Tri-State Commodities, Inc. v. GSO America, Inc.

18 F. App'x 737
CourtCourt of Appeals for the Tenth Circuit
DecidedSeptember 5, 2001
Docket99-3117, 99-3168
StatusUnpublished

This text of 18 F. App'x 737 (Tri-State Commodities, Inc. v. GSO America, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-State Commodities, Inc. v. GSO America, Inc., 18 F. App'x 737 (10th Cir. 2001).

Opinion

*739 ORDER AND JUDGMENT **

WEINSHIENK, District Judge.

INTRODUCTION

This diversity breach of contract case involves issues concerning the nature of a contract to supply mulch. Appellant TriState Commodities, Inc., (Tri-State) believed it had signed a minimum requirements contract with appellee GSO America, Inc., (GSO) guaranteeing that GSO would purchase all of its mulch from TriState over a five-year period. GSO believed that it merely was a one-year contract, renewable for additional one-year periods, that required GSO to purchase certain minimum amounts if the contract was to renew automatically for another year. GSO also came to believe that TriState fraudulently had induced it into signing a contract by misrepresenting TriState’s relationship with its suppliers.

Tri-State brought suit in the District of Kansas for breach of contract. The district court granted partial summary judgment to GSO, finding that the contract was only for one year, and that GSO was required only to purchase certain limited amounts of mulch from Tri-State. The district court also granted GSO’s motion in limine to limit damages to lost profits. Finding for Tri-State on the breach of contract claim, the jury awarded Tri-State damages less than the maximum allowable lost profit figure. GSO then moved for a judgment as a matter of law, which was denied. Tri-State appeals from the district court’s partial summary judgment in favor of GSO, and from the ruling granting GSO’s motion in limine. GSO cross-appeals from the district court’s denial of its motion for judgment. We assert jurisdiction pursuant to 28 U.S.C. § 1291, and, for the reasons stated below, affirm the district court’s rulings.

BACKGROUND

Tri-State historically has been in the transportation business. In early 1995, Tri-State became aware that Munson Trucking (Munson) had mulch for sale at its facilities in Washington State. TriState then approached GSO, a manufacturer of mulch and other gardening products, about supplying mulch to GSO. As GSO was concerned about a possible shortage of mulch, it expressed interest. Tri-State then contracted with Munson to purchase mulch, and, after exchanging a variety of oral and written proposals, signed a contract on May 4, 1995, to supply GSO with mulch.

Initially, the contract between Tri-State and GSO functioned well. GSO set up a bagging facility at Tri-States’ depot in Nebraska and shipped the bagged mulch to GSO’s commercial facilities. However, in July, 1995, after a trip to Washington State where representatives met with Munson, GSO began to suspect that it had been fraudulently induced into signing the contract with Tri-State. Specifically, GSO claims that it had been led to believe that Tri-State had exclusive supply contracts with over forty lumber mills on the west coast.

Relations between Tri-State and GSO went downhill rapidly, and GSO stopped purchasing mulch from Tri-State. On December 20, 1995, GSO removed its bagger from Tri-State’s facility, and on February 20, 1996, GSO sent a letter to Tri-State terminating their contract, claiming that *740 Tri-State had misrepresented that it had exclusive supply contracts with over forty mills on the west coast, and characterizing Tri-State’s pricing as unreasonable and unconscionable. After the February 20, 1996, letter, GSO began purchasing mulch directly from Munson. Tri-State ceased purchasing mulch from Munson, and was sued for breach of contract by Munson. In turn, Tri-State sued GSO for breach of contract.

Tri-State’s amended complaint against GSO alleged, among other claims, that GSO had agreed to purchase all of its Grade A cedar bark mulch from Tri-State for a period of five years, in the following quantities: 10,000 cubic yards for inventory as well as a minimum of 70,000 cubic yards the first year, 140,000 cubic yards during the second year, and 190,000 cubic yards during the third, fourth and fifth years. GSO denied liability, and claimed the contract was procured by fraud. In GSO’s view, the contract required GSO to purchase only 10,000 cubic yards during the first year. After that point, the contract continued only if GSO satisfied a condition precedent, the minimum purchase of at least 70,000 additional cubic yards of mulch within the first year. Another provision of the contract gave either side the right to terminate the contract upon notice at least 90 days in advance of the contract’s anniversary.

The district court, in granting GSO’s motion for partial summary judgment, found that the contract required GSO to purchase unconditionally 10,000 cubic yards, and required GSO to purchase an additional 70,000 cubic yards only if it wished to renew the contract for another year. However, during the term of the contract, GSO was obligated to purchase all of its mulch requirements from TriState. GSO then filed a motion in limine, granted by the district court, which limited the measure of damages to lost profits of $6.20 per cubic yard, not the full contract price of $18.50 per cubic yard as sought by Tri-State.

The jury found that GSO had breached the contract by purchasing mulch during the first year directly from Munson, rather than through Tri-State, and awarded TriState $32,132.60 in damages, based on lost net profits of $4.03 per cubic yard for 7,973.35 cubic yards of mulch purchased by GSO directly from Munson. Following the jury verdict, GSO moved for judgment as a matter of law under Fed.R.Civ.P. 50(b); the motion was denied. Tri-State appeals the district court’s partial summary judgment in favor of GSO concerning the interpretation of the contract, and the district court’s ruling granting GSO’s motion in limine with respect to contract damages. GSO cross-appeals the district court’s denial in part of its motion for summary judgment, arguing that Tri-State presented no evidence that GSO processed any mulch in violation of the contract during its term, and also arguing that the district court’s instruction to the jury during testimony of a GSO witness in effect granted Tri-State a directed verdict with respect to the volume of mulch at issue.

DISCUSSION

This Court reviews grants or denials of summary judgment de novo. Butler v. City of Prairie Village, Kansas, 172 F.3d 736, 745 (10th Cir.1999). The methodology of calculating a damage award is a question of law, and thus reviewed de novo, while the amount of a damage reward is a question of fact, and thus is reviewed for clear error. Southern Colorado MRI, Ltd. v. Med-Alliance, Inc., 166 F.3d 1094, 1100 (10th Cir.1999). The standard of review for evidentiary rulings is abuse of discretion. Mitchell v. Gencorp, Inc., 165 F.3d 778, 780 (10th Cir.1999).

*741 I. The Contract:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mitchell v. Gencorp Inc.
165 F.3d 778 (Tenth Circuit, 1999)
Southern Colorado MRI, Ltd. v. Med-Alliance, Inc.
166 F.3d 1094 (Tenth Circuit, 1999)
Yapp v. Excel Corporation
186 F.3d 1222 (Tenth Circuit, 1999)
Butler v. City of Prairie Village, Kansas
172 F.3d 736 (Tenth Circuit, 1999)
Marquis v. State Farm Fire & Casualty Co.
961 P.2d 1213 (Supreme Court of Kansas, 1998)
Barbara Oil Co. v. Kansas Gas Supply Corp.
827 P.2d 24 (Supreme Court of Kansas, 1992)
General Surgery, P.A. v. Suppes
953 P.2d 1055 (Court of Appeals of Kansas, 1998)
Jackson v. City of Cookeville
31 F.3d 1354 (Sixth Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
18 F. App'x 737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-state-commodities-inc-v-gso-america-inc-ca10-2001.