Travelers Insurance Co. v. Dayton Power & Light Co.

663 N.E.2d 1383, 76 Ohio Misc. 2d 17, 1996 Ohio Misc. LEXIS 3
CourtMiami County Court of Common Pleas
DecidedJanuary 23, 1996
DocketNo. 95-169
StatusPublished
Cited by3 cases

This text of 663 N.E.2d 1383 (Travelers Insurance Co. v. Dayton Power & Light Co.) is published on Counsel Stack Legal Research, covering Miami County Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Travelers Insurance Co. v. Dayton Power & Light Co., 663 N.E.2d 1383, 76 Ohio Misc. 2d 17, 1996 Ohio Misc. LEXIS 3 (Ohio Super. Ct. 1996).

Opinion

Jeffrey M. Welbaum, Judge.

On May 18, 1993, a fire broke out in electrical equipment owned and maintained by Hammer Graphics, Inc., a printing company in Piqua, Ohio. Two items [19]*19of equipment were damaged in the fire, the transformer and the transition cabinet. The transformer takes electricity from defendant Dayton Power and Light Company’s (“DP & L’s”) distribution line and reduces the voltage to a level appropriate for industrial machinery. The electricity is then carried by a small number of large cables to the transition cabinet. There the electricity is distributed among a large number of smaller wires that run from the transition cabinet to individual items of equipment in the Hammer Graphics plant.

Hammer Graphics contacted its insurer, plaintiff Travelers Insurance Company (“Travelers”), regarding the loss. On May 19, 1993, Travelers asked S.E.A., Inc. (“SEA”) to examine the damage and determine the cause of the failure. On May 20, 1993, Jeffrey Lindsey of SEA inspected the transition cabinet; he examined the transformer the following day. In his report, dated June 16, 1993, Lindsey concluded that the fire was probably caused by the alleged failure of DP & L employees to sufficiently tighten a bolt when they connected new cables to the transformer in 1991.

According to Lindsey, the “key evidence” supporting his theory of the fire’s origin was arc damage he found on one of the four “pads” where cables were connected to the transformer. Lindsey never inspected the equipment inside the transition cabinet to determine whether similar evidence of arc damage was also present there. Evidence of arc damage was likely to be found there because photographs of the transition cabinet taken shortly after the fire indicate that numerous cable connections had melted away inside the transition cabinet, just as they had at the one location inside the transformer. The transition cabinet was damaged much more severely than the transformer. The photographs, however, are inadequate for the purpose of detecting arc damage now in the absence of the transition cabinet itself.

Hammer Graphics disposed of the transition cabinet within days of the fire, after being told by Lindsey that he did not need it. Although DP & L personnel were on the scene shortly after the fire was discovered, their purpose there was to restore power to Hammer Graphics as quickly as possible, not to conduct a fire investigation. DP & L was afforded the opportunity to inspect the transformer. The evidence is uncontroverted that the transformer was internally undamaged.

Travelers paid $102,751.54 to Hammer Graphics for the fire damage. On May 16, 1995, two days before the statute of limitations would have run, Travelers brought suit against DP & L. Consistent with Lindsey’s report, Travelers claims the fire was caused by DP & L’s negligence in performing the 1991 work.

Plaintiff contends that the doctrine of spoliation of evidence applies only to products liability cases and not to this case, where the cause of action sounds only in negligence. The doctrine is not limited to products liability cases. [20]*20Transamerica, Ins. Group v. Maytag, Inc. (1994), 99 Ohio App.3d 203, 650 N.E.2d 169; Travelers Ins. Co. v. Knight Elec. Co. (Dec. 21, 1992), Stark App. No. CA-8979, unreported, 1992 WL 398201.

In this case there was no protective order prohibiting destruction of the transition cabinet at the time of its disposal. This is a consideration when balancing the equities in this case. However, defensive spoliation principles do apply by means of a motion under Civ.R. 37 requiring the court to fashion a just remedy. Cincinnati Ins. Co. v. Gen. Motors Corp. (Oct. 28, 1994), Ottawa App. No. 94-OT-017, unreported, 1994 WL 590566; Bright v. Ford Motor Co. (1990), 63 Ohio App.3d 256, 578 N.E.2d 547; Russo v. Goodyear Tire & Rubber Co. (1987), 36 Ohio App.3d 175, 521 N.E.2d 1116; Cincinnati Ins. Co. v. Synergy Gas, Inc. (Ala.1991), 585 So.2d 822; Shelbyville Mut. Ins. Co. v. Sunbeam Leisure Products Co. (1994), 262 Ill.App.3d 636, 199 Ill.Dec. 965, 634 N.E.2d 1319; Graves v. Daley (1988), 172 Ill.App.3d 35, 122 Ill.Dec. 420, 526 N.E.2d 679.

The court further finds that at the time there was no intent on the part of plaintiff or its agent to willfully destroy evidence for the purpose of depriving defendant of evidence at trial. However, negligent or inadvertent destruction of evidence is sufficient to trigger sanctions where the opposing party is disadvantaged by the loss. Farley Metals, Inc. v. Barber Colman Co. (1994), 269 Ill.App.3d 104, 109, 206 Ill.Dec. 712, 716, 645 N.E.2d 964, 968. Where the loss of evidence is belated, a court should not dwell on intent but focus on the importance of information, legitimately sought, that is unavailable as a result of the destruction of evidence. Farley Metals, Inc., supra. The intent of the offending party, the level of prejudice, and the reasonableness of the offending party’s action must all be balanced in fashioning a just remedy. The relative importance of the information denied the opposing party bears directly on the reasonableness of such party’s action and the resulting prejudice. The issue arises whether it was foreseeable that the evidence made unavailable would be relevant and, therefore, whether it would fall within the scope of items worthy of retention for inspection. Shelbyville Mut. Ins. Co. v. Sunbeam Leisure Products Co., supra. The relative importance of the evidence in addition to its mere relevance must be weighed in fashioning a just result. The loss of an essential item of evidence is far more prejudicial than a mere relevant piece of evidence. Almost any item found at a fire scene is arguably relevant. Obviously, not all such items are foreseeably essential or foreseeably relevant. Not all items arguably relevant at a fire scene may practically be retained. Consequently, the court must determine the reasonableness of the offending party’s action in fashioning a just result.

The court finds that at the time the transition cabinet was made unavailable, plaintiffs agent knew or should have known that the transition cabinet would be [21]*21material in a lawsuit. A lawsuit was anticipated. A mental awareness by plaintiff or its agent that future litigation would likely result is present in this case. The amount of the claim involved, the nature of the defendant, the prompt response by plaintiff sending a fire investigator to the scene to determine the likely cause of the fire, and the other facts and circumstances of the case, all weigh in favor of this awareness. The importance of the transition cabinet should have been obvious. The fire damage to the transformer and the transition cabinet coupled with plaintiffs investigator’s expert opinion that DP & L’s transformer was the cause of the fire made it foreseeable that future litigation was likely to result.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penix v. Avon Laundry Dry Cleaners, 91355 (3-26-2009)
2009 Ohio 1362 (Ohio Court of Appeals, 2009)
American States Insurance v. Tokai-Seiki (H.K.), Ltd.
704 N.E.2d 1280 (Miami County Court of Common Pleas, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
663 N.E.2d 1383, 76 Ohio Misc. 2d 17, 1996 Ohio Misc. LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/travelers-insurance-co-v-dayton-power-light-co-ohctcomplmiami-1996.