Tri Am Construction, Inc. v. J & V Development, Inc.

415 S.W.3d 242, 2011 WL 3847166, 2011 Tenn. App. LEXIS 466
CourtCourt of Appeals of Tennessee
DecidedAugust 30, 2011
DocketE2010-01952-COA-R9-CV
StatusPublished
Cited by1 cases

This text of 415 S.W.3d 242 (Tri Am Construction, Inc. v. J & V Development, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri Am Construction, Inc. v. J & V Development, Inc., 415 S.W.3d 242, 2011 WL 3847166, 2011 Tenn. App. LEXIS 466 (Tenn. Ct. App. 2011).

Opinion

OPINION

D. MICHAEL SWINEY, J.,

delivered the opinion of the Court,

in which HERSCHEL P. FRANKS, P.J., and CHARLES D. SUSANO, JR., J., joined.

This interlocutory appeal stems from a lien enforcement action. Tri Am Construction, Inc. (“Tri Am”) filed a complaint in the Chancery Court for Rhea County (“the Trial Court”) against J & V Development, Inc. (“J & V”), Randall E. Vick, Brenda B. Jung 1 , and Branch Banking and Trust Company (“BB & T”) to enforce a lien. BB & T 2 moved to dismiss Tri Am’s complaint, citing alleged fatal procedural defects. The Trial Court denied BB *244 & T’s motion to dismiss and allowed Tri Am to amend its complaint to cure the procedural defects. We granted permission for this interlocutory appeal. We find that the Trial Court did not err in liberally construing the revised mechanics’ and ma-terialmen’s liens statutes to permit Tri Am to amend its complaint in order to cure the procedural defects. We further find that the Trial Court did not err in declining to hold that BB & T’s rights would be retroactively impaired by the liberal application of the revised mechanics’ and material-men’s liens statutes. We affirm the judgment of the Trial Court.

Background

Dillard Construction, Inc. (“Dillard”) 3 and J & V entered into a contract whereby the former agreed to perform work on property owned by J & V at a site called Taylor’s Landing. According to Dillard’s pleading in subsequent litigation, visible commencement of construction on the project began “by at least” February 2007. In April 2007, BB & T’s Deed of Trust on the relevant property was executed and recorded.

Tri Am entered into a contract in December 2007 with J & V to perform work at Taylor’s Landing. On May 18, 2007, the revised mechanics’ and materialmen’s liens statutes, Tenn.Code Ann. § 66-11-101 et seq., entered effect. The legal consequences of this legislative action are contested in this appeal. BB & T later recorded a second Deed of Trust on the property.

Tri Am filed a notice of lien in August 2008. According to its notice of lien, Tri Am last worked on the project in June 2008. In October 2008, Tri Am filed a complaint to enforce lien, stating, in part, that defendants had failed to pay Tri Am for part of its work. BB & T filed its answer in December 2008. BB & T moved to amend its answer in October 2009, ultimately filing an amended answer containing affirmative defenses in December 2009. BB & T also filed a motion to dismiss. BB & T argued that Tri Am’s complaint to enforce lien was fatally defective. Hearings were held in this case in February and April, 2010. BB & T filed a second motion to dismiss, arguing that the statute of limitations had expired and Tri Am could not timely amend its original complaint to correct the claimed defects. In May 2010, the Trial Court entered its order, stating, in part:

BB & T’s Motion to Dismiss is based on allegations that that [sic] Tri-Am did not file its mechanics’ and materialman’s lien complaint under oath, that although Tri-Am prayed for issuance of a writ of attachment and furnished a bond for same, no writ of attachment was issued, that Tri-Am did not name the trustee under the deed of trust in favor of BB & T as a defendant in this action and that as a result of these deficiencies, no suit to enforce Tri-Am’s lien rights was commenced within the applicable statute of limitations. Tri-Am’s Response to the Motion to Dismiss includes a request that it be allowed to amend its complaint to correct the alleged deficiencies, among other arguments. The Court has previously ruled that the mechanics’ and materialman’s lien law in effect following May 18, 2007 (the “May 18 Law”) is controlling in this case, and that TriAm’s purported mechanics’ and materi-alman’s lien relates back to a date of visible commencement of operations at Taylor’s Landing which occurred prior to the effective date of the May 18 Law *245 even though Tri-Am’s contract with the Owner/Developer (Defendant J & V Development, Inc.) was not signed and it did not begin its own operations until after that date. The Court also notes that the Trustee appeared and participated in a hearing in December, 2008, pursuant to a Motion to Stay Foreclosure, and agreed to an Order staying said foreclosure; accordingly the Trustee was on actual notice of these proceedings and submitted to the Court upon entry of the Order in January, 2009. The Court concludes that Tenn. Code Ann. § 66-11-148, a portion of the May 18 Law, provides that the mechanics’ lien statute is to be construed liberally so as to provide the beneficial results, intents and purposes of the statute, and the Court concludes that under this law, the Court is to look to substance over form, so that the Amended Complaint may be filed to cure the failure to file suit under oath, to have an attachment issued and to add the trustee under the deed of trust as a party defendant in this case. Therefore, it is hereby
ORDERED, ADJUDGED and DECREED that BB & T’s Motion to Dismiss hereby is denied. Tri-Am shall be allowed to file an amended complaint to file suit under oath, to have an attachment issued and to add the trustee under the deed of trust as a party defendant in this case.

The Trial Court’s May 2010 order also denied BB & T’s second motion to dismiss. The Trial Court granted BB & T’s motion for interlocutory appeal. We subsequently granted permission to appeal pursuant to Tenn. R.App. P. 9.

Discussion

We restate the issues raised on this interlocutory appeal as follows: 1) whether the Trial Court erred in liberally construing the mechanics’ and materialmen’s liens statutes to permit Tri Am to cure procedural defects in its lien enforcement action; and 2) whether the Trial Court erred in declining to hold that BB & T’s constitutional rights would be retroactively impaired by a liberal application of the revised mechanics’ and materialmen’s liens statutes.

Our review is de novo upon the record, accompanied by a presumption of correctness of the findings of fact of the trial court, unless the preponderance of the evidence is otherwise. Tenn. R.App. P. 13(d); Bogan v. Bogan, 60 S.W.3d 721, 727 (Tenn.2001). A trial court’s conclusions of law are subject to a de novo review with no presumption of correctness. S. Constructors, Inc. v. Loudon County Bd. of Educ., 58 S.W.3d 706, 710 (Tenn.2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

83 Freight, LLC v. C4 Sourcing Solutions, LLC
Court of Appeals of Tennessee, 2025

Cite This Page — Counsel Stack

Bluebook (online)
415 S.W.3d 242, 2011 WL 3847166, 2011 Tenn. App. LEXIS 466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-am-construction-inc-v-j-v-development-inc-tennctapp-2011.