Trio Industries, Inc. v. Joseph E. Bennett Co.

193 F. Supp. 423, 1961 U.S. Dist. LEXIS 3332
District Court, D. Massachusetts·Decided April 18, 1961·No. Civ. A. No. 59-911·Published

Opinion

CAFFREY, District Judge.

This is a diversity action sounding in contract. The plaintiff is a corporation organized under the laws of the State of New York, and maintains a usual place of business in. Bridgeport, Connecticut. The defendant is a corporation organized under the laws of the Commonwealth of Massachusetts, and maintains a usual place of business in Brookline, Massachusetts.

Plaintiff’s complaint contains two causes of action. The first is based on a contract entered into between the pai’ties on January 29, 1957, under which plaintiff, as a subcontractor, for a consideration' of $34,000, undertook to do certain work, consisting of furnishing the aluminum curtain wall of a building for which defendant was the general contractor under a contract between defendant and the U. S. Army Corps of Engineers. A “curtain wall” is a non-load-bearing wall that closes voids in the exterior of a building.

In its first cause of action, plaintiff alleges complete performance by it of all its obligations under the contract in accordance with the applicable plans and specifications, and seeks recovery of $4124.66. In its second cause of action, plaintiff claims that defendant breached the contract, first by failing to provide plaintiff with certain detail drawings of masonry, stone, and steel work necessary in order for plaintiff to prepare its plans and drawings, and secondly, by failing to supply plaintiff with “prepared openings” in the building at the time plaintiff was [424]*424required tó commence its performance of the contract, which failure resulted in plaintiff’s being obliged to incur substantial additional expense in order to complete its performance as required under the contract. In its second cause of action, as amended, plaintiff seeks recovery of $7,401.50.

The defendant, in its answer, denies a breach of the contract; alleges that the $10,000 jurisdictional amount is not involved herein; and counterclaims for $18,770 by reason of alleged breach of contract on the part of plaintiff. Defendant says that plaintiff failed to have its plans approved on time and also failed to begin or to complete its work on time.

The case was tried to the Court without a jury and at the close of all the evidence the defendant filed a motion to dismiss on the basis of lack of the jurisdictional amount and, also, a motion for judgment on the second cause of action on the grounds of failure of proof. Both motions were denied.

I find that Joseph E. Bennett Co., Inc. entered into a contract on November 19, 1956, with the U. S. Army Corps of Engineers, for the construction of the Administration Building, St. Lawrence Seaway, Massena, New York. This con-' tract bore the Identification DA-30-023CIV-ENG-57-33 and called for payment of $708,200 to the Bennett Company. It provided for the work to be completed not more than 400 calendar days from receipt of notice to proceed. The notice to proceed was received by the defendant on November 28, 1956. Thereafter, the defendant entered into negotiations with the plaintiff, Trio Industries, Inc., which culminated in the execution of a contract between defendant and plaintiff on January 29,1957. This contract obligated the plaintiff, as subcontractor, to furnish all -labor, materials, equipment, and supervision necessary to erect the aluminum curtain wall system, aluminum sills, two aluminum plaques, and aluminum letters, for the Administration Building, in accordance with the prime contract and plans and specifications thereto. Plaintiff was obligated, also, to furnish shop drawings, samples, and certificates, and to secure necessary approvals thereof from the Corps of Engineers.

The contract required that shop drawings setting out in detail the exact dimensions of the aluminum curtain wall would be prepared by plaintiff. The manager of plaintiff’s Erection Department, Edward L. Cairns, a qualified engineer, testified that the customary and usual practice in the building trade was for these aluminum shop drawings to be made by draftsmen employed by the aluminum subcontractor at a time subsequent to the delivery by the general contractor to the aluminum subcontractor of detailed drawings prepared by the masonry, stone, and steel subcontractors. After execution of the contract in the instant case, the first activities of the parties, spread over a period of some months, were concerned with the preparation and obtaining of approval of the Corps of Engineers of the shop drawings for the aluminum subcontract.

I find that the usual practice in the building trade is for the general contractor to receive the detailed shop drawings from the various subcontractors and for the general contractor then to obtain approval of the owner or the architect. I find that contrary to this usual practice, the defendant Bennett Company, the general contractor, required the plaintiff Trio to submit its proposed shop drawings directly to the Corps of Engineers for approval. I further find that the first plans submitted by plaintiff to the Corps of Engineers were not approved, due to inaccuracies relating to masonry openings and entrance units, and I find that these inaccuracies were attributable to Bennett Company’s failure to supply Trio Industries with the detailed drawings relating to masonry and entrance units. I further find that the first notice plaintiff had that the usual practice was not to be followed in this case, was contained in a letter from defendant to plaintiff dated April 29, 1957. Thereafter, on May 2 and May 16, 1957, plaintiff submitted plans to the Corps of [425]*425Engineers for approval and by June 10, Plans 1, 2 and 3 were disapproved and Plans 4 and 5 were approved. Plans 1, 2 and 3 were resubmitted by plaintiff on June 19 to the Corps of Engineers and were finally approved on June 28, 1957. I find that the delay in obtaining approval of these plans was due to the failure of the Bennett Company to supply Trio Industries with shop drawings relating to masonry, steel, stone, and vestibule entrances. I further find that the late approval of the plans is not material to the delays in constructing the building and, in fact, the president of the Bennett Company admitted that the late plans did not result in any delay prior to the pouring of the concrete, which was completed on August 23, 1957.

Defendant, at the trial, attempted to demonstrate that plaintiff was responsible for defendant’s failure to complete the building within the 400 day period after receipt of the notice to proceed, i. e., by January 4, 1958. The building was accepted by the Government on March 3, 1958. Defendant’s progress chart called for the curtain wall erection to begin on June 15, 1957 and to be finished on August 15, 1957. I find that the building was not ready on June 15,1957 to receive the aluminum curtain wall. In fact, the Corps of Engineers notified defendant that as of July 1, 1957 the building was only 17 per cent completed whereas it should have been 35 per cent completed at that time. Plaintiff was in no way responsible for this lag as of July 1, 1957, which was characterized as “substantial” by the Government’s chief of construction (called as a witness by defendant), and I so find, having in mind that some seven months after receiving the notice to proceed the defendant was about 50 per cent behind schedule. I find that the Bennett Company took the position that the job was ready to receive plaintiff’s work on September 20, 1957 (Ex. 30), some three months after the starting date for plaintiff’s work set forth in defendant’s progress chart.

Free access — add to your briefcase to read the full text and ask questions with AI

Trio Industries, Inc. v. Joseph E. Bennett Co., 193 F. Supp. 423, 1961 U.S. Dist. LEXIS 3332 (D. Mass. 1961).

193 F. Supp. 423 (Trio Industries, Inc. v. Joseph E. Bennett Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.