment would be “promptly” made. And, following these assertions, one of defendant’s attorneys called plaintiff’s [449]*449counsel to say that he 1 ‘ had not as yet had an opportunity ’ ’ to check the figures, promising that he would do so and ‘‘ let [him] know further ”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Triple Cities Constr. Co. v. Dan-Bar Contracting Co., Inc.
128 N.E.2d 318 (New York Court of Appeals, 1955)
Romano v. Metropolitan Life Insurance
2 N.E.2d 661 (New York Court of Appeals, 1936)
Metropolitan Life Ins. Co. v. . Childs Co.
130 N.E. 295 (New York Court of Appeals, 1921)
Syracuse Lighting Co. v. . Maryland Casualty Co.
123 N.E. 723 (New York Court of Appeals, 1919)
Triple Cities Construction Co. v. Dan-Bar Contracting Co.
285 A.D. 299 (Appellate Division of the Supreme Court of New York, 1954)
Lynn v. Lynn
97 N.E.2d 748 (New York Court of Appeals, 1951)
Stein v. Palisi
125 N.E.2d 575 (New York Court of Appeals, 1955)
Rego Building Corp. v. Maryland Casualty Co.
151 Misc. 801 (City of New York Municipal Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
4 N.Y.2d 443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triple-cities-construction-co-v-maryland-casualty-co-ny-1958.