Trench Shoring Services, Inc. v. Saratoga Springs Development, L.L.C.

2002 UT App 300, 57 P.3d 241, 457 Utah Adv. Rep. 8, 2002 Utah App. LEXIS 91, 2002 WL 31119880
CourtCourt of Appeals of Utah
DecidedSeptember 26, 2002
Docket20010784-CA
StatusPublished
Cited by3 cases

This text of 2002 UT App 300 (Trench Shoring Services, Inc. v. Saratoga Springs Development, L.L.C.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trench Shoring Services, Inc. v. Saratoga Springs Development, L.L.C., 2002 UT App 300, 57 P.3d 241, 457 Utah Adv. Rep. 8, 2002 Utah App. LEXIS 91, 2002 WL 31119880 (Utah Ct. App. 2002).

Opinion

OPINION

BILLINGS, Associate Presiding Judge:

¶ 1 Saratoga Springs Development, L.L.C., (Developer) appeals the district court’s orders granting summary judgment and awarding attorney fees to Trench Shoring Services, Inc. (Supplier). We affirm.

BACKGROUND

¶ 2 Developer owned several lots in Sarato-ga Springs, a planned unit development. To obtain the Town of Saratoga Springs’s approval of subdivision plats, Developer agreed to improve the development’s sewer system (the project).

¶ 3 Developer contracted with Larry Price Construction to make the project improvements. Larry Price Construction then subcontracted some of the project work to Freewheeling Enterprises, Inc. (Subcontractor). To perform that work, Subcontractor rented trench shoring equipment from Supplier on August 25,1999. The rental agreement indicated the equipment was to be used on the project. Subcontractor gave Supplier a check for $3,392.57 for the rental. Thereafter, Supplier delivered the rented equipment to the project site.

¶4 On September 1, 1999, the $3,392.57 Subcontractor promised to pay under the rental agreement had been consumed. Supplier continued to rent the equipment to Subcontractor on Subcontractor’s credit account with Supplier. On September 24, 1999, Subcontractor’s check for $3,392.57 was returned for insufficient funds. The following day, Supplier retrieved its equipment from the project site.

¶ 5 After Subcontractor failed to pay for the rented equipment, Supplier filed an action against Subcontractor 1 and Developer. Supplier and Developer filed motions for summary judgment. In its motion, Supplier contended that because Developer failed to require Larry Price Construction, the project contractor, to obtain a payment bond under Utah Code Ann. § 14-2-1 to — 5 (1999) (the Payment Bond Statute), Developer was liable for the rent for the equipment plus interest and collection costs and attorney fees as specified in the rental agreement and under the Payment Bond Statute. In its cross-motion, Developer admitted it failed to require a payment bond, but contended that the Payment Bond Statute did not apply to rent charges for equipment; therefore, Supplier was not entitled to recover under the statute. Developer also contended Supplier was not entitled to recover because Subcontractor’s work failed to comply with project specifications and Supplier’s equipment therefore did not benefit the project.

¶ 6 Following a hearing, the district court granted Supplier’s motion and awarded Supplier the rent it claimed, prejudgment and postjudgment interest, and costs and attorney fees in collecting the judgment. Subsequently, the court also awarded attorney fees to Supplier as a prevailing party under the Payment Bond Statute. Developer now appeals.

ISSUES AND STANDARDS OF REVIEW

¶ 7 Developer argues the district court erred in concluding that Supplier is entitled to recover under the Payment Bond Statute. This issue presents a question of statutory interpretation, which is a question of law. See John Wagner Assocs. v. Hercules, Inc., 797 P.2d 1123, 1126 (Utah Ct.App.1990). Thus, we review the district court’s interpretation for correctness. See id.

¶ 8 Developer also argues the district court erred in awarding Supplier attorney fees under the Payment Bond Statute. We review the district court’s award of attorney fees under this statute, which makes the award discretionary, for an abuse of discre *244 tion. See Bailey-Allen Co. v. Kurzet, 876 P.2d 421, 428 (Utah Ct.App.1994). 2

ANALYSIS

I. Supplier’s Recovery Under the Payment Bond Statute

A. Payment Bond Statute’s Applicability to Rented Equipment

¶ 9 Developer first argues the district court erred in granting Supplier’s motion for summary judgment because the Payment Bond Statute does not provide for the recovery of rent for the equipment used on the project. The Payment Bond Statute provides in relevant part:

(2)(a) ... before any contract exceeding $2,000 in amount for the construction, alteration, or repair of any building, structure, or improvement upon land is awarded to any contractor, the owner shall obtain from the contractor a payment bond complying with Subsection (8)....
[[Image here]]
(3) The payment bond shall be ... for the protection of all persons supplying labor, services, equipment, or material in the prosecution of the work provided for in the contract in a sum equal to the contract price.

Utah Code Ann. § 14-2-l(2)(a), (3) (1999). The statute further provides:

[A]n owner who fails to obtain a payment bond is liable to each person who performed labor or service or supplied equipment or materials under the contract for the reasonable value of the labor or service performed or the equipment or materials furnished up to but not exceeding the contract price.

Id. § 14-2-2(1).

¶ 10 “ ‘We will interpret and apply [a] statute according to its literal wording unless it is unreasonably confused or inoperable.’ ” Cox Rock Prods. v. Walker Pipeline Constr., 754 P.2d 672, 676 (Utah Ct.App.1988) (citation omitted) (alteration in original). Only “ ‘[w]hen uncertainty exists as to the interpretation and application of a statute, [is it] appropriate to look to its purpose in the light of its background and history, and also to the effect it will have in practical application.’ ” John Wagner Assocs. v. Hercules, Inc., 797 P.2d 1123, 1125 (Utah Ct.App.1990) (citation omitted). We conclude the statute’s plain meaning includes rent for the equipment used on the project.

¶ 11 Developer argues that under the statute an owner who fails to require a bond is liable for equipment that is “furnished,” not equipment that is “rented.” Thus, Developer argues the statute protects only equipment sellers. We disagree. The statute unambiguously imposes liability on an owner, who fails to require a contractor to obtain a bond, “to each person” who “supplied equipment ... under the contract.” Utah Code Ann. § 14-2-2(1) (emphasis added). The owner is liable “for the reasonable value of, ... the equipment ... furnished.” Id. (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Po-Cheng Chang v. Soldier Summit Development
2003 UT App 415 (Court of Appeals of Utah, 2003)
Harris v. IES Associates, Inc.
2003 UT App 112 (Court of Appeals of Utah, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2002 UT App 300, 57 P.3d 241, 457 Utah Adv. Rep. 8, 2002 Utah App. LEXIS 91, 2002 WL 31119880, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trench-shoring-services-inc-v-saratoga-springs-development-llc-utahctapp-2002.