TRENTON RENEWABLE POWER, LLC v. DENALI WATER SOLUTIONS, LLC (C-000049-20, MERCER COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided January 24, 2022·No. A-3060-20·Published

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-3060-20

TRENTON RENEWABLE POWER, LLC,

Plaintiff,1 APPROVED FOR PUBLICATION January 24, 2022

v.

APPELLATE DIVISION

DENALI WATER SOLUTIONS, LLC,

Defendant-Respondent.

SYMBIONT SCIENCE, ENGINEERING AND CONSTRUCTION, INC.,

Appellant.

Argued November 29, 2021 – Decided January 24, 2022 Before Judges Messano, Accurso, and Enright.

On appeal from an interlocutory order of the Superior Court of New Jersey, Chancery Division, Mercer County, Docket No. C-000049-20.

1 Trenton Renewable Power, LLC is not a party to the appeal.

Daniel J. Cohen argued the cause for appellant (Newman, Simpson & Cohen, LLP, attorneys; Daniel J. Cohen and Daniel C. Stark, on the briefs).

Jeffrey M. Pollock argued the cause for respondent (Fox Rothschild, LLP, attorneys; Jeffrey M. Pollock and Steven J. Link, of counsel and on the brief;

Dominique J. Carroll, on the brief).

The opinion of the court was delivered by MESSANO, P.J.A.D.

Plaintiff Trenton Renewable Power, LLC owns and operates an anaerobic biodigester facility in Trenton (the Trenton Facility). Plaintiff or its predecessors contracted with non-party appellant, Symbiont Science, Engineering and Construction, LLC (Symbiont), an engineering, design and construction firm in Milwaukee, Wisconsin, to design and build out the facility. Defendant Denali Water Solutions, LLC (Denali) contracted with plaintiff to supply organic waste for processing at the Trenton Facility.

Disagreements arose between plaintiff and Denali, and, in March 2020, Denali cited the contract's force majeure provision, claiming the Covid-19 pandemic made it impossible for it to perform as required by the agreement. Denali also alleged the Trenton Facility could not process all categories and quantities of waste Denali was required to deliver under the contract because of fundamental design flaws and inadequate equipment and technology at the plant. Unable to resolve the dispute, plaintiff filed suit.

A-3060-20

The judge denied plaintiff a temporary restraining order, and, before the date set for a hearing on a preliminary injunction, plaintiff eliminated its request for injunctive relief in its July 2020 amended complaint. Denali answered and served plaintiff, Symbiont and other non-parties, Renew Energy A/S LLC (Renew), DSM Environmental Services, Inc. (DSM), and Leidos Engineering & Sciences, Inc. (Leidos), with subpoenas ad testificandum and duces tecum. When plaintiff and most of the non-parties failed to comply, Denali filed a motion to compel.2 Plaintiff, Symbiont, and other non-parties filed cross-motions to quash the subpoena or, alternatively, for a protective order limiting the scope of the request.3 Symbiont asserted compliance would be unduly burdensome, and it also sought to shift the costs of compliance to Denali. The judge entered an order on February 1, 2021, granting Denali's motion to compel and denying the cross-motions to quash. Symbiont moved for reconsideration, which the judge denied, and he subsequently denied Symbiont's motion for a stay pending appeal.

2 In a footnote in its brief, Denali states that DSM did not file opposition to Denali's motion to compel and produced the requested discovery. 3 Symbiont's counsel represented all the non-parties before the motion judge, but only Symbiont moved for leave to appeal. As appropriate, we limit our discussion to Symbiont's arguments.

A-3060-20

We granted Symbiont's motion for leave to appeal and temporarily stayed the discovery order for forty-five days to permit the parties to participate in a conference through the Civil Appeals Settlement Program; the conference was unsuccessful. In the interim, pursuant to Rule 4:41-1, the judge appointed a special discovery master because of the extraordinary volume of discovery-related issues that arose. The order limited the master's authority to resolving discovery disputes between the parties. On September 7, 2021, we entered an order staying further discovery as to Symbiont and accelerated its appeal from the motion judge's February 1 and April 22, 2021 orders.

I.

The record further reveals the judge entered a case management order on September 3, 2020. As expected, the order set forth deadlines for various discovery, with all "fact discovery" to be completed by April 30, 2021. The order did not explicitly mention discovery from non-parties, and it prohibited the filing of any "discovery-related motions" unless first discussed with the court. One week later, on September 10, Denali served its subpoena on Symbiont.

The subpoena demanded Symbiont provide for deposition a corporate designee with knowledge of seventeen "topics," including: the terms of

A-3060-20

Symbiont's agreement with plaintiff, "including the drafting, revision, and execution of the agreement"; "[t]he calculation of Symbiont's guaranteed maximum price to complete the construction to retrofit the Trenton Facility"; and "[a]ll communications with [plaintiff c]oncerning the construction and design" of the facility, "including but not limited to, the construction cost, construction schedule, and design modifications." Attached to the subpoena was a document demand, encompassing thirteen categories, including: all communications between Symbiont and plaintiff regarding Symbiont's efforts to be selected for the project, including "all proposals submitted, all interviews given, all pitches made, and the basis for calculating the guaranteed maximum price"; construction documents for the facility, including any modifications; and documentation of disputes between plaintiff and Symbiont; documents and communications between Symbiont and plaintiff's lenders, and between Symbiont and Renew, DSM and Leidos.

Emails in the record document the dialogue between Symbiont's counsel and Denali's counsel after service of the subpoena. In a November 25, 2020 email, Symbiont's counsel provided a list of fifty-five "custodians who worked on the [p]roject," and designated eleven who were "key personnel." He suggested the parties confer to "identify the custodians whose records [Denali] would like [Symbiont] to initially search," and to otherwise agree on a

A-3060-20

reduction in the scope of the demand. Counsel suggested Denali would bear the costs of compliance if the scope of the discovery demand was not reduced. Denali's counsel responded five days later, stating it was "not prepared to limit [its] requests to certain custodians or search terms." As threatened in the email, Denali filed its motion to compel on December 18.

In its cross-motion to quash the subpoena or for a protective order, Symbiont's counsel, and its in-house general counsel, certified that Symbiont had preliminarily identified four "computer drives" in its electronic filing system that included some information on the Trenton project; those cont ained 40,000 files and approximately 136 gigabytes of data. This did not include the emails of Symbiont's 100 workers, most of whom "had some involvement with" the Trenton project, because the emails were stored elsewhere in the system. Symbiont searched only the emails of the key personnel it had earlier identified and found 30,999 potentially responsive emails. Counsel certified that an outside vendor estimated the cost of processing the data would be $10,000, plus an additional $5330 per month in storage fees. Counsel requested the court quash the subpoena or otherwise limit its scope.

The judge considered oral argument on the motion and entered an order on February 1, 2021, granting Denali's motion and denying all cross-motions. In a written statement of reasons that accompanied the order, the judge first

A-3060-20

Free access — add to your briefcase to read the full text and ask questions with AI

TRENTON RENEWABLE POWER, LLC v. DENALI WATER SOLUTIONS, LLC (C-000049-20, MERCER COUNTY AND STATEWIDE), (N.J. Ct. App. 2022).

TRENTON RENEWABLE POWER, LLC v. DENALI WATER SOLUTIONS, LLC (C-000049-20, MERCER COUNTY AND STATEWIDE) (TRENTON RENEWABLE POWER, LLC v. DENALI WATER SOLUTIONS, LLC (C-000049-20, MERCER COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cavallaro v. Jamco Property Mgt.
760 A.2d 353 (New Jersey Superior Court App Division, 2000)
Piniero v. Div. of State Police
961 A.2d 1 (New Jersey Superior Court App Division, 2008)
Berrie v. Berrie
457 A.2d 76 (New Jersey Superior Court App Division, 1983)
Payton v. New Jersey Turnpike Authority
691 A.2d 321 (Supreme Court of New Jersey, 1997)
Beckwith v. Bethlehem Steel Corp.
440 A.2d 1372 (New Jersey Superior Court App Division, 1981)
Cummings v. Bahr
685 A.2d 60 (New Jersey Superior Court App Division, 1996)
Pomerantz Paper Corp. v. New Community Corp.
25 A.3d 221 (Supreme Court of New Jersey, 2011)
Arcell v. Ashland Chemical Co., Inc.
378 A.2d 53 (New Jersey Superior Court App Division, 1977)
Cypress Point Condominium Association, Inc. v. Adria Towers
118 A.3d 1080 (New Jersey Superior Court App Division, 2015)
Horizon Blue Cross Blue Shield v. State
39 A.3d 228 (New Jersey Superior Court App Division, 2012)
Brugaletta v. Garcia
190 A.3d 419 (Supreme Court of New Jersey, 2018)
Alexander v. Federal Bureau of Investigation
186 F.R.D. 21 (District of Columbia, 1998)
Zubulake v. UBS Warburg LLC
216 F.R.D. 280 (S.D. New York, 2003)
In re Automotive Refinishing Paint Antitrust Litigation
229 F.R.D. 482 (E.D. Pennsylvania, 2005)
Concord Boat Corp. v. Brunswick Corp.
169 F.R.D. 44 (S.D. New York, 1996)