Tribble & Stephens Co. v. RGM Constructors, L.P.

CourtCourt of Appeals of Texas
DecidedOctober 28, 2004
Docket14-02-01062-CV
StatusPublished

This text of Tribble & Stephens Co. v. RGM Constructors, L.P. (Tribble & Stephens Co. v. RGM Constructors, L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tribble & Stephens Co. v. RGM Constructors, L.P., (Tex. Ct. App. 2004).

Opinion

Reversed and Remanded; Plurality and Concurring and Dissenting Opinions filed October 28, 2004

Reversed and Remanded; Plurality and Concurring and Dissenting Opinions filed October 28, 2004.

In The

Fourteenth Court of Appeals

____________

NO. 14-02-01062-CV

TRIBBLE & STEPHENS CO., Appellant

V.

RGM CONSTRUCTORS, L.P., Appellee

On Appeal from the County Civil Court at Law No. 3

Harris County, Texas

Trial Court Cause No. 713,187

C O N C U R R I N G   A N D   D I S S E N T I N G   O P I N I O N

I concur in the court=s disposition of the challenges asserted by appellant Tribble & Stephens Co. (AT&S@) to the trial court=s summary judgment in favor of appellee RGM Constructors, L.P. (ARGM@) on T&S=s claims under the Texas Deceptive Trade Practices Act (ADTPA@) and to the trial court=s order granting sanctions against T&S on the DTPA claims.  In all other respects, I respectfully dissent. 


The court holds that the trial court erred in (1) denying T&S=s motion for summary judgment on the stated grounds that fact issues exist as to the intent of the parties to incorporate certain condition-precedent language of the General Conditions into the subcontract; (2) granting RGM=s motion for summary judgment on its contract claim; and (3) striking portions of T&S=s summary-judgment evidence.  These rulings by the trial court should be affirmed.

T&S=s Motion for Summary Judgment

The plurality concludes fact issues exist regarding the intent of the parties to incorporate the condition-precedent language of paragraph 4.3.2 of the General Conditions into the subcontract.  The plurality=s analysis is flawed because this language from the General Conditions was not incorporated into the parties= agreement.  Because RGM did not agree to be bound by this alleged condition-precedent, the trial court did not err in denying T&S=s motion for summary judgment.

The subcontract=s Aflow down@ provision did not incorporate all of the terms of the General Conditions into the subcontract.  The plain language of article 1.2 of the subcontract speaks only to the work to be performed by the subcontractor.  It does not address the dispute-resolution clause contained in paragraph 4.3.2.  Because the subcontract does not incorporate the dispute-resolution provision, this provision is not part of the parties= agreement.  Although certain provisions of the subcontract cannot be construed without reference to specific provisions of the prime contract (and its General Conditions), this does not mean that the parties incorporated the entirety of that document and all of its terms and conditions into the subcontract.  See LeBlanc, Inc. v. Gulf Bitulithic Co., 412 S.W.2d 86, 93 (Tex. Civ. App.CTyler 1967, writ ref=d n.r.e.) (A[T]he clear inference is that the parties did not intend to incorporate all provisions of the prime contract.@).  The parties did not agree that RGM had to submit the payment claim made in this case to the architect as a condition precedent to pursuing litigation against T&S.


The plurality=s analysis conflicts with controlling precedent.  See Seale v. Roy M. Mitchell Contracting Co., 321 S.W.2d 149, 150B51 (Tex. Civ. App.CAustin 1959, writ ref=d).  When parties to a subcontract incorporate only the provisions of the principal contract that apply to the subcontractor=s work, the subcontract does not incorporate any dispute-resolution provision contained in the principal contract.  See id. at 150B51.  In Seale, the general contractor=s contract with the owner contained provisions for arbitrating disputes between the owner and the general contractor.  See id. at 150.  Arbitration was a condition precedent to litigation.  See id.  The subcontractor=s contract stated that the subcontractor would A>comply with all terms and conditions pertaining to his part of the work as contained in the contract between the general contractor and the owner.=@  See id.  The court held that the arbitration provision was not incorporated into the subcontract because the language of the subcontract did not incorporate the provision.  See id. at 151.  The incorporation language related only to the performance of the work the subcontractor had contracted to do, and the arbitration provision did not fit into that classification.  See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd.
940 S.W.2d 587 (Texas Supreme Court, 1996)
LeBlanc, Inc. v. Gulf Bitulithic Company
412 S.W.2d 86 (Court of Appeals of Texas, 1967)
Appleton v. Appleton
76 S.W.3d 78 (Court of Appeals of Texas, 2002)
Seale v. Roy M. Mitchell Contracting Co.
321 S.W.2d 149 (Court of Appeals of Texas, 1959)
Sun Oil Co. (Delaware) v. Madeley
626 S.W.2d 726 (Texas Supreme Court, 1981)
Nowlin v. Frost National Bank
908 S.W.2d 283 (Court of Appeals of Texas, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Tribble & Stephens Co. v. RGM Constructors, L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/tribble-stephens-co-v-rgm-constructors-lp-texapp-2004.