Tri-County Plumbing & Heating, Inc. v. Levee Restorations, Inc.

720 P.2d 247, 221 Mont. 403, 1986 Mont. LEXIS 918
CourtMontana Supreme Court
DecidedJune 5, 1986
Docket85-367
StatusPublished
Cited by8 cases

This text of 720 P.2d 247 (Tri-County Plumbing & Heating, Inc. v. Levee Restorations, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-County Plumbing & Heating, Inc. v. Levee Restorations, Inc., 720 P.2d 247, 221 Mont. 403, 1986 Mont. LEXIS 918 (Mo. 1986).

Opinion

MR. JUSTICE HARRISON

delivered the Opinion of the Court.

*405 Plaintiff Tri-County Plumbing and Heating, Inc./Atlas Electric, Inc. (hereinafter “Tri-County”) brought this action in Chouteau County District Court to foreclose a mechanics’ lien filed by them against certain real property located in Fort Benton, Montana, owned by defendant Levee Restorations, Inc. (hereinafter “Levee”). The Deer Lodge Bank and Trust Company (hereinafter “Bank”) was also named as a defendant by virtue of its mortgage on the same real property. Ingram-Clevenger, Inc. (hereinafter “Ingram-Clevenger”) filed a motion to intervene as a plaintiff in order to foreclose its own mechanics’ lien on the same property. The Bank then cross-claimed against Levee to foreclose its mortgage on the subject property.

The matter was heard by the District Court, sitting without a jury, in March of 1985. In June of 1985, the trial court issued its findings of fact, conclusions of law, and decree granting judgment against Levee in favor of Tri-County and Ingram-Clevenger for the amounts requested in their respective mechanics’ liens plus interest, attorneys fees and costs. The trial court also awarded judgment against Levee in favor of the Bank for the amount of their mortgage plus interest, attorneys fees, and costs. The trial court further accorded the liens of Tri-County and Ingram-Clevenger equal status and declared them to be superior in priority to the mortgage of the Bank. In addition, the trial court granted lien status to certain items furnished by Tri-County and Ingram-Clevenger which followed the date on which their mechanics’ liens were filed. These additional items were supplied by the two plaintiffs for the preservation and protection of the subject property and were awarded a first priority by the trial court over payment of all other liens and encumbrances. Only the bank, and not Levee, appeals from this judgment of the trial court. We affirm.

On November 4, 1983, Ingram-Clevenger (a general contractor with its principal place of business in Helena, Montana) entered into several contracts with Levee for the interior restoration, remodeling and renovation of the Grand Union Hotel (“Hotel”) located in Fort Benton, Montana. The total contract price for the work to be performed under these contracts was $862,260. Ingram-Clevenger then subcontracted a major portion of the work to Tri-County (a plumbing, heating and electrical contractor with his principal place of business in Helena, Montana) for the performance of the plumbing, heating and electrical work on the Hotel.

On February 6, 1984, Levee obtained a loan from the Bank in the *406 amount of $210,000. The majority of this loan ($179,500) was applied by Levee to the Hotel renovation project. This loan was secured by two mortgages given by Levee to the Bank, one of which included a mortgage on the Hotel. The other mortgage given by Levee to the Bank was not at issue in this lawsuit. The mortgage on the Hotel was recorded in the Chouteau County Clerk and Recorder’s office on February 10, 1984.

Ingram-Clevenger started work on the Hotel project on or about November 4, 1983. From time to time, as required under the construction contracts, Ingram-Clevenger submitted applications for payment to Levee’s architect for the project, Richard Shope. Ingram-Clevenger submitted a total of nine applications for payment to Shope, of which only the first four were approved and paid covering the period from November, 1983 through February, 1984. The last five applications for payment (covering March through May, 1984) were not approved or paid by Shope because Levee had not secured future financing for the Hotel project. After the last payment was made by Levee to Ingram-Clevenger in February of 1984, Ingram-Clevenger continued to work on the project apparently in anticipation of Levee securing future financing. During the late spring of 1984, it became apparent that future financing for the project could not be found and Ingram-Clevenger halted work at the end of May. It appears that the only financing obtained by Levee for the Hotel project was the above mentioned loan from the Bank. To date, Levee has only paid the sum of $145,440 to Ingram-Clevenger under the Hotel project contracts, despite a total of over $600,000 worth of work having been performed by the plaintiffs.

On June 7, 1984, Tri-County filed a mechanics’ lien against the Hotel in the amount of $149,829. This sum represented the amount it was owed by Ingram-Clevenger for its unpaid subcontracting work. On July 7, 1984, Ingram-Clevenger filed its own mechanic’s lien against the Hotel for the sum of $441,344. This sum was the unpaid portion of the Hotel project contracts at the time the lien was filed, and it was based on the unpaid applications for payment presented to Levee. Both of these liens were properly recorded with the Clerk and Recorder of Chouteau County.

It should be noted that Tri-County’s mechanics’ lien claim was included in its entirety in Ingram-Clevenger’s lien except for the sum of $2,369. This amount represented items which were negotiated directly between Tri-County and Levee, and this sum was included in Tri-County’s lien of $149,829.

*407 Following the filing of the mechanic’s liens by Tri-County and Ingram-Clevenger, both Ingram-Clevenger and Tri-County continued to incur expenses relating to the protection and preservation of the Hotel project. These expenses included $10,000 for the installation of a water line, $3,671.99 for insurance premiums, $5,303.91 for gas and electricity, and $629 for repairs due to freezing.

Once it became apparent that no more funds were forthcoming from Levee for the Hotel project, Tri-County filed suit on its mechanics’ lien on June 8, 1984, and the above-described proceedings ensued. The District Court granted judgment against Levee in favor of Tri-County and Ingram-Clevenger for the respective amounts of their mechanics’ liens, $149,829 and $312,491 (which included a $20,976 mathematical error discovered during trial). Ingram-Clevenger’s judgment was later reduced by the trial court to the sum of $300,076 due to the sale of certain construction supplies from the Hotel project. The trial court also accorded equal lien status to the liens of Ingram-Clevenger and Tri-County, and declared the mortgage of the Bank ($210,000) to be second in priority. The trial court further decreed that the “preservation” expenses incurred by Ingram-Clevenger and Tri-County should be accorded a first priority of payment over all other liens and encumbrances.

The Bank now presents the following pertinent issues for review by this Court:

1. Did the District Court err in not granting a continuance of the trial in order that discovery could be initiated and completed?

2. Was there substantial evidence to support the finding of the District Court as to the amount of Ingram-Clevenger’s lien and that the lien was not in fact overstated?

3. Did the District Court err in awarding lien status to certain “preservation expenses” incurred subsequent to the filing of IngramClevenger’s and Tri-County’s mechanics’ liens and granting a priority to these expenses superior to that accorded either the mechanics’ liens or the Bank’s mortgage?

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A.C.I. v. Elevated Property
2021 MT 246 (Montana Supreme Court, 2021)
Burns v. a Cash Construction Lien Bond
2000 MT 233 (Montana Supreme Court, 2000)
Coffin v. Atraqchi
2000 MT 172N (Montana Supreme Court, 2000)
In Re the Marriage of Caras
868 P.2d 615 (Montana Supreme Court, 1994)
United States v. Bretz
902 F.2d 41 (Ninth Circuit, 1990)
Corscadden v. Komrosky
788 P.2d 321 (Montana Supreme Court, 1990)
American Federal Savings & Loan Ass'n v. Schenk
785 P.2d 1024 (Montana Supreme Court, 1990)
AMERICAN FEDERAL S & L v. Schenk
785 P.2d 1024 (Montana Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
720 P.2d 247, 221 Mont. 403, 1986 Mont. LEXIS 918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-county-plumbing-heating-inc-v-levee-restorations-inc-mont-1986.