Trinkle v. Commonwealth

196 S.E. 652, 170 Va. 429, 1938 Va. LEXIS 200
CourtSupreme Court of Virginia
DecidedApril 28, 1938
StatusPublished
Cited by3 cases

This text of 196 S.E. 652 (Trinkle v. Commonwealth) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinkle v. Commonwealth, 196 S.E. 652, 170 Va. 429, 1938 Va. LEXIS 200 (Va. 1938).

Opinion

Holt, J.,

delivered the opinion of the court.

On October 5, 1932, Jim Frank entered into a contract with the Commonwealth of Virginia, acting through [432]*432its Commissioner of Highways, H. G. Shirley, under which he undertook to construct, for $14,641.15,1.3 miles of gravel road in Russell county, designated as project No. F-661CB-12. That contract he sublet in October, 1932, to J. .E. Trinkle for $1,000. The rules and regulations of the Highway Department forbid subleases of highway contracts, but the trial court, in order to prevent delay, permitted this case to be heard upon its merits. In doing this, it has very properly charged Trinkle, the plaintiff, with all knowledge which could be properly charged against the contractor, Frank. A jury was empaneled but was afterwards discharged by consent and the entire matter submitted to the court. Plaintiff’s major claim is set forth in this letter:

“Clinchport, Ya.
“Dec. 1, 1932.
“Mr. W. W. McCleavy, Dist. Mngr.,
“Bristol, Va.
“Dear Sir:—
“I have been informed that the Gravel for project f661 CB Russell County will come for Gravel pit on the property of Tigner’s approximately two and one half miles from the road under construction.
“When this project was let to contract the engineer was unable to to give any information concerning the location of the Gravel pit for this project other than it would be along the right of way for this project and would not have to be hauled from other locality.
“Please take this up with the State and arrange for the payment of extra price for hauling this gravel from this Gravel pit now under consideration. You realize it will cost me thirty cents more per cubic yard more than the price bid on this gravel if I have to haul it that distance, and will appreciate you looking into this matter and arrange for the payment of the extra amount per Cu yard for hauling this gravel to this project.
“Yours Very Truly,
“Jim Frank.”

[433]*433To that letter the district engineer replied on December 5th, saying:

“I note that you state when you looked over this project that you were advised that the gravel would be along the right of way of this project. I am inclined to believe that there is some misunderstanding in regard to this for there are no indications that the gravel could be had along the right of way. If there had been any question in your mind as to the location from which this gravel was to be secured the time to have taken this matter up would have been prior to bidding on the work. You have been doing work for the State long enough to know that it is impossible to change contract prices after the contract has been signed, up, and the time to get matters of this kind straightened out is prior to bidding on the work.”

This gravel pit was farther away than Frank thought it was.

The contract itself contains a statement of the items which went to make up the contract price of $14,641.15. In it this appears: “4,268 cu. yds. gravel @ fifty cents per cu. yd. 50c $2,134.00.” Plaintiff’s claim now is for 4,390-43 cubic yards of gravel at $1.32 per cubic yard, aggregating $5,795.37. In paragraph six of his petition, this appears:

“Said officers and agents of the Department of Highways did, before such overhaul work was performed, agree and promise to pay your petitioner a reasonable amount, to-wit, an amount of eighty-two cents per cubic yard, for such overhaul work over and above the price stated in said proposal.”

In a book of the Highway Department entitled “Specifications,” which went into effect on January 1, 1931, appears this statement:

“(c) All gravel from local pits shall be placed as directed by the Engineer within the free haul of one-half (%) mile haul, and an allowance of one (1) cent per cubic yard per one hundred (100) feet will be made for overhaul in excess of one-half (*/£) mile.

[434]*434“(d) No overhaul will be allowed on gravel, other than that secured from local pits.”

These specifications the Highway Department has changed from time to time as it had a right to do. Some of them appear upon a printed sheet which went into effect January 1, 1932, and which was mailed to contractors of record, including Frank. Among those changes is this:

“Section 11, page 84, paragraph 4d:

“Shall read as follows: ‘No overhaul will be allowed on gravel.’ ”

Not only was this sheet mailed to Frank, but he tells us that he knew about the change. This knowledge is imputed to Trinkle, who was, as we have seen, not a subcontractor at all but was merely doing that work for Frank which Frank had contracted to do.

The trial judge has filed in the record this memorandum of his judgment, which we adopt:

“The petition in this cause shows that on the 5th day of October, 1932, one Jim Frank of Clinchport, Virginia, was awarded a contract by the Highway Commission for the construction of 1.3 miles of highway, designated as project No. F-661C-B-2; under plans and specifications prepared by the Highway Department, for the sum of $14,641.15. He was also the successful bidder in two other projects at, or about the same time and verbally assigned the project to J. E. Trinkle, a contractor, and on the 5th day of December, 1933, confirmed the assignment in writing and asserts that the Department of Highways had notice of, recognized and approved the sublease or assignment. This was denied by the defendant, and that proposition is sustained by the court for the reason that the rules and regulations of the Highway Department forbid any sublease, and throughout this case there was no such recognition by the Highway Department, and all transactions were with the original contractor, Jim Frank, and all checks were made payable to him, the petitioner being recognized as the agent or superintendent of the contractor. For the purpose of preventing delay and cost, the pleadings will be amended and [435]*435the cause continued in the name of Jim Frank, as all facts and law applicable to him apply likewise to his assignee.

“The principal amount involved in this petition is for overhaul, that is, the hauling of gravel from pits further from the project than one-half a mile, the plaintiff contending that he should be compensated on the basis of eighty-two (.82c) cents per cubic yard, for such overhaul and the defendant relying on what is asserted, as an amendment to Paragraph 4-D of Section 11, on page 84 of the specifications of January 1, 1931, as embodied in an errata sheet. A jury was empaneled to try the facts in the case and in its progress it became apparent that it was primarily a question of law and practically the entire amount involved was fixed, therefore, the jury was discharged and the cause was submitted on oral arguments and briefs. The primary question for consideration and determination, is:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DR. WILLIAM ES FLORY v. Com.
541 S.E.2d 915 (Supreme Court of Virginia, 2001)
Ragland v. Commonwealth
200 S.E. 601 (Supreme Court of Virginia, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
196 S.E. 652, 170 Va. 429, 1938 Va. LEXIS 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinkle-v-commonwealth-va-1938.