Tri-South Mortgage Investors v. Forest & Waterway Corp.

354 So. 2d 588, 1977 La. App. LEXIS 3909
CourtLouisiana Court of Appeal
DecidedDecember 13, 1977
DocketNo. 8310
StatusPublished
Cited by2 cases

This text of 354 So. 2d 588 (Tri-South Mortgage Investors v. Forest & Waterway Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-South Mortgage Investors v. Forest & Waterway Corp., 354 So. 2d 588, 1977 La. App. LEXIS 3909 (La. Ct. App. 1977).

Opinion

BOUTALL, Judge.

This appeal involves the competition for priority between a mortgagee and laborers and materialmen. ■

On June 28, 1972, Tri-South Mortgage Investors, hereinafter referred to as TriSouth, foreclosed upon a mortgage granted it by the Forest and Waterway Corporation on a development project known as the Forest Isles Apartment Complex, Tall Timbers Subdivision. A Sheriff’s sale was scheduled for August 17, 1972 by the Civil Sheriff for the Parish of Orleans. However, numerous contractors and material-men filed petitions of intervention prior to the Sheriff’s sale as well as subsequent to the Sheriff’s sale, seeking to determine the ranking of privileges on the proceeds. The trial court ordered the Sheriff to hold all the proceeds of the sale pending disposition of the issue of the validity and priority of the asserted liens. The purchaser at the sale was the mortgagee, Tri-South.

The lower court referred the trial of the ranking and validity of the liens to a Commissioner who tried the claims. The Commissioner submitted a report and the trial court then adopted the report of the Commissioner and rendered various judgments. Some judgments ranked the priority of the asserted liens and privileges above that of the mortgage granted in favor of Tri-South and granted a personal judgment against Tri-South for the amounts found due by the Commissioner. Additionally, some liens and claims filed were either dismissed or settled. Tri-South now appeals those judgments which acknowledge the priority of liens and claims of 13 claimants who claim under authority of LSA-R.S. 9:4801 et seq. Two claimants, Wallace C. Drennan, Inc. and Summit Building, Inc. have answered the appeal and seek an increase in the quantum of their claims recognized in the lower court.

There are numerous principal issues for us to consider in this appeal. How[591]*591ever, the issue which we must consider first is the question of when did the work begin on the Forest Isles Apartment Complex? The answer to that question is basically determinative of the rights of the mortgagee, Tri-South and the various claimants. LSA-R.S. 9:4812 says that the laborers and materialmen’s privilege shall be superior to all the claims against the land except for a bona fide mortgage, if the “mortgage exists and has been duly recorded before the work or labor is begun or any material is furnished.” LSA-R.S. 9 ¡4819(A)(1) defines the term “before the work or labor is begun or any material is furnished” as:

“(1) In the event that the work or construction is new, then ‘work or labor is begun or material is furnished’ is defined as having begun when either excavation has been started so that it can be observed on inspection, or material has been furnished and delivered to the job site which is visible upon inspection and which material when delivered had a value in excess of one hundred dollars provided, however, that test piling shall be excluded from this definition.”

The mortgage granted in favor of TriSouth in the amount of $7,500,000 against the subject property was executed and recorded on April 8, 1971, but there is a serious question as to when the work was begun. The testimony of numerous contractors, especially employees of Rouse’s Dozer Service, was that a large and ambitious project had already been under way to clear the land and begin the construction prior to April 8, 1971. Counsel for appellant Tri-South attempts to characterize the work during prior to April 8 as merely clearing of the land and not excavation, and to support this contention appellant cites several cases distinguishing clearing work from excavation work as intended by the Statute.

In the case before us we cannot reach any other conclusion but that the work done prior to April 8 was that type of work intended to be covered by the private works statute. The testimony of various contractors and workers was that, of the 26 acre site that the apartment complex was to cover, approximately 90% of that area had been cleared in preparation for the stages of construction for the individual housing units that were to immediately follow the clearing. This clearing project, which included the cutting of swale ditches for drainage, building temporary and basic roads, moving earth to building sites, and various other projects in an amount of approximately $19,000 was the first step in the overall construction process. As such it is impossible to distinguish this project from the rest of the construction project. As the Commissioner found in his report:

“The intent of the developer to continue the work from the inception of land clearing to the completion of the apartment complex is manifest. There was no interlude between the land clearing and the construction of buildings. There was no sale of any part of the cleared ground to other parties.
“R.S. 9:4819 defines the beginning of work as ‘when excavation has been started so that it can be observed on inspection.’ There is no question but that on April 8, 1972, (sic) the prudent mortgage investor would have observed, and thereby been enlightened, in regard to the extensive land clearing and excavations taking place in coordination with the intended development of the site as a large apartment complex.”

If a mortgagee fails to protect his interest by inspection of the property to determine whether work has commenced or materials have been supplied, he proceeds at his own peril with respect to the priority of liens of materialmen or laborers. Capitol Bank & Trust Company v. Broussard Paint & Wallpaper Company, La.App. 1st Cir., 198 So.2d 204 (1967). The test is not whether such an inspection is actually made, but rather would such an inspection, if made, reveal that the work had already begun. Pringle-Associated Mortgage Corporation v. Evans-Benck Construction Company, La. App. 1st Cir., 209 So.2d 606 (1967). We hold that had the mortgagee in this case, TriSouth, taken the simple precaution of in[592]*592specting the subdivision to determine if work had already begun, it could have protected its interest prior to entering into the mortgage. With a vast area having already been cleared by April 8,1 and numerous pieces of construction equipment working on the construction site at the time, a simple inspection by the mortgagee would unquestionably have revealed the fact that work had begun. Therefore the liens of laborers and materialmen prime the mortgage.

Having decided that the labor and materialmen’s liens outrank the mortgage held by Tri-South, we now pass to a consideration of the effect of the filing of lien release bonds by Tri-South upon those liens.

To place this issue in proper perspective, we must recount the procedural situation at that time. The basic suit herein is a mortgage foreclosure via executiva by Tri-South Mortgage Investors, holders of the mortgage, against Forest & Waterway Corporation, owners of the property upon which the mortgage was given and the development project took place, giving rise to the liens herein involved. In this proceeding numerous subcontractors and materialmen filed petitions of intervention. Those interventions were referred to the Commissioner of the Civil District Court for trial, and some 5 days of trial followed over a lengthy period. The proceeding was a summary proceeding in which the lien holders asserted their claim to preference in the distribution of the proceeds of the sale of the property, C.C.P. Articles 2643 and 1092, and C.C.P. Article 2592.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C & J Contractors v. American Bank & Tr.
559 So. 2d 810 (Louisiana Court of Appeal, 1990)
Central Progressive Bank v. Doerner
365 So. 2d 263 (Louisiana Court of Appeal, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
354 So. 2d 588, 1977 La. App. LEXIS 3909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-south-mortgage-investors-v-forest-waterway-corp-lactapp-1977.