Travelers Property Casualty Company of America v. Rubenstein's Contract Carpet LLC
Opinion
1 2 3 4
5 6 7 UNITED STATES DISTRICT COURT 8 WESTERN DISTRICT OF WASHINGTON AT SEATTLE 9 10 TRAVELERS PROPERTY CASE NO. C19-1175 MJP CASUALTY COMPANY OF 11 AMERICA, ORDER GRANTING LEAVE TO AMEND 12 Plaintiff, 13 v. 14 RUBENSTEIN’S CONTRACT CARPET LLC et al., 15 Defendants. 16 17 18 THIS MATTER comes before the Court on Defendant’s motion to amend its answer to 19 the Second Amended Complaint, affirmative defenses, amended counterclaim, and third-party 20 complaint. (Dkt. No. 53.) Having considered the motion, the response (Dkt. No. 58), the reply 21 (Dkt. No. 59), and other relevant documents, the Court GRANTS the motion. 22 23 24 1 Background 2 This dispute arises out of an issue with the flooring at the 13 Coins Restaurant in Seattle 3 that was installed by the Defendant, North American Terrazzo (“NAT”). (Dkt. No. 41 (“SAC”), 4 ¶¶ 3.2-3.9.) Approximately four months after the flooring was installed, 13 Coins notified NAT
5 that there were problems with its work due to faulty material or incorrect installation. (Id. ¶ 3.9.) 6 13 Coins Restaurant contends its service was disrupted and it incurred significant costs when 7 NAT allegedly failed to correct the defects. (Id. ¶¶ 3.15.) On December 4, 2018, NAT tendered 8 the 13 Coins Restaurant loss to Plaintiff, Travelers Property Casualty Company of America 9 (“Travelers”). (Id. ¶ 3.17.) 10 On April 30, 2020, all parties to this suit participated in a mediation of claims which had 11 informally been made against NAT, and settlements were reached between the owners of 13 12 Coins, the general contractor Sodo Builders, NAT, and third-party defendant Terrazzo Marble 13 Supply Co., of Illinois. (Dkt. No. 53 at 2.) NAT has now made all payments required of it and 14 contends it is entitled to recover the settlement and other related damages from Travelers. (Id. at
15 3.) NAT seeks to amend its Answer to Travelers’ Second Amended Complaint to assert that 16 with the advent of the settlement, there is now a justiciable controversy concerning Travelers’ 17 liability for that settlement. Additionally, NAT desires to amend its counterclaim to remove the 18 contingent nature of it and seek damages, which include the April 30, 2020 settlement amounts. 19 (Id.) 20 Discussion 21 I. Legal Standard 22 Federal Rule of Civil Procedure 15 provides leave to amend should be granted freely 23 “when justice so requires.” Fed. R. Civ. P. 15(a)(2). In determining whether leave to amend is
24 1 appropriate, the district court should consider the presence of bad faith, undue delay, prejudice to 2 the opposing party, and/or futility. Owens v. Kaiser Found. Health Plan, 244 F.3d 708, 712 (9th 3 Cir. 2001). Generally, the analysis of these elements should be “performed with all inferences in 4 favor of granting the motion.” Griggs v. Pace Am. Group, Inc., 170 F.3d 877, 880 (9th Cir.
5 1999). Prejudice to the opposing party carries the greatest weight, and absent prejudice or a 6 strong showing of any of the remaining factors, there is a presumption in favor of granting leave 7 to amend. Eminence Capital, LLC v. Aspeon, Inc., 316 F.3d 1048, 1052 (9th Cir. 2003). 8 Granting the motion to amend will not prejudice Plaintiff. Indeed, Travelers’ opposition 9 does not mention prejudice, apparently conceding the issue. (See Dkt. No. 58.) Further, 10 Travelers has failed to make a “strong showing of any of the remaining factors.” First, there is 11 nothing to suggest that NAT brings this motion in bad faith. Instead, it seeks to amend its 12 answer and counterclaims to encompass the recent settlement, a relevant factual development 13 that NAT immediately communicated to Travelers. (Dkt. No. 53 at 4.) Again, NAT agrees that 14 the recent settlement, “entered into without Travelers’ consent . . . does in fact raise new
15 coverage issues.” (Dkt. No. 58 at 12.) Second, there is no undue delay. The final settlement 16 was executed and circulated on May 26, 2020, less than two weeks before NAT filed the instant 17 motion. (Dkt. No. 53 at 4.) And the Parties remain in the discovery stage of this action, with 18 more than five months left before trial. (Dkt. No. 52.) 19 Finally, NAT’s amended complaint is not futile. Should NAT prevail on any of its 20 currently pleaded causes of action and establish the reasonableness of the settlement, it will be 21 entitled to recover indemnity for the settlement either in tort, or in contract. While difficult to 22 follow, Travelers appears to argue that because there has always been a justiciable controversy, 23 NAT should not be permitted to amend their Answer and Counterclaims to “agree that with the
24 1 advent of the settlement, there is now a justiciable controversy.” (Dkt. No. 53 at 2.) Because 2 Travelers has failed to establish any of the elements that would weigh against granting leave, and 3 additionally because both Parties appear to agree NAT’s amendments would more accurately 4 reflect the status of this matter, the Court GRANTS NAT’s motion for leave to amend.
5 6 The clerk is ordered to provide copies of this order to all counsel. 7 Dated July 10, 2020.
A 8 9 Marsha J. Pechman 10 United States Senior District Judge
11 12 13 14 15 16 17 18 19 20 21 22 23 24