TRETINA PRINTING v. Fitzpatrick

619 A.2d 1037, 262 N.J. Super. 45
CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 9, 1993
StatusPublished
Cited by4 cases

This text of 619 A.2d 1037 (TRETINA PRINTING v. Fitzpatrick) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TRETINA PRINTING v. Fitzpatrick, 619 A.2d 1037, 262 N.J. Super. 45 (N.J. Ct. App. 1993).

Opinion

262 N.J. Super. 45 (1993)
619 A.2d 1037

IN THE MATTER OF THE ARBITRATION BETWEEN TRETINA PRINTING, INC. AND HI-TECH PROPERTIES, A GENERAL PARTNERSHIP, AND JAN TRETINA AND OLGA TRETINA, INDIVIDUALLY, PETITIONERS-APPELLANTS/CROSS-RESPONDENTS,
v.
FITZPATRICK & ASSOCIATES, INC., RESPONDENT-RESPONDENT/CROSS-APPELLANT. FITZPATRICK & ASSOCIATES, INC., PLAINTIFF-RESPONDENT/CROSS-APPELLANT,
v.
TRETINA PRINTING CO., INC., HI-TECH PROPERTIES, A GENERAL PARTNERSHIP, AND JAN TRETINA AND OLGA TRETINA, INDIVIDUALLY, DEFENDANTS-APPELLANTS/CROSS-RESPONDENTS.

Superior Court of New Jersey, Appellate Division.

Argued December 2, 1992.
Decided February 9, 1993.

*47 Before Judges KING, BRODY and LANDAU.

George F. Mackey argued the cause for appellants/cross-respondents (Mackey & Moore, attorneys; Mr. Mackey and Gary J. Mueller, of counsel and on the brief).

Robert Hedinger argued the cause for respondent/cross-appellant (Peckar & Abramson, attorneys; Mr. Hedinger and Caroline M. Rossi, on the brief).

The opinion of the court was delivered by BRODY, J.A.D.

Both parties appeal from a judgment confirming an arbitration award as modified by the trial judge. The dispute arose under an "Owner-Construction Manager" contract between Tretina Printing, Inc. (Tretina) and Fitzpatrick & Associates, Inc. (Fitzpatrick). We hold that the arbitrator imperfectly executed his powers upon the subject matter submitted to him and that it is too late to direct a rehearing because the time within which he was empowered by the parties to make an award has expired.

Tretina engaged Fitzpatrick to manage the construction of a building to house Tretina's printing business and rental office space. Fitzpatrick guaranteed that Tretina's total cost would *48 not exceed $2,566,050, the Guaranteed Maximum Price (GMP). Tretina agreed to pay Fitzpatrick a $200,000 Construction Manager's Fee, to be included in the total cost, and 30% of any saving if the total cost is less than the GMP. The parties agreed that instead of paying Fitzpatrick the fee in monthly installments, Tretina would pay the entire fee with "an interest rate of 11.5%" after the work was completed. Significantly, the contract provided that the total cost included the "cost of corrective work." Fitzpatrick agreed to absorb any portion of the total cost that exceeded the GMP.[1]

The contract provides that all disputes "shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association...." Fitzpatrick submitted the parties' disputes to arbitration when Tretina failed to pay requisition # 15 in the amount of $45,083, which had been approved by Tretina's architect. By then Tretina had paid Fitzpatrick $2,119,819, which was $446,231 less than the GMP. Thus, under the basic terms of the contract, when the parties went into arbitration Tretina was liable for up to $446,231 of the remaining costs of construction, which included the cost of corrective work and Fitzpatrick's $200,000 fee.

After conducting twenty-one arbitration sessions over the period of a year, the arbitrator issued a written award in a form that has the appearance of resolving each of Fitzpatrick's and Tretina's contract claims by either assigning a dollar amount to each or stating that the claim is "denied." The "TOTAL AWARD TO FITZPATRICK" was $269,912.34, and the "TOTAL AWARD TO TRETINA" was $530,180, leaving a "TOTAL NET AWARD TO TRETINA" of $260,267.66. After making several adjustments for open items that the arbitrator had determined it would be premature for him to decide, the trial *49 judge confirmed the net award — but reduced it by $201,148, the sum noted in requisition # 15 as accumulated "retainage."

Tretina appeals, claiming that the judge should not have reduced the award. Fitzpatrick cross-appeals claiming that the award is so defective that the judge should have vacated it.

The Supreme Court has recently defined a court's limited authority to review an arbitration award in the private sector. "We sit not as an appellate court to review arbitral decisions of law but only to safeguard against interpretive error that may be characterized on its face as gross, unmistakable, undebatable, or in manifest disregard of the applicable law and leading to an unjust result." Perini Corp. v. Greate Bay Hotel & Casino, Inc., 129 N.J. 479, 496, 610 A.2d 364 (1992). From our review of the award, the fundamental provisions of the parties' contract, and the claims submitted by Fitzpatrick to the arbitrator, we conclude on the basis of the Perini standard that we must vacate the award.

By specifying how he arrived at the award, the arbitrator has enabled us to observe how he manifestly disregarded the heart of the parties' contract.

To begin with, the award ignores the Guaranteed Maximum Price, which is at the core of the contract and gives it its distinctive character. The contract requires that Tretina absorb all costs, including costs of correction, up to the GMP. As we previously noted, that means that based on a GMP of $2,566,050 Tretina must absorb $446,231 of the unpaid costs, including costs of correction and Fitzpatrick's fee, before costs may be charged to Fitzpatrick. Accepting for the moment the correctness of the itemization in the award, that means that the $269,912.34 that the arbitrator awarded Fitzpatrick is $176, 318.66 short of what Tretina is contractually obliged to pay Fitzpatrick. Crediting Fitzpatrick with the full $446,231 reduces the total net award to Tretina to $83,949.

*50 As a general rule under the contract, once Tretina pays the GMP, Fitzpatrick must absorb all additional costs. Thus, except as noted below, Fitzpatrick is not entitled to be paid claims, however valid, that the arbitrator did not award in full or omitted altogether from the award. Such omissions include full payment of the "retainage" and requisition # 15.

However, the contract contains several significant exceptions to the general rule. One exception that entitles Fitzpatrick to payment of more than the original GMP is based on Article 9 of the contract, which provides for adjusting the GMP to reflect authorized changes in the project. We note, for instance, that the award contains credits to Fitzpatrick totalling $73,701.37 for items found in Change Order # 3. That change order, not yet accounted for in requisition # 15, appears to have produced a post-contract authorized increase in the cost of the project entitling Fitzpatrick to a corresponding increase in the GMP.

We also note that the arbitrator awarded Fitzpatrick $68, 710.97 for "Delays by owner." Section 7.2.2 of Article 7 of the contract provides that "For delays in the Project not the responsibility of the Construction Manager, there will be an equitable adjustment in the fee to compensate the Construction Manager for his increased expenses." It may be equitable for Tretina to pay Fitzpatrick an additional fee for owner-caused delay damages even if doing so will exceed the GMP. We cannot tell if the arbitrator would have so concluded had he properly considered the matter.

There may be other items payable by Tretina above the GMP, such as the 11.5% interest to Fitzpatrick provided for in Article IIX of the May 29, 1987 rider to the contract for the delay in paying his fee until after the work is completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Payton v. New Jersey Turnpike Authority
691 A.2d 321 (Supreme Court of New Jersey, 1997)
Tretina Printing, Inc. v. Fitzpatrick & Associates, Inc.
640 A.2d 788 (Supreme Court of New Jersey, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
619 A.2d 1037, 262 N.J. Super. 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tretina-printing-v-fitzpatrick-njsuperctappdiv-1993.