Trinity Industries Leasing Company v. Lattimore Materials Corp.

CourtCourt of Appeals of Texas
DecidedJuly 29, 2024
Docket05-23-00512-CV
StatusPublished

This text of Trinity Industries Leasing Company v. Lattimore Materials Corp. (Trinity Industries Leasing Company v. Lattimore Materials Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity Industries Leasing Company v. Lattimore Materials Corp., (Tex. Ct. App. 2024).

Opinion

REVERSE and REMAND and Opinion Filed July 29, 2024

S In The Court of Appeals Fifth District of Texas at Dallas No. 05-23-00512-CV

TRINITY INDUSTRIES LEASING COMPANY, Appellant V. LATTIMORE MATERIALS CORP., Appellee

On Appeal from the 68th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-20-08632

MEMORANDUM OPINION Before Justices Reichek, Goldstein, and Garcia Opinion by Justice Garcia This case involves application of the statute of limitations to a railroad car

lease agreement requiring prompt reimbursement for damage to the railcars. A jury

found that Lattimore Materials Corp. (“Lattimore”) breached the lease (the “Lease”)

and awarded Trinity Industries Leasing Company (“Trinity”) $1.6 million for lost

rent and $9 million for failure to reimburse Trinity for corrosion damage to the

railcars. The trial court entered judgment for Trinity awarding lost rent, interest, and

attorney’s fees, but relied on a jury finding about when Trinity knew about the

corrosion to disregard the corrosion damage award. Trinity now argues the evidence is legally insufficient to establish the statute

of limitations bars the jury’s corrosion damage award. Alternatively, Trinity argues

the jury’s date finding cannot bar recovery because the Lease is a continuing

contract.

We conclude that corrosion damage, in and of itself, is not a breach of the

unambiguous terms of the Lease and therefore cannot trigger limitations on Trinity’s

claim for breach. Article 13, the Lease provision concerning corrosion damage, was

not breached until Lattimore refused to reimburse Trinity for loss, damage, or

expense that Trinity suffered as a consequence of railcar corrosion. The evidence

shows this did not occur until January 2020 when Latimore terminated the Lease

before the expiration of its term. Accordingly, Trinity’s June 2020 suit was not time

barred.

We therefore reverse the trial court’s judgment and render judgment that

Trinity is entitled to recover the $10,661,000 in actual damages found by the jury

for breach of articles 4 and 13 of the Lease, attorney’s fees, and pre- and post-

judgment interest on the actual damages. We remand the case to the trial court for

entry of judgment consistent with this opinion.

I. BACKGROUND

Trinity is a Texas-based company that manufactures, sells, and leases railcars.

Lattimore is an aggregates and ready-mix concrete producer that is a wholly owned

by Holcim Ltd., a Swiss multinational company.

–2– Trinity and Lattimore entered into the Lease in 2009. The Lease provided that

Trinity would lease railcars to Lattimore pursuant to “Riders,” which the parties

executed separately. Riders were executed and renewed in 2010, 2013, and 2018.

Article 4 of the Lease addresses the payment of rent, and obligates Lattimore

to pay monthly rent for each car from the date the car is delivered until the date of

its return. The applicable Rider specifies the amount due and number of cars. Article

10 describes the parties’ maintenance responsibilities and requires that Trinity

maintain the railcars in good condition “according to the Interchange Rules.” This

Article also prevents Lattimore from making repairs without Trinity’s prior written

consent, and requires Lattimore to promptly notify Trinity if a car is damaged or in

need of repair. Article 17 describes the condition in which the railcars were to be

returned to Trinity, stating: “At the expiration of the Lease term as provided in the

Riders, [Lattimore] shall, at its expense, return the cars to [Trinity] at the location

and to the agent selected by [Trinity] empty, clean and free from residue, and in the

same good condition as the cars were when delivered, except for normal wear and

tear.”

Article 13 concerns reimbursement for corrosion and other damage to the

railcars, and provides as follows:

Notwithstanding the exception for normal wear and tear in Article 17,[4] if during the term of any Rider any of the Cars or any components or appurtenances thereto shall be unduly or materially damaged, destroyed or depreciated in value or condition due to the corrosive or other damaging effect of any substance carried therein or thereon

–3– (whether or not such damage was foreseeable), [Lattimore] will reimburse [Trinity] promptly for such damage, loss or expense suffered by [Trinity] as a consequence thereof and no abatement of rent shall occur during the period in which repairs are performed.

Following execution of the Lease and Riders, Lattimore used the railcars

every day to haul limestone aggregate from its quarry in Stringtown, Oklahoma to

various ready-mix sites in Texas. Lattimore would wash the aggregate material and,

while still wet, load that material into the railcars. This commodity and wet-loading

process took its toll and caused considerable corrosion to Trinity’s railcars. As early

as 2013, the contractor retained by Trinity to service and maintain the railcars

observed corrosion and scaling of the side sheets, side scopes, and hinges on the

railcars. As Trinity’s expert explained, the corrosion “happen[ed] from the inside

out.” It was caused by “the rock and the water that was brought into contact with the

steel, and the amount of time that it was kept in contact with the steel.”

When two Riders expired in 2018, Lattimore continued to lease and use the

railcars on a month-to-month basis as the parties negotiated renewal Riders. During

these negotiations, Lattimore requested an inspection to assess liability if the Lease

were to end and Lattimore returned the cars. This led to a joint inspection of two

representative railcars in June 2018. The inspection revealed that the railcars were

“heavily corroded and in need of repair,” such that “all of [the] cars may require a

complete re-body.”

Trinity informed Lattimore that if all the railcars were in the same condition

when returned to Trinity, Lattimore would owe Trinity about $60,000 per railcar –4– ($13.5 million total). Lattimore did not dispute its obligation to reimburse Trinity

for the corrosion damage.

Because the railcars were still operable and capable of profitable use, Trinity

gave Lattimore the option of deferring the cost of repairing the railcars. Lattimore

did not pay for repairs and in December 2018, renewed the Riders through

November 2021. Lattimore agreed the renewal was “conclusive evidence of the fit

and suitable condition of such car or cars.”

Nonetheless, railcar corrosion continued to be a problem. At Lattimore’s

request, Trinity’s mobile railcar inspection team conducted an inspection, which

revealed “corrosion to the car bodies” was “beginning to present a bigger problem.”

The side sheets were tearing, and although the parties had “been able to patch these

to keep the cars in service . . . the inspection concluded that “the situation [would]

continue to get worse.”

Trinity met with Lattimore in January 2019 to review the findings from the

corrosion inspection. Trinity again told Lattimore that Lattimore’s loading of wet

limestone aggregate was the cause of the corrosion, and suggested that Lattimore

might avoid further damage by switching to a dry loading process in which limestone

is washed and allowed to drain and dry outside of the railcars before loading. Trinity

also reminded Lattimore that “[d]amage to the Railcars by loading is Lattimore’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Manufacturers Mutual Insurance Co. v. Schaefer
124 S.W.3d 154 (Texas Supreme Court, 2003)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
COC Services, Ltd. v. CompUSA, Inc.
150 S.W.3d 654 (Court of Appeals of Texas, 2004)
Mancorp, Inc. v. CULPEPPEER
802 S.W.2d 226 (Texas Supreme Court, 1990)
Garcia v. Insurance Co. of State of Pennsylvania
751 S.W.2d 857 (Texas Supreme Court, 1988)
Burroughs Wellcome Co. v. Crye
907 S.W.2d 497 (Texas Supreme Court, 1995)
Vincent v. Bank of America, N.A.
109 S.W.3d 856 (Court of Appeals of Texas, 2003)
Brown v. Zimmerman
160 S.W.3d 695 (Court of Appeals of Texas, 2005)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Cook Composites, Inc. v. Westlake Styrene Corp.
15 S.W.3d 124 (Court of Appeals of Texas, 2000)
City of Brownsville v. Alvarado
897 S.W.2d 750 (Texas Supreme Court, 1995)
Heritage Resources, Inc. v. NationsBank
939 S.W.2d 118 (Texas Supreme Court, 1997)
Spencer v. Eagle Star Insurance Co. of America
876 S.W.2d 154 (Texas Supreme Court, 1994)
Kachina Pipeline Company, Inc. v. Michael D. Lillis
471 S.W.3d 445 (Texas Supreme Court, 2015)
Bp America Production Company v. Red Deer Resources, Llc
526 S.W.3d 389 (Texas Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Trinity Industries Leasing Company v. Lattimore Materials Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-industries-leasing-company-v-lattimore-materials-corp-texapp-2024.