Triad Drywall, LLC v. Vratsinas Construction Company

CourtCourt of Appeals of Georgia
DecidedMarch 25, 2013
DocketA12A2318
StatusPublished

This text of Triad Drywall, LLC v. Vratsinas Construction Company (Triad Drywall, LLC v. Vratsinas Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triad Drywall, LLC v. Vratsinas Construction Company, (Ga. Ct. App. 2013).

Opinion

FIRST DIVISION ELLINGTON, C. J., PHIPPS, P. J., and DILLARD, J.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. (Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008) http://www.gaappeals.us/rules/

March 25, 2013

In the Court of Appeals of Georgia A12A2317, A12A2318. VRATSINAS CONSTRUCTION COMPANY v. TRIAD DRYWALL, LLC.; and vice versa.

DILLARD, Judge.

After the completion of a commercial construction project in which the project

owner declared bankruptcy, Triad Drywall, LLC (“Triad”), a subcontractor, sued

Vratsinas Construction Company (“VCC”), the general contractor, to recover money

owed for its work on the project. VCC defended the lawsuit based upon a “pay-if-

paid” provision contained in the parties’ contract, which provided that Triad would

not be paid unless and until VCC was first paid by the project owner. The trial court

denied VCC’s motions for summary judgment, directed verdict, and judgment

notwithstanding the verdict, holding that the question of whether VCC waived the

pay-if-paid provision presented an issue for jury resolution. The jury ultimately awarded damages to Triad, and the parties filed cross-appeals. In Case Number

A12A2317, VCC argues, inter alia, that the trial court erred in submitting the issue

of waiver to the jury. In Case Number A12A2318, Triad asserts certain legal errors

contingent upon the grant of a new trial in VCC’s appeal. Because we conclude that

VCC was entitled to a judgment as a matter of law on the issue of waiver, we are

constrained to reverse in Case Number A12A2317, rendering Triad’s appeal in Case

Number A12A2318 moot.

Construed in the light most favorable to Triad,1 the facts show that VCC was

the general contractor under an agreement with Thomas Enterprises/Fourth Quarter

Properties (the “Owner”) to build the Ashley Park shopping center (the “Project”) in

Newnan. In January 2007, VCC contracted with Triad to install drywall and drop

ceilings, and to perform other work on the Project (the “Subcontract”). The

Subcontract contained the following pay-if-paid provision:

Notwithstanding anything contained herein to the contrary, save and except when the failure to receive payment is the result of default by [VCC] in the performance of its obligations under the Contract Documents unrelated to [Triad’s] performance of the Subcontract, all

1 See Hill Roofing Co., Inc. v. Lowe’s Home Ctrs. Inc., 265 Ga. App. 822, 822 (595 SE2d 638) (2004).

2 payments by [VCC] to [Triad] under the Subcontract, including without limitation, progress payments, full payment or partial release of retainage, payment for change orders and final payment, are expressly and unequivocally contingent upon and subject to Owner’s acceptance of all Subcontract Work and [VCC’s] receipt of payment from Owner for the Subcontract Work. Subcontractor expressly acknowledges that it relies on payment under the Subcontract on the creditworthiness of Owner, and not that of Contractor. It is expressly understood that any other basis for such non-payment by Owner, including the bankruptcy or insolvency of Owner, will not excuse this condition precedent to payment from [VCC] to [Triad]. [Triad] further agrees that Owner’s acceptance of the Subcontract Work and Owner’s payment to [VCC] for the Subcontract Work are express, independent conditions precedent to any obligation of [VCC] to make any payments to [Triad] and are not merely expressions of the time or manner of such payments.

It is undisputed that VCC paid Triad’s first three payment applications2 for

which the Owner paid VCC in full. But as rumors started swirling about the solvency

of the Owner, Gadi Gal—a co-owner of Triad—requested a meeting with John

Davenport, VCC’s project manager. During that meeting (which took place in the fall

of 2007), Gal—who was acutely aware of the contractual pay-if-pay

2 A payment application is the vehicle through which a subcontractor submits its invoices and requests for payment to the general contractor. As a general rule, Triad filled out its payment applications on the 20th day of any given month and was supposed to receive payment from VCC by the 20th day of the following month.

3 provision—expressed concern about the Owner’s ability to pay for the Project.

According to Gal, Davenport told him not to worry about the Owner’s finances and

to keep working, stating that VCC would pay Triad from its “own pocket” if

necessary.3

After this meeting, Triad continued work on the Project and submitted a fourth

payment application to VCC, who paid Triad the entire outstanding balance (via two

separate checks—one issued in November and one issued in February), despite not

having been paid in full for that work by the Owner.4 VCC refused to pay subsequent

payment applications, however, and by the time Triad finished work on the Project

in the spring of 2008, Triad had seven unpaid applications totaling approximately

$465,888. The Owner did not pay any monies to VCC after September 2007, despite

the continuing work and ultimate completion of the Project, and VCC tendered no

payment to Triad after the February 2008 check.

3 At trial, Davenport agreed that he met with Gadi Gal, but denied telling Gal that VCC would pay Triad from its own pocket. In accordance with our standard of review, however, we must assume that this statement was made as represented by Gal. See Hill Roofing Co., Inc., 265 Ga. App. at 822. 4 VCC only received a partial payment from the Owner for the work covered by the fourth payment application.

4 In March 2009, Triad filed the instant lawsuit against VCC to recover the

outstanding balance owed on the remaining payment applications. VCC argued, in

accordance with the pay-if-paid provision, that it was not contractually obligated to

pay Triad because it had not received payment from the Owner. Triad, on the other

hand, maintained that VCC waived the pay-if-paid provision through its conduct

when (1) Davenport assured Triad that VCC would pay Triad from its “own pocket,”

and (2) VCC paid Triad’s fourth payment application despite not having been paid

in full by the Owner. The trial court denied VCC’s motion for summary judgment

after holding that the issue of whether VCC waived the pay-if-paid provision

presented a genuine issue of material fact for jury resolution5 and, at the conclusion

of Triad’s case, denied VCC’s motion for a directed verdict. The jury returned a

verdict in favor of Triad for $465,888 plus interest and the trial court entered

judgment on the verdict. These cross-appeals follow the trial court’s denial of VCC’s

motion for judgment notwithstanding the verdict.

1. In Case Number A12A2317, VCC argues that the trial court erred in denying

its motions for directed verdict and judgment notwithstanding the verdict because

5 VCC sought and was denied a certificate of immediate review of the trial court’s denial of its motion for summary judgment.

5 Triad failed as a matter of law to present sufficient evidence to show waiver of the

pay-if-paid provision.6 We agree.

To begin with, we note that a party to a contract may waive a contractual right,

and that any such waiver may be accomplished expressly or implicitly through the

party’s conduct.7 But the law will not infer the waiver of an important contract right

unless “the waiver is clear and unmistakable.”8 And because waiver is not favored

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Accurate Printers, Inc. v. Stark
671 S.E.2d 228 (Court of Appeals of Georgia, 2008)
Integrated Micro Systems, Inc. v. NEC Home Electronics (USA), Inc.
329 S.E.2d 554 (Court of Appeals of Georgia, 1985)
Primetech Systems, Inc. v. Avion Systems, Inc.
648 S.E.2d 487 (Court of Appeals of Georgia, 2007)
DI Corbett Electric, Inc. v. Venture Construction Company
231 S.E.2d 536 (Court of Appeals of Georgia, 1976)
Mortensen v. Fowler-Flemister Concrete, Inc.
555 S.E.2d 492 (Court of Appeals of Georgia, 2001)
Hill Roofing Co. v. Lowe's Home Centers, Inc.
595 S.E.2d 638 (Court of Appeals of Georgia, 2004)
Eckerd Corp. v. Alterman Properties, Ltd.
589 S.E.2d 660 (Court of Appeals of Georgia, 2003)
Forsyth County v. WATERSCAPE SERVICES, LLC
694 S.E.2d 102 (Court of Appeals of Georgia, 2010)
Oxford Motors Co. v. Niblack
360 S.E.2d 23 (Court of Appeals of Georgia, 1987)
Mauldin v. Weinstock
411 S.E.2d 370 (Court of Appeals of Georgia, 1991)
Mahsa, Inc. v. Al-Madinah Petroleum, Inc.
625 S.E.2d 37 (Court of Appeals of Georgia, 2005)
Croxton v. MSC Holding, Inc.
489 S.E.2d 77 (Court of Appeals of Georgia, 1997)
Goldsmith v. Peterson
703 S.E.2d 694 (Court of Appeals of Georgia, 2010)
Berman v. Fraternities Health & Accident Ass'n
78 A. 462 (Supreme Judicial Court of Maine, 1910)
Plumer v. Continental Casualty Co.
77 S.E. 917 (Court of Appeals of Georgia, 1913)
Stapleton v. Dismukes
159 S.E. 768 (Court of Appeals of Georgia, 1931)
MNM 5, Inc. v. Anderson/6438 Northeast Partners, Ltd.
451 S.E.2d 788 (Court of Appeals of Georgia, 1994)
Rowe v. Law Offices of Ben C. Brodhead, P.C.
735 S.E.2d 39 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Triad Drywall, LLC v. Vratsinas Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triad-drywall-llc-v-vratsinas-construction-company-gactapp-2013.