Tri-State Elevator Co. v. Terral

174 So. 2d 289, 1965 La. App. LEXIS 4272
CourtLouisiana Court of Appeal
DecidedMarch 17, 1965
DocketNo. 10338
StatusPublished

This text of 174 So. 2d 289 (Tri-State Elevator Co. v. Terral) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-State Elevator Co. v. Terral, 174 So. 2d 289, 1965 La. App. LEXIS 4272 (La. Ct. App. 1965).

Opinion

HARDY, Judge.

This is an action by plaintiff subcontractor against defendant as contractor on construction work, praying for judgment in the sum of $1,658.21 allegedly representing the value of extra work performed over and above the contract price. Plaintiff has appealed from judgment rejecting his demands.

Defendant was the general contractor on the project for the construction of the new Winn Parish courthouse in Winnfield. Plaintiff was awarded the subcontract to furnish and install an elevator in the building in accordance with the architect’s plans and specifications. The contract price was fixed at $8,500.00. In preparation for actual installation of the elevator it was necessary to dig or drill a hole to a depth of approximately 25 feet for the accommodation of what is called the elevator jack hole.

It is the contention of plaintiff that in the course of drilling the jack hole quicksand was encountered, requiring extra labor and materials not contemplated by the subcontractor to the extent of the amount for [291]*291which he seeks judgment The defense is predicated upon the claim that the difficulty; encountered by plaintiff in connection with the digging of the jack hole did not constitute such an unusual condition as to justify an allowance for extra work and materials. In connection with this principal defense, it is claimed that plaintiff should and could have familiarized himself with the subsurface soil condition and been prepared for the circumstances which developed.

In his written reasons for judgment our learned brother of the district court primarily predicated his conclusion upon the ■finding that the presence of quicksand was not an unusual condition and should have been anticipated upon the basis of the subsoil data incorporated in the plans and specifications with which it was the duty of the subcontractor to fully acquaint himself. The trial judge further concluded that plaintiff failed to establish his claims by certain and acceptable proof.

Before this court the above holdings of the district judge are relied upon as specifications of error.

One of the primary considerations with respect to the determination of the issue before us requires the interpretation of what is referred to as the jack hole provision of the specifications, which reads as follows:

“JACK HOLE
“The contract price is based on the seller encountering soil free from rock, boulders, building construction members, or any obstructions or unusual conditions when installing the jack. Should such obstructions or unusual conditions be encountered, the contract price shall be increased by the amount of the additional labor at Seller’s usual rates and the actual material and incidental expense, plus 15%.” (Emphasis supplied.)

The principal question is whether the quicksand constituted an “unusual condition” under the above provision.

The gist of the defense and the basis of the finding of the district court rests upon the premise that the construction plans contained a disclosure of subsoil conditions as determined from test borings conducted by Eustis Engineering Company of Metairie, Louisiana. It is further implied that plaintiff either failed to acquaint himself with the subsoil conditions reflected by the plans or disregarded the probability of quicksand conditions. After careful examination of the record and study of the plan of the subsoil structure, we are unable to concur in these conclusions.

The plot plan of the test borings reflects a subsoil profile resulting from three separate core holes varying in depth from 50 to 75 feet. These profiles show that under an overlay of sandy clay several strata of sand existed. However, it is important to note that the profile gives no indication of any moisture content in the sand nor does it give the slightest indication that any stratum was of that nature which is commonly designated as quicksand. Nor, in fact, does the plan appear to indicate the relation of the three test borings to the elevator shaft.

Strangely enough, no employee of the Eustis Engineering Company was called as a witness. Defendant relied almost exclusively upon the testimony of Mr. U. M. Nolan, a member of the firm of Nolan, Norman, Architects of New Orleans, who prepared the plans and specifications. It is noteworthy that Mr. Nolan testified that he was not an expert on subsoil conditions and he admitted that the plan and profile as prepared by the Eustis firm did not indicate the presence of moisture in the sand. This witness took the position that plaintiff should have expected to encounter quicksand. The following extracts from his testimony are pertinent:

“Q. In other words, it is your testimony that there is sufficient information on page 1 of the plans —of the set of drawings as to the borings, the signs from borings and soil samples?.
[292]*292“A. I took that stand, yes, sir.
“Q. That a person contracting to build an elevator should have expected to encounter quicksand or abnormal soil?
“A. What is illustrated here on the plans is sufficient for any man who’s going to bore the ground, put a hole in it. To know that there is sand there, when there is sand there you can have water —it’s possible to have water and when you do have water, you possibly can have a quick condition. Yes, sir, there is ample information here for any man.
“Q. Do you know whether or not the Tri-State Elevator people checked this job to see if there were any unusual conditions before they started?
“A. No, sir.”
* * * * * *
“Q. Now, I believe you also testified that you, of your own knowledge, couldn’t say how frequently the the quicksand condition is encountered. I believe you also said that you had gotten from someone an indication that maybe ten per cent of the time, would a condition that you can reasonably expect to encounter ten per cent of the time be an unusual condition or would that be something that in preparing your bid you would make an extra allowance to take care of?
“A. To clarify the ten per cent, the ten per cent that I have in mind is a statistic that I recollect having read in correspondence of some sort in the file. It’s not my statistic * * (Emphasis supplied.)

The witness did not define the area upon which his hearsay estimate of the ten per cent chance of encountering quicksand was based.

As opposed to the testimony of the architect, Mr. J. D. Alexander, Jr., Vice President of plaintiff corporation, testified that the subcontractor’s estimate on the job was made after reference to the subsoil plan and upon the basis of this plan, as well as the experience of his firm in connection with a similar job which it had performed for the First Federal Savings and Loan building just across the street from the courthouse site.

After careful consideration of the testimony on this point we are convinced that plaintiff was not guilty of any neglect or lack of care, measured by standards of reason and prudence, in failing to anticipate the presence of quicksand. It necessarily follows that this development constituted an unusual condition as contemplated under the jack hole provision of the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
174 So. 2d 289, 1965 La. App. LEXIS 4272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-state-elevator-co-v-terral-lactapp-1965.