This text of Tribus, LLC v. Majestic Realty, LLC (Tribus, LLC v. Majestic Realty, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tribus, LLC v. Majestic Realty, LLC, (E.D. Mo. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION TRIBUS, LLC, ) ) Plaintiff, ) ) vs. ) Case No.: 4:20CV1643 HEA ) MAJESTIC REALTY, LLC, ) ) Defendant. )

OPINION, MEMORANDUM AND ORDER This matter is before the Court on Plaintiff’s Motion for Partial Summary Judgment as to Liability Only, [Doc. No. 10]. Defendant opposes the Motion. For the reasons set forth below, the Motion is denied. Facts and Background1 Plaintiff’s Petition, which was filed in the Circuit Court of St. Charles County, Missouri, alleges the following: Plaintiff and Defendant entered into a Development and Licensing Agreement on October 29, 2018 (“Agreement”) whereby Plaintiff was to provide Defendant with various intranet and extranet services including but not limited to the development of custom software including client relations software, and the hosting of

1 This recitation of the facts is for the purposes of this motion only and in no way relieves the parties of the necessary proof thereof in later proceedings. Defendant’s data. Per the Agreement, Defendant agreed to pay Plaintiff pursuant to the various payment schedules for the products and services that Plaintiff would be

providing Defendant. Plaintiff and Defendant agreed on various project costs and the hourly rates Defendant would pay Plaintiff for certain development, design, and project

management tasks. Defendant agreed to pay Plaintiff’s invoices when Plaintiff sent those invoices. In October of 2018, Plaintiff began its performance under the Agreement. Plaintiff alleges it has fully performed all its obligations under the Agreement.

Plaintiff further alleges Defendant has failed and refused to pay many of Plaintiff’s invoices for the services Plaintiff has provided pursuant to the Agreement. Specifically, despite making ten change orders to the Agreement

during September of 2019 that required Plaintiff to spend more than 100 hours of development, design, and project management time, Defendant failed and refused to pay for this work. Plaintiff, in a good faith effort to work with Defendant, continued to perform

all of its obligations under the Agreement and continually sought Defendant’s compliance with the terms of the Agreement, including but not limited to timely payment. By September 1, 2019, Defendant stopped making payments under the terms of the Agreement despite Plaintiff's continued performance.

Plaintiff claims it had fully performed all of its obligations under the Agreement and had satisfied any conditions precedent to Defendant’s obligation to pay Plaintiff, but Defendant, without justification, stopped making payments to

Plaintiff that conformed to the Agreement. Plaintiff continued to perform its obligations under the Agreement, including the provision of ongoing services such as hosting data for Defendant, despite Defendant’s failure to pay under the terms of the contract.

Summary Judgment Standard Pursuant to Federal Rule of Civil Procedure 56(a), a district court may grant a motion for summary judgment if all of the information before the court

demonstrates that “there is no genuine [dispute] as to any material fact and the moving party is entitled to judgment as a matter of law.” Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The burden is on the moving party. City of Mt. Pleasant, Iowa v. Associated Elec. Co-op. Inc., 838 F.2d

268, 273 (8th Cir. 1988). After the moving party discharges this burden, the nonmoving party must do more than show that there is some doubt as to the facts. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586, 106 S.Ct.

1348, 89 L.Ed.2d 538 (1986). Instead, the nonmoving party bears the burden of setting forth affirmative evidence and specific facts by affidavit and other evidence showing that there is a genuine dispute of a material fact. Anderson v. Liberty

Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Celotex, 477 U.S. at 324, 106 S.Ct. 2548. “A dispute about a material fact is ‘genuine’ only ‘if the evidence is such that a reasonable jury could return a verdict for the

nonmoving party.’” Herring v. Canada Life Assur. Co., 207 F.3d 1026, 1030 (8th Cir. 2000) (quoting Anderson, 477 U.S. at 248, 106 S.Ct. 2505). A party resisting summary judgment has the burden to designate the specific facts that create a triable controversy. See Crossley v. Georgia–Pacific Corp., 355 F.3d 1112, 1114

(8th Cir. 2004). In ruling on a motion for summary judgment, the court must review the facts in a light most favorable to the party opposing the motion and give that party the

benefit of any inferences that logically can be drawn from those facts. Matsushita, 475 U.S. at 587; Woods v. DaimlerChrysler Corp., 409 F.3d 984, 990 (8th Cir. 2005). The Court may not “weigh the evidence in the summary judgment record, decide credibility questions, or determine the truth of any factual issue.”

Kampouris v. St. Louis Symphony Soc., 210 F.3d 845, 847 (8th Cir. 2000). Discussion Plaintiff seeks partial summary judgment on liability arguing Defendant

breached the Agreement by failing to provide notice of a breach with an opportunity to cure any alleged breach under Section 8(a) of the Development and Licensing Agreement. Defendant argues it was not required to provide the

specified notice and cure because Plaintiff failed to comply with the specifications and timeline set forth in the Agreement, therefore, it was free to terminate upon notice as provided in Section 1 F of the Service Level Agreement.

Section 8(a) of the Development and Licensing Agreement provides, 8. Term and Termination. The term of this Agreement shall commence on the Effective Date and, unless earlier terminated, shall continue through the third anniversary of the date when the System is deployed and accepted in writing by CLIENT, as set forth in Exhibit D (the “Initial Term”). After the Initial Term, the Agreement shall renew automatically for two (2) year terms (each, a “Renewal Term”). Either Party may provide the other with written notice of nonrenewal at least ninety (90) days prior to the end of the Initial Term or any Renewal Term. This Agreement may be terminated as follows:

(a) Termination for Cause. If either Party breaches a material obligation under this Agreement and fails to cure such breach within sixty (60) days after receipt of written Notice from the other Party identifying such breach, then the non-breaching Party may terminate this Agreement by providing the breaching Party with prior written notice of termination. In addition, CLIENT shall have the right to terminate this Agreement immediately upon written notice to Tribus as set forth in Section 1 F of Exhibit A hereto.

Section 1 F of the Service Level Agreement provides, f. In the event that during any three successive calendar months Tribus fails to meet all of the availability and performance requirements set forth in clauses A through D above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Tribus, LLC v. Majestic Realty, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tribus-llc-v-majestic-realty-llc-moed-2021.