Trinity Universal Ins. Co. v. Coker

150 S.W.2d 640, 286 Ky. 261, 1941 Ky. LEXIS 233
Court of Appeals of Kentucky (pre-1976)·Decided April 25, 1941·Published

Opinion

Opinion op the Court by

Judge Tileord

—Affirming.

Appellant was surety on the bond of the White Construction Company which had contracted with the Department of Highways to construct a section of the Princeton-Wilson Warehouse Road. The bond guaranteed the performance of the contract and the full payment of the cláims of all persons supplying labor and materials in the prosecution of the work. The White Construction Company failed to pay numerous claims, and, to procure their liquidation, this action was insti *262 tilted by the appellant against the Construction Company, the Department of Highways, and the claimants. An attachment was procured against the funds due the Construction Company by the Highway Department, and among the claims listed as due and owing by the Construction Company was that of the appellee for $1,428.05. A joint and separate answer, counterclaim, and cross-petition was filed by the claimants, and thereafter the appellant filed an amended petition in which it withdrew its allegation that the Construction Company was indebted to the appellee. By amendments to the original answer, counterclaim, and cross petition, the appellee alleged 'that his total claim was $1,549.94, of which, $1,506.33 represented 25% of the net profits de- • rived by the Construction Company from the portion of the work completed by the appellee under his written contract, and $43.61 represented the amount due him for additional labor. In its reply the appellant traversed the allegations referred to and pleaded affirmatively that the services rendered by appellee to the Construction Company were not “labor” as defined by Kentucky Statute Section 2495-2, which provides that that term shall not be construed as including work done by any officer, superintendent, or stockholder of a corporation, and that, accordingly, the obligation of the Construction Company to appellee was not covered by the bond. The amount due by the Construction Company to appellee is not in dispute, and the material question presented for decision is whether appellee performed his work as a sub-contractor under the Construction Company or as a superintendent employed by it in that capacity.

Since it is argued by appellant’s counsel that appellee’s relationship to the Construction Company and the character of the work performed by hrm must be determined by the terms of the contract between appellee and the Construction Company unaided by parol testimony, it is necessary to set forth the terms of the contract in full:

“Whereas:
“Party of the second part agrees to supervise or oversee or to be responsible for the part of the above named project known as concrete work in accordance with Kentucky State specifications as follows: — ■

*263 1348.78 C. Y. Class A Concrete at.. .$14.00 per C. Y.

112260 lbs. of structural steel at... .04 per lb.

2275 yds. structural excavation at..

.60 per C. Y. 1251 L. P. Concrete Cross Drain

18’ at........................ 1.70 per L. P.

762 L. P. Concrete Cross Drain

24’ at........................ 2.60 per L. F.

“Party of the second part further agrees to complete the concrete work on this job by January, 1939, or at any time.

“It is further understood or agreed that party of the second part is to be subject to the orders or directions of the management of White Construction Company.

“Party of the second part agrees to keep th.e concrete work ahead or out of the way of the Roadway Excavation in order not to delay same.

“Party of the second part agrees to furnish whatever concrete tools or equipment he may have on hand, such as picks or shovels, etc.

“Party of the first part agrees to pay to the party of the second part $35.00 per week during the time the above concrete work is being done, and 25% of the profits on the same when the whole job is completed and the State takes it up.

“For failure to perform any part of the above contract party of the second part agrees to forfeit any rights to a share in the profits or any of his tools that may be on the job.

“Should it become necessary, for some unforeseen reason, for the party of the first part to discharge the party of the second part, all rights to share in the profits are forfeited.

“Party of the first part agrees to furnish the necessary equipment, to buy the materials and pay the labor.

“Witness our hands this 22nd day of June, 1938.

“White Construction Company “By A. W. Denhan, G-. M.

“J. Gu Coker.”

Free access — add to your briefcase to read the full text and ask questions with AI

Trinity Universal Ins. Co. v. Coker, 150 S.W.2d 640, 286 Ky. 261, 1941 Ky. LEXIS 233 (Ky. 1941).

150 S.W.2d 640 (Trinity Universal Ins. Co. v. Coker) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Blair & Franse Construction Co. v. Allen
65 S.W.2d 78 (Court of Appeals of Kentucky (pre-1976), 1933)
Deep v. Farmers' National Bank of Lebanon
57 S.W.2d 1002 (Court of Appeals of Kentucky (pre-1976), 1933)
Mitchell v. Southern Railway Co.
74 S.W. 216 (Court of Appeals of Kentucky, 1903)