Trimble v. Fester

162 A. 337, 106 Pa. Super. 544, 1932 Pa. Super. LEXIS 284
CourtSuperior Court of Pennsylvania
DecidedMay 2, 1932
DocketAppeal 109
StatusPublished
Cited by2 cases

This text of 162 A. 337 (Trimble v. Fester) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trimble v. Fester, 162 A. 337, 106 Pa. Super. 544, 1932 Pa. Super. LEXIS 284 (Pa. Ct. App. 1932).

Opinion

Opinion by

Stadtfehd, J.,

This was an action of assumpsit brought by Harry L. Trimble against Joseph H. Fester, to recover the sum of $2,399.53, with interest from September 20, 1927, a balance alleged to be due on a written agreement under which plaintiff agreed to provide all the materials, and perform all the work for the alterations, additions and repairs to a store and apartment building and row of four houses in the Borough of Bracken-ridge. Under the agreement, copy of which is attached to plaintiff’s statement, and dated May 31,1927, plaintiff agreed to provide all the materials and perforin all of the work as shown on the drawings and specified in the specifications prepared by Stuart and Scheuneman, architects, and which are made part of the contract. The work was to be done under the direction of said architects and no alterations were to be made in the work, except upon the written order of the architects. The contract further provided that in case the contractor fail to prosecute the work with promptness and diligence, if the architects shall certify that such failure is sufficient ground for such action, the owner shall be at liberty to terminate the employment of the contractor and enter upon the premises for the purpose of completing the work included under the contract. The work was to be completed within ninety days from the time the contract was signed. The contractor agreed to pay the owner the sum of $20 per day for every day over ninety days to complete the work. The owner agreed to pay the contractor $10 per day for every day under ninety days time to complete the same.

The contract further provided, inter alia, that if the *547 contractor be delayed by tbe act, neglect or default of the owner, then the time fixed therein for completion shall be extended for a period equivalent to the time lost by reason of such cause, which extended period shall be determined and fixed by the architects, but no such allowance shall be made unless a claim is presented in writing to the architects within forty-eight hours of the occurrence of such delay. The total consideration to be paid to the contractor by the owner was the sum of $24,900.

In plaintiff’s statement, he avers that he proceeded to do the work in accordance with the terms and conditions of said agreement; that he received his orders for the same from the defendant, and not from the architects mentioned in said agreement. That from time to time defendant directed plaintiff to change the plans and specifications for said work, and on July 25, 1927, defendant authorized and directed plaintiff in writing to make certain changes and additions at a cost of $1,440.

Plaintiff further averred that by reason of the changes made in said work and the manner of constructing the same, the provision of the contract which required the work to be fully completed within ninety days was abrogated by mutual consent.

Plaintiff averred that he completed the alterations, additions and repairs described in the written agreement, and, in addition to the extra work authorized in writing on July 25,1927 at defendant’s special request, furnished certain other extra work amounting to the sum of $385.17. That the total amount due plaintiff by reason of the contract and the extra, work is the sum of $26,725.17, upon which defendant is entitled to a credit of $24,325.64, leaving a balance of $2,399.53, with interest thereon as aforesaid, due and owing.

To this statement of claim, defendant filed an affidavit of defense, denying that any changes were made in the written agreement, or that the clause concern *548 ing the completion of the work was abrogated by mutual consent, or that any other agreements were made or substituted for those contained in that portion of said contract. Defendant admitted the extra work set forth in plaintiff’s statement. Defendant denied the indebtedness set forth in said statement, and claimed that in addition to the credit given by plaintiff thereon, defendant paid to plaintiff on account of said contract, on May 31, 1928, the sum of $1,200.

Defendant further averred that plaintiff delayed completing the work until January 15,1928, a total of 229 days, and claimed due and owing to him by plaintiff the sum of $20 per day for each of 139 days, or a total of $2,780, and the further sum of $800 for the correction of defective work, and failure of plaintiff to perform the work in a workmanlike manner, and in accordance with the plans and specifications, leaving a balance due defendant in the sum of $2,380.47, for which he asked for a certificate in his favor.

A replication was filed by plaintiff averring that defendant had a tenant in a portion of the premises to be repaired, and that said tenant had a lease on said property for a period of two months, and refused to vacate, by reason of which plaintiff was unable to commence work until the property was vacated, and that defendant then and there advised plaintiff that he, defendant, would not hold plaintiff to that portion of the contract requiring the work to be done within a specified time. Plaintiff denied the credit of $1,200 claimed by defendant, and averred that of said sum, $1,099.36 was applied by plaintiff toward the Watson Boulevard job, due from defendant to plaintiff.

Plaintiff denied that he delayed completing the work until January 15,1928, and averred that the same was substantially completed during the early part of November, 1927, and that defendant occupied the premises by his tenants prior to completion. Plaintiff further *549 averred that the work was not completed with the time specified, for the reason that defendant was attempting to lease the premises to the United States government for post office purposes, and at defendant’s request, the work was held up until defendant could ascertain whether he could make such lease with the government.

Plaintiff denied the averments as to alleged defective work, and denied the alleged indebtedness on account of delay, and averred that defendant was attempting to sell the building, and advised plaintiff that he would pay the latter the amount of the indebtedness claimed by plaintiff when the building was sold.

On the issues thus framed the case went to trial before SwEAKinGEsr, J., and a jury, and resulted in a verdict in favor of plaintiff and against defendant in the sum of $2,399.53, being the amount of plaintiff’s claim without interest. A motion for new trial was made ex parte defendant, which was refused, and judgment entered on the verdict. Prom that judgment this appeal is taken by defendant.

There are three assignments of error. The first that the court erred in affirming plaintiff’s first point which was: “If you find from the evidence that the defendant, by words or conduct, indicated to the plaintiff that he would not hold him to the ninety days time fixed for completion in the contract, the defendant cannot now claim damages for any delay in the completion of the work.” The second is the overruling of defendant’s motion for a new trial; and the third, in entering judgment on the verdict.

Nowhere in the record doe's it appear that an exception was taken to the action of the court in the affirmance of plaintiff’s first point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glick v. Peoples-Pittsburgh Trust Co.
7 A.2d 364 (Superior Court of Pennsylvania, 1939)
KoEune v. State Bank of Schuylkill Haven
4 A.2d 234 (Superior Court of Pennsylvania, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
162 A. 337, 106 Pa. Super. 544, 1932 Pa. Super. LEXIS 284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trimble-v-fester-pasuperct-1932.