Treen Construction, Inc. v. Reasonover

30 So. 3d 933, 9 La.App. 5 Cir. 438, 2009 La. App. LEXIS 2207, 2009 WL 5125267
CourtLouisiana Court of Appeal
DecidedDecember 29, 2009
Docket09-CA-438
StatusPublished

This text of 30 So. 3d 933 (Treen Construction, Inc. v. Reasonover) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Treen Construction, Inc. v. Reasonover, 30 So. 3d 933, 9 La.App. 5 Cir. 438, 2009 La. App. LEXIS 2207, 2009 WL 5125267 (La. Ct. App. 2009).

Opinion

MARC E. JOHNSON, Judge.

_JjThe Plaintiff, Treen Construction, Inc., appeals a judgment in favor of the Defendant, Charles Reasonover, in a construction contract dispute. We affirm.

In November of 2005, the Plaintiff began work on the Defendant’s home to repair damages sustained by Hurricane Katrina. *935 Pursuant to an oral agreement, the Plaintiff billed the Defendant for the costs of the job, plus 10% overhead and 10% profit. The Defendant paid approximately $61,000 during the course of the work, but refused to pay the last five invoices.

On October 13, 2006, the Plaintiff filed a lien in the amount of $5,647.34 against the property, and also filed a petition to enforce the lien. The Defendant filed an answer and reconventional demand contending that no further amounts were due, and seeking damages suffered as a result of errors and overcharges in the amount of $11,613.07.

The hen was subsequently dismissed because the contract was not in writing. A judge trial was held on the merits of the claims on November 6, 2008, after which judgment was rendered in favor of the Plaintiff for $721.43. The trial lajudge disallowed the Plaintiffs charges of $4,925.91 that were related to the kitchen cabinets, the granite counter tops, the patio doors, and for double billing the Defendant for profit and overheard from his son’s company. On the reconventional demand, the trial judge awarded the Defendant $4,312.73. 1

On appeal, the Plaintiff asserts that the trial judge erred in denying all but $721.43 of its claim. It further asserts that the trial judge erred in granting refunds on invoices that the Defendant previously paid, and thus waived his right to contest the payments, and in granting the Defendant’s reconventional demand regarding the patio doors, cabinets, and countertops. He also asserts that the trial judge erred in disallowing the profit and overhead charge for the SW Louisiana Permit job, in awarding costs for the cost of cleaning air conditioning ducts, and in awarding costs to replace the security system.

Contractor’s burden of proof

The trial judge found that the Plaintiff failed to produce any invoices to support its claims. The Plaintiff argues that the invoices were received into evidence at the trial in connection with the testimony of John Treen.

The standard of review in a cost plus contract case is manifest error, or whether the findings of fact were clearly wrong. Bishop v. Shaw, 43,137, p. 3-4 (La.App. 2 Cir. 3/12/08), 978 So.2d 568, 571-572; Burdette v. Drushell, 01-2494, p. 5 (La.App. 1 Cir.12/20/02), 837 So.2d 54, 59, writ denied, 03-0682 (La.5/16/03), 843 So.2d 1132.

In reviewing the case for manifest error, where there is a conflict in the testimony, reasonable evaluations of credibility and reasonable inferences of fact should not be disturbed upon review, even though the appellate court may feel that |4its own evaluations and inferences are as reasonable. Rosell v. ESCO, 549 So.2d 840, 844 (La.1989); Himel v. State ex rel. Dept. of Transp. and Development, 04-274, p. 8 (La.App. 5 Cir.1/12/04), 887 So.2d 131,137, writ denied, 04-2802 (La.3/18/05), 896 So.2d 999. The issue to be resolved by the reviewing court is not whether the factfinder was right or wrong, but whether its conclusion was a reasonable one. Stobart v. State, Through DOTD, 617 So.2d 880, 882 (La.1993); Himel, 04-274 at 8, 887 So.2d at 138; LeBlanc v. Baxter, 05-33, p. 19 (La.App. 5 Cir. 5/31/05), 905 So.2d 415, 426. Thus, where two permissible views of the evidence exist, the factfinder’s choice between them cannot be manifestly erroneous or clearly wrong. Stobart, 617 So.2d at 882; Himel, 04-274 at 8, 887 So.2d at 138. Only where the documents *936 or objective evidence so contradict a witness’s story, or the story itself is so internally inconsistent or implausible on its face that a reasonable factfinder would not credit the witness’s story, may the court of appeal find manifest error, even in a finding purportedly based upon a credibility determination. Rosell, 549 So.2d at 844-45; Himel, 04-274 at 8, 887 So.2d at 138.

In a cost plus contract, the owner agrees to reimburse the contractor for the costs of material and labor and to pay a percentage of those costs as his profit. Bishop, 43,137 at 5, 978 So.2d at 572; Burdette, 01-2494 at 5, 837 So.2d at 59. Under a cost plus contract, the contractor may charge only those costs that are shown to be reasonable and proper. Bishop, 43,137 at 5, 978 So.2d at 572; Burdette, 01-2494 at 5, 837 So.2d at 59. When the owner denies his indebtedness to the contractor, the contractor has the burden to itemize and prove his costs. Bishop, 43,-137 at 5, 978 So.2d at 572; Burdette, 01-2494 at 5, 837 So.2d at 59.

|,-,The Plaintiff relies on the unpublished case of Meg-A Builders, L.L.C. v. Maggio, 2008 WL 5377614, 4 (La.App. 1 Cir. 12/23/08). There, the court summarized:

Meg-A Builders responded to the Maggios’ letter requesting an itemization of the expenses with an invoice that detailed labor and materials. The trial court evaluated each item of expense and deducted the markup of forty percent on labor for which Meg-A Builders failed to offer evidence to support. While the Maggios complain that the itemization provided to them by Meg-A Builders and introduced into evidence does not set forth the actual material lists, receipts, check stubs showing payment, labor time records, invoices of subcontractors, or other records as proof to substantiate the charges billed to them, they neither demanded such through discovery nor presented evidence challenging Meg-A Builders’ testimony and itemization of the expenses. At trial, the primary issue was whether the parties had entered into a costs plus contract. [Emphasis added.]

The court found no manifest error in the judgment granting the contractor relief. However, the dissent disagreed because the Plaintiff failed to present any evidence proving that it paid the costs listed in the invoice sued upon. It cited Burdette. It also cited M. Carbine Restoration, Ltd. v. Sutherlin, 544 So.2d 455, 458-59 (La.App. 4 Cir.1989), writ denied,, 547 So.2d 355. In that case, the Fourth Circuit Court of Appeal stated:

Once the existence of a cost-plus contract has been established, the contractor also has a duty to submit an itemization of each and every expenditure made during the course of the project because there is an implicit agreement between the parties that the costs will be reasonable. Presentation of invoices and statements of accounts, accompanied by proof of payment, is the proper method of proving the cost of improvements. Proof of payment can be established by presentation of invoices marked “paid.” [Emphasis added.]

Id., 544 So.2d at 458-59.

We agree with the decisions in Burdette, Bishop,M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bishop v. Shaw
978 So. 2d 568 (Louisiana Court of Appeal, 2008)
Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)
Burdette v. Drushell
837 So. 2d 54 (Louisiana Court of Appeal, 2002)
M. Carbine Restoration, Ltd. v. Sutherlin
544 So. 2d 455 (Louisiana Court of Appeal, 1989)
LeBlanc v. Baxter
905 So. 2d 415 (Louisiana Court of Appeal, 2005)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Red Barn Chemicals, Inc. v. Lassalle
350 So. 2d 1315 (Louisiana Court of Appeal, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
30 So. 3d 933, 9 La.App. 5 Cir. 438, 2009 La. App. LEXIS 2207, 2009 WL 5125267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/treen-construction-inc-v-reasonover-lactapp-2009.