[784]*784OPINION
J, Brett Busby, Justice
Appellant Trelltex, Inc. d/b/a Texcel (Texcel) appeals from a judgment awarding appellee and cross-appellant Intecx, L.L.C. d/b/a Rocky Mountain Industrial Technologies (RMIT) $21,589.88 in damages for underpaid commissions occurring between October 1, 2001 and May 1,- 2006, $43,179.76 in treble damages under Colorado law, and' $76,235.10 in reasonable attorney’s fees and court costs. On appeal, Texcel argues that the trial court erred in awarding damages for underpaid commissions between October 1, 2001 and May 1, 2006 because any such damages are barred by the four-year statute of limitations applicable to breach of contract claims. We conclude that the damages awarded- by the trial court are barred by the statute of limitations and therefore reverse and render judgment that RMIT take nothing on these claims. Because we do so, we also reverse the trial court’s award of treble damages under Colorado law and the, trial court’s award of attorney’s fees and court costs.
, In a single issue on cross-appeal, RMIT contends that the trial court erred in concluding that it waived its right to damages from underpaid commissions occurring after May 1, 2006. We hold RMIT waived its right to any damages not barred by the statute of limitations. We therefore affirm the portion of the.trial court’s judgment denying any relief not granted.
. Background
In August 2001, Texcel entered into a Sales Representative Agreement with RMIT. In pertinent part, the agreement provided: “The commission rate is 9% for all sales, existing and new sales.” The agreement went on to state:
NOTE: This'commission' structure has been designed for the. benefit of both parties. It -is understood that, this rate will be evaluated after some time and possibly adjusted as necessary to allow a greater territory expansion for RMIT as warranted and or a different commission rate. , ,
[[Image here]]
From time to time a specific order may suggest a mutually agreed upon commission rate. This will be discussed and agreed upon at the tim.e of quotation.
In a section entitled Revisions, the agreement stated: “Any revisions to this agreement must be done in writing and accepted by both parties.”
In October 2001, Texcel lowered • the commission rate to five percent. The trial court found that the reduction was without RMIT’s knowledge or agreement.- The parties operated under the agreement until Texcel terminated the agreement. The termination went into effect on February 29, 2012. The parties do not dispute that from October 1, 2001 until the agreement was terminated, Texcel paid RMIT a five-percent commission on all sales.
On September 10, 2012, RMIT filed suit against Texcel to collect the underpaid commissions. RMIT asserted that Texcel breached the contract by paying commissions at five percent between January 2008 and February 2012. when the contract called for nine percent.- RMIT also asserted a, violation of a Colorado statute which allowed it collect treble damages on the underpaid commissions.
In its answer, Texcel asserted numerous affirmative . defenses, including . that RMIT’s claims had been waived and were barred by the statute of limitations. Tex-cel also filed a counterclaim seeking a declaratory judgment that the agreement did not require it to obtain written approval from RMIT to change the commission rate [785]*785or expand. RMIT’s territory. Notwithstanding the sales agreement’s revisions section, which required any revisions to be in writing and accepted by both parties, Texcel asserted that the provision entitled “Note” allowed it to adjust the commission rate unilaterally. Alternatively, Texcel sought a declaratory judgment, that the parties had modified the agreement orally.
Following a bench trial, the trial court rendered judgment in favor of RMIT. The court awarded $21,589.88 for underpaid commissions from October 1, 2001 to May 1, 2006 and $43,179.76 in additional damages under the Colorado statute. It also awarded RMIT $76,235.10 in reasonable attorneys’ fees and court costs. Subsequently, the trial court signed findings of fact and conclusions of law. Texcel filed a notice of appeal, and RMIT filed a notice of cross-appeal.
Analysis
I. The damages awarded by the trial court for commissions underpaid from October 1, 2001 to May 1, 2006 are barfed by limitations.
In its first issue, Texcel argues that the trial court erred in awarding damages for alleged underpayments occurring between October 1, 2001 and May 1, 2006 because any such damages are barred by the statute of limitations. We begin our analysis by considering whether Texcel preserved this issue for our review.
Limitations is an affirmative defense that must be specifically pleaded and proved. Intermedics, Inc. v. Grady, 683 S.W.2d 842, 845 (Tex.App.-Houston [1st Dist.] 1984, writ ref'd n.r.e.). In addition, a party asserting an affirmative defense in a bench trial must request findings in support of that defense in order to avoid waiver on .appeal. Sears, Roebuck & Co. v. Nichols, 819 S.W.2d 900, 907 (Tex.App.Houston [14th Dist.] 1991, writ denied). When the trial court makes findings that do not establish any element of a defense, the party relying upon that defense must file- a request for additional findings to avoid waiver of that defense on appeal. Id. .
' In this case, Texcel’s pleadings raised the statute of limitations repeatedly as an affirmative defense. Texcel also requested findings of fact and conclusions óf law, which the trial court issued.' In firiding of fact 6, the trial court concluded Texcel underpaid commissions from October 2001 until February 2012. In finding of fact nine, the trial court included a chart in which it calculated the amount of commissions that Texcel owed but did not- pay RMIT in each year from 2001 until 2012. In conclusion of law three, the trial 'cdurt concluded that these - underpayments breached the parties’ contract. Because the trial court concluded that RMIT had waived its right to receive underpaid commissions owed after May 1, 2006, it awarded RMIT damages for the underpaid commissions only from October 1, 2001 to May 1, 2006. In conclusion of law eleven, the trial court concluded that Texcel “failed to prove any of its alleged affirmative defenses other than waiver.” No motion for new trial, objection to the trial court’s findings of fact or conclusions of law, or request for additional or amended findings or conclusions appear in our record, and the parties do not argue that any was made.
The trial court’s findings establish elements of Texcel’s limitations defense by charting when the underpayments .occurred. No party has contended that any other disputed facts needed to be resolved in order to determine whether RMIT’s claims for breach of contract regarding those underpayments were barred by limitations. For these reasons, no request for additional findings was necessary to pre[786]*786serve Texcel’s limitations issue for appellate review. See Sears, Roebuck & Co., 819 S.W.2d at 907-08 (holding defense of plaintiffs negligence was not waived by-defendant’s failure to request negligence finding because trial court had included adverse finding on element of proximate cause); see also Limbaugh v. Limbaugh, 71 S.W.3d 1, 7 (Tex.App.-Waco 2002, no pet.) (explaining findings.are required only when material factual disputes impact ultimate or controlling issues); Howard P. Foley Co. v. Cox, 679 S.W.2d 58, (Tex.App.-Houston [14th Dist.] 1984, no writ) (“The trial court is not required to make findings of fact as to undisputed facts.”). Nor was it necessary for Texcel to take exception to the trial court’s adverse conclusion of law that Texcel had failed to prove its defense in order to challenge that conclusion on appeal. See Tex.R.App. P. 33.1(c); Sears, Roebuck & Co., 819 S.W.2d at 903 (“Conclusions of law are always renewable by an appellate court.”); see also Sammons v. Elder, 940 S.W.2d 276, 280 (Tex.App.-Waco 1997, writ denied); W. Wendell Hall et. al., Hall’s Standards of Review in Texas, 42 St. Mary’s L.J. 3, 243 (2010).1 .
Having concluded that Texcel preserved the limitations issue for our review, we next analyze whether, in light of the trial court’s unchallenged findings about when the underpayments occurred, the trial court’s -legal conclusion that Tex-cel failed to prove its defense is erroneous. The statute of limitations for breach-of-contract actions is four years from the date of accrual. Tex. Civ. Prac. & Rem. Code Ann. § 16.051 (West 2015). An action for breach of contract accrues immediately upon breach. Barker v. Eckman, 213 S.W.3d 306, 311 (Tex.2006). “A party breaches a contract by failing to perform when that party’s performance is due.” E.P. Towne Ctr. Partners, L.P. v. Chopsticks, Inc., 242 S.W.3d 117, 123 (Tex.App.-El Paso 2007, no pet.).
If the parties’ agreement contemplates a continuing contract for performance, the limitations period usually does not commence until the contract is fully performed. Intermedics, Inc. v. Grady, 683 S.W.2d 842, 845 (Tex.App.-Houston [1st Dist.] 1984, writ ref'd n.r.e.). When the terms of an agreement call for fixed, periodic payments, however, a separate cause of action arises for each missed payment. Slusser v. Union Bankers Ins. Co., 72 S.W.3d 713, 717 (Tex.App.-Eastland 2002, no pet.). “Thus, a suit for the breach of a contract requiring payment in [787]*787periodic installments may include all payments due within the four-year statute of limitations period, even if the initial breach was beyond the limitations period. Recovery of any payment more than four years overdue is barred.” Spin Doctor Golf, Inc. v. Paymentech, L.P., 296 S.W.3d 354, 362 (Tex.App.-Dallas 2009, pet. struck). Whether a claim is barred by the statute of limitations is a legal question we review de novo. Hunt Oil Co. v. Live Oak Energy, Inc., 313 S.W.3d 384, 387 (Tex.App.-Dallas 2009, pet. denied).
Texcel contends that because RMIT filed suit on September 10, 2012, it cannot recover any purported underpayments that occurred before September 10, 2Q08.2 The sales agreement provided that payments were due on a monthly basis: “Commission checks are paid on the last day of the following month in which the commissions were earned.” Accordingly, a breach occurred and a cause of action arose for each underpayment occurring between October 1, 2001 and May 1, 2006. See Slusser, 72 S.W.3d at 717. The trial court erred by awarding damages for underpaid commissions occurring during this time frame because recovery of any such underpayments was barred by the four-year statute of limitations. See Tex. Civ. Prac. & Rem.Code Ann. § 16.051.
RMIT argues that the agreement between the parties was a continuing’ contract and thus the limitations period did not commence until Texcel terminated the agreement in 2012. This argument misses the mark for the reasons explained in Davis Apparel v. Gale-Sobel, a Division of Angelica Corp., 117 S.W.3d 15 (Tex.App.-Eastland 2003, no pet.). In Davis Apparel, Gale-Sobel paid Davis Apparel a fifteen-percent commission rate from 1994 to 1997. Id. at 17. Believing it was entitled to receive a commission of twenty percent, Davis Apparel filed suit against Gale-So-bel to recover the underpaid commissions on December 1, 2000. Id. Gale-Sobel argued that it never agreed to pay a‘twenty-percent commission rate and also raised the statute of limitations as an affirmative defense. Id. The jury found that Gale-Sobel agreed to pay Davis Apparel a twenty-percent commission and awarded damages in the amount of $28,467.68. Id. But the jury also found that the earliest date Gale-Sobel failed to comply with the agreement was March 4, 1994. Id. Based on this finding, the trial court rendered a take-nothing judgment against Davis Apparel, concluding all damages were barred by the statute of limitations. Id.
On appeal, Davis Apparel argued that the agreement was a continuing contract that was not breached until it expired in May 1997. Id. at 18. The Eastland Court of Appeals took a different view, concluding that the evidence supported the jury’s finding that the first breach occurred in March 1994. Id. The court of appeals therefore affirmed the trial court’s take-nothing judgment with regard to claims arising more than four years before suit was filed (before December 1, 1996), but reversed the judgment for claims arising after that date and remanded those claims for trial. Id. at 19. The court of appeals explained:
[Ijrrespective of the jury’s determination of when the earliest breach of the contract occurred, limitations should not [788]*788bar claims for damages arising after December . 1, 1996. The evidence in the record demonstrates that the parties treated their agreement as an installment contract whereby Gale-Sobel made ; monthly payments - of commissions to .Davis Apparel. As,we noted in Slusser, a separate cause of action arises for each missed payment under an. installment contract. .
Id.
As in Davis Apparel, the agreement in this case féqüired 'periodic commission payments, and recovery for any underpayments occurring more than four years before RMIT filed suit is therefore barred by the statute of limitations. During oral argument, RMIT asserted that the payments Texcel was required to make under the agreement were not fixed because they were based on commissions that varied from month to month. Although the payments varied in amount, they were fixed in that the agreement required them to be made using a specified formula on particular dates. The commission payments also varied in amount in Davis Apparel, yet the court concluded that payments missed outside the four-year limitations period were barred. 117 S.W.3d at 18.3 See also Spin Doctor Golf, Inc., 296 S.W.3d at 362-63 (collecting and discussing cases applying the breach-of-contract accrual rule to payments calculated and due on a periodic basis, and. holding that claims for failures to make payments within four years before suit were not barred by limitations but that the claim for initial breach, which occurred outside that period, was barred).
For these reasons, we sustain Texcel’s first issue. We therefore reverse the trial court’s award of $21,589.88 iii damages to RMIT for any underpaid commissions Occurring between October 1, 2001 and May 1, 2006.- As a result, we also reverse the trial court’s award of $43,179.76 in additional damages for underpaid commissions under Colorado law. We likewise reverse the trial’s award of $76,235.10 in reasonable attorneys’ fees and court costs because RMIT is no longer a prevailing party on its breach of contract claim and has not recovered damages. See Ashford Partners, Ltd. v. ECO Res., Inc., 401 S.W.3d 35, 40 (Tex.2012) (“[W]e have said that to qualify for fees under the statute, a litigant must' prevail on a breach of contract claim and recover damages”); see also Tex. Civ. Prac. & RenxCode Ann. § 38.001 (West 2015). We render judgment that RMIT take nothing on these claims.4
[789]*789II. The trial court did not err in concluding that RMIT waived its right to commissions underpaid from September 2008 to February 2012.
In its sole issue on cross-appeal, RMIT argues “there is no evidence or insufficient evidence” that it waived by implication its right to receive any commissions not paid between May 1, 2006 and February 29, 2012. RMIT asks us to reverse the trial court’s conclusion of law that Texcel proved waiver and to render judgment in its favor for $128,153.27 in commissions underpaid during that period. RMIT also asks us to reverse the trial court’s factual findings that RMIT received monthly statements from Texcel after May 1, 2006 from which it could have calculated that it was being paid only five-percent commissions, and that RMIT never complained about the underpaid commissions before the agreement was terminated. As explained below, however, RMIT’s brief does not demonstrate that the evidence is insufficient to support these findings. Instead, RMIT largely argues that these findings are insufficient to support the legal conclusion that an implied waiver occurred. We focus our analysis on that question.
The sales agreement calls'for commissions to be paid on the last day of the month following that in which the commissions were earned. Because RMIT filed suit on September 10, 2012, any underpaid commissions due from May 1, 2006 through August 31, 2008 are barred.by the' four-year statute of limitations, as discussed above.5 We therefore address only whether the trial court erred in concluding that RMIT waived by implication its right to recover any underpaid commissions due between September 2008 and the agreement’s termination in February 2012.6 ■
A. Standard of review
When, as in this case, specific findings of fact and conclusions of law are filed and a reporter’s record is before the appellate court, the findings, will be sustained if there is evidence to support them, and the appellate court will review the legal conclusions drawn.from the facts found to determine their correctness. CD. Holdings, Inc. v. H.D.H. Land & Timber, L.P., 407 S.W3d 856, 859 (Tex.App.-Tyler 2013, no pet.). Findings of fact have the same force and dignity as a jury’s verdict and are reviewable under the same standards of legal and factual sufficiency. Foley v. Capital One Bank, N.A., 383 S.W.3d 644, 646 (Tex.App.-Houston [14th Dist.] 2012, no pet.).
Texcel bore the burden to prove its affirmative defense of waiver. Accordingly, we review RMIT’s legal sufficiency challenge under a “no evidence” standard. City of Keller v. Wilson, 168 S.W.3d 802, 810 (Tex.2005). A no-evidence, challenge will be sustained when (a) there is a com-[790]*790píete absence of evidence of a vital fact, (b) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact, (c) the evidence offered to prove a vital fact is no more than a mere scintilla, or (d) the evidence conclusively establishes the opposite of the vital fact. Serv. Corp. Intern. v. Guerra, 348 S.W.3d 221, 228 (Tex.2011).
We review a trial court’s conclusions of law de novo. State v. Heal, 917 S.W.2d 6, 9 (Tex.1996); Potcinske v. McDonald Prop. Inn, ltd., 245 S.W.3d 526, 529 (Tex.App.-Houston [1st Dist.] 2007, no pet.). When performing a de novo review, we exercise our own judgment and redetermine each legal issue. Sembera v. Petrofac Tyler, Inc., 253 S.W.3d 815, 822 (Tex.App.-Tyler 2008, pet. denied). To make this determination, we consider whether the conclusions are correct based on the facts from which they are drawn. Potcinske, 245 S.W.3d at 529.
In reviewing the factual sufficiency of the evidence, we must examine the entire record, considering both the evidence in favor of, and contrary to, the challenged findings. See Maritime Overseas Corp. v. Ellis, 971 S.W.2d 402, 406-07 (Tex.1998); Cain v. Bain, 709 S.W.2d 175, 176 (Tex.1986). When a party challenges the factual sufficiency of the evidence supporting a finding for which it did not have the burden of proof, we may set aside the verdict only if it is so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. See Ellis, 971 S.W.2d at 407; Barnhart v. Morales, 459 S.W.3d 733, 745 (Tex.App.-Houston [14th Dist.] 2015, no pet.). The amount of evidence necessary to affirm is far less than the amount necessary to reverse a judgment. Barnhart, 459 S.W.3d at 745. This Court is not a fact-finder. Id. (citing Ellis, 971 S.W.2d at 407). Instead, the jury is the sole judge of the credibility of the witnesses and the weight to be given their testimony. Id. We may not, therefore, pass upon the witnesses’ credibility or substitute our judgment for that of the jury, even if the evidence would also support a different result. Id. If we determine the evidence is factually insufficient, we must detail the evidence relevant to the issue and state in what regard the contrary evidence greatly outweighs the evidence in support of the verdict; we need not do so when affirming a jury’s verdict. Id. (citing Gonzalez v. McAllen Med. Ctr., Inc., 195 S.W.3d 680, 681 (Tex.2006) (per curiam)).
B. Applicable law
Waiver may be asserted as an affirmative defense against a party who intentionally relinquishes a known right or engages in intentional conduct inconsistent with claiming that right. Singleton v. Elliott, 14-13-00040-CV, 2014 WL 1922260, at *4 (Tex.App.-Houston [14th Dist.] May 13, 2014, no pet.). The elements of waiver include (1) an existing right, benefit, or advantage held by a party; (2) the party’s actual knowledge of its existence; and (3) the party’s actual intent to relinquish the right, or intentional conduct inconsistent with the right. Ulico Cas. Co. v. Allied Pilots Ass’n, 262 S.W.3d 773, 778 (Tex.2008).
Waiver is largely a matter of intent, and for implied waiver to be found through a party’s conduct, intent must be clearly demonstrated by the surrounding facts and circumstances. In re Gen. Elec. Capital Corp., 203 S.W.3d 314, 316 (Tex.2006). “Silence or inaction, for so long a period as to show an intention to yield the known right, is also enough to prove waiver.” Tenneco Inc. v. Enter. Prods. Co., 925 S.W.2d 640, 643 (Tex.1996). Waiver is ordinarily a question of fact, but when the surrounding facts and circumstances are undisputed, the question becomes one of [791]*791law. Jerrigan v. Langley, 111 S.W.3d 153, 156-57 (Tex.2003).
C. Implied waiver
In its fourth conclusion of law, the trial court stated that “Texeel has proven RMIT waived its rights to receive the underpaid commissions that were owed to RMIT by Texeel after May 1, 2006.” RMIT asserts that the evidence and findings show “mere” acceptance of payments and possibly a lack of care on its part, which are insufficient to support a legal conclusion of implied waiver. RMIT asserts there is “no evidence or insufficient evidence” of its intent to yield its right to payment of nine-percent commissions. Thus, according to RMIT, we must reverse the trial court’s conclusion that Texeel proved waiver.
We conclude that the findings and supporting evidence provide a sufficient basis for the trial court’s conclusion that RMIT waived its right to collect any underpaid commissions after May 1, 2006. The evidence at trial demonstrated, and the trial court found, that RMIT received commission payments at a rate of five percent beginning in October 2001. The trial court also found that after May 1, 2006, RMIT received monthly statements showing the amount of monthly sales and the amount of commissions paid. From this information, the trial court found, RMIT could have calculated it was being paid only five-percent commissions, though it never made those calculations.7 The trial court also found that RMIT did not complain of underpaid commissions before the agreement was terminated in 2012. These findings (numbered twelve through fifteen) are supported by the monthly statements themselves, which were introduced into evidence, and by the testimony of RMIT partner Robert Merkin that he could have calculated the commission rate from the sales reports but.did not do so until the contract was. terminated in February 2012.
As previously explained, silencé or inaction for so long a period as to show an intention to yield the known right is sufficient to prove waiver. See Tenneco, 925 S.W.2d at 643. Tenneco addressed a contractual provision prohibiting transfer’ of an ownership interest in a fractionation plant unless the transferee agreed to deliver at least 31,000 barrels of natural,gas liquids per day. Id. at 642. The Texas Supreme Court held' that one group of owners waived their complaint concerning a transferee’s failure to meet the delivery obligation by accepting the transferee’s delivery of substantially less than the required 31,000 barrels per day for three years without complaint. Id. at 643.
Similarly, RMIT’s conduct in this ease together with 'its silence or inaction — accepting commission payments calculated at a rate of five percent for nearly six years without complaint — was intentional conduct inconsistent with claiming a known right to receive commissions at a rate of nine percent. We therefore hold that the evidence summarized above is legally and factually sufficient to" support the ’ trial court’s findings and its conclusion of waiver. See Shaver v. Schuster, 815 S.W,2d 818, 825 (Tex.App.-Amarillo 1991, no writ) (holding waiver of contract provision by conduct was fact question regarding party’s intent as revealed by reasonable inferences drawn from the evidence, which was [792]*792sufficient to support jury’s finding of waiver).
RMIT argues that Texeel was required to prove that RMIT actually (1) calculatéd the percentage of the commissions it was paid, (2) knew that the legal effect of those payments was to breach the contract, and (3) intended to accept the non-compliant payments. RMIT is incorrect. Waiver requires either actual intent to relinquish a right or intentional conduct inconsistent with claiming the right— not both.8 Ulico Cas. Co., 262 S.W.3d at 778; Tenneco Inc., 925 S.W.2d at 643. As the Restatement of Contracts explains, “[t]het common definition of waiver may lead to the incorrect inference. that the promisor must know his legal rights and must intend the legal effect of the promise [to waive a condition]. But ... it is sufficient if he has reason to know the essential facts.” Restatement (Second) of Contracts § 84 cmt. b (1981); see id. §§ 93, 247.9 Proof regarding a party’s actual understanding of the legal consequences of those facts is not required, as parties are presumed to know and understand the legal effect of their contracts and waivers.10
[793]*793To support its position; RMIT relies on our opinion in Clear Lake Center, L.P. v. Garden Ridge, L.P., 416 S.W.3d 527 (Tex.App.-Houston [14th Dist.] 2013, no pet.). We conclude, however, that Clear Lake supports our holding. In that case, Garden Ridge claimed that -from 2003 to 2009, Clear Lake charged it impermissible fees under a commercial real property lease. Id. at 532-34. Clear Lake raised several affirmative defenses, including waiver. Id. at 533. We held that Garden Ridge’s payments did not constitute waiver because Garden Ridge paid the management fee without knowing that the fee included charges not authorized by the lease, and indeed the fee' statements suggested the entire fee was proper. Id. at 543. We said, “Clear Lake cités no case holding that a party to a contract waived a right when the plaintiff did not actually know facts pertinent to the breach.” Id'.' at 542. We then examined Tenneco and explained that actual knowledge of the facts pertinent to that breach — including the’ delivery of less than 31;O0O barrels per day — was key to establishing waiver. Id. RMIT urges that this discussion supports its argument.
In this case, however, the key to establishing waiver identified in Tenneco and Clear Lake is. present. . .The trial court found that after May 1, 2006, RMIT received monthly ‘ statements from Texcel showing both the amount of sales revenue and the amount of commissions paid. Each month’s commissions amounted to five percent of the sales revenue, and there is no dispute that RMIT knew the contract entitled it to a commission rate of nine percent for all sales. RMIT thus had actual knowledge of the facts pertinent to the breach — that is, of material facts sufficient to support a legal conclusion that the contract had been breached 11 — as early as May 1, 2006, and it had been paid commissions; at a rate of five percent since October 2001.12 Yet RMIT did not complain of the alleged underpaid commissions until 2012 — long after the statute of limitations had run on many of the commission payments and the contract had terminated.13 [794]*794This evidence supports a reasonable inference that RMIT waived its right to the underpaid commissions. See Tenneco Inc., 925 S.W.2d at 643; Clear Lake Ctr., L.P., 416 S.W.3d at 542.
To buttress its argument that the trial court erred in concluding Texcel proved waiver, RMIT points to the trial court’s findings of fact sixteen through nineteen, which state:
16. RMIT never expressly relinquished its right to be paid the 9% commission called for in the contract.
17. RMIT never approved the unilateral reduction of its commission from 9% to 5% under the contract.
18. RMIT never intended to make TEXCEL’s unilateral reduction of the commission from 9% to 5% valid.
19. RMIT never agreed to modify or revise the commission rate under its contract with TEXCEL from 9% to 5%. In considering these findings, we are
bound to assume the validity of the trial court’s judgment. Leonard v. Eskew, 731 S.W.2d 124, 131 (Tex.App.-Austin 1987, writ ref'd n.r.e.); see Vickery v. Comm’n for Lawyer Discipline, 5 S.W.3d 241, 251-52 (Tex.App.-Houston [14th Dist.] 1999, pet. denied). Thus, we must construe the judgment and any attendant findings of fact and conclusions of law in a way that sustains the judgment if we are able to do so without doing-violence to the language used. Matter of Marriage of Merrikh, 14-14-00024-CV, 2015 WL 2438770, at *5 (Tex.App.-Houston [14th Dist.] May 19, 2015, no. pet. h.). So construed, findings sixteen through nineteen address whether RMIT expressly waived its right to receive commissions at a rate of nine percent, not whether RMIT waived its right by implication — a defense that the trial court addressed separately in findings twelve through- fifteen.14 Based on- findings twelve through fifteen, the trial court correctly concluded that Texcel impliedly waived its right to receive any underpaid commissions not barred by the statute of limitations. We overrule RMIT’s issue on cross-appeal. Because we do so, we need not address whether the trial court erred in finding' that Texcel breached the agreement and denying Texcel’s counterclaim for declaratory relief.
Conclusion
Having held that the damages awarded by the trial court are barred by the statute of limitations, we reverse the trial court’s judgment awarding $21,589.88 for breach of contract by underpaying commissions between October 1, 2001 and May 1, 2006, together with the related awards of additional damages under. Colorado law, attorney’s fees, and court costs. We render judgment that RMIT take nothing on these claims. In addition, because Texcel proved RMIT waived any right to damages not barred by the four-year limitations period, we affirm the portion of the judgment denying all other requested relief.
(Frost, C.J., dissenting)