Travelers Casualty And Surety Company of America v. City of South Pittsburg,Tennessee

CourtCourt of Appeals of Tennessee
DecidedJanuary 30, 2015
DocketM2014-00269-COA-R9-CV
StatusPublished

This text of Travelers Casualty And Surety Company of America v. City of South Pittsburg,Tennessee (Travelers Casualty And Surety Company of America v. City of South Pittsburg,Tennessee) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Travelers Casualty And Surety Company of America v. City of South Pittsburg,Tennessee, (Tenn. Ct. App. 2015).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE October 23, 2014 Session

TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA v. CITY OF SOUTH PITTSBURG, TENNESSEE

Appeal from the Circuit Court for Marion County No. 18589 J. Curtis Smith, Judge

No. M2014-00269-COA-R9-CV - Filed January 30, 2015

In a suit arising out of a construction project at a wastewater treatment facility, the City of South Pittsburg brought an action against an engineering firm and a construction firm for breach of contract, negligence and professional negligence. The insurance company which issued a performance bond covering the project was added as a party and moved for summary judgment on the ground that the City had not instituted a proceeding to recover under the bond within the two year period specified in the bond for doing so. The insurance company appeals the denial of its motion. Finding no error, we affirm the judgment of the trial court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed.

R ICHARD H. D INKINS, J., delivered the opinion of the court, in which W. N EAL M CB RAYER, and B RANDON O. G IBSON, JJ., joined.

Jarrod W. Stone, Nashville, Tennessee, for the appellant, Travelers Casualty and Surety Company of America.

William L. Gouger, Jr., Jasper, Tennessee, for the appellee, City of South Pittsburg, Tennessee.

Parks T. Chastain and Gordon C. Aulgur, Nashville, Tennessee, for the appellee, Bituminous Casualty Corporation. OPINION 1

This case comes before us a second time. It arises out of a suit for breach of contract and professional negligence filed August 18, 2009, by the City of South Pittsburg (“the City”) against James C. Hailey & Co. (“Hailey”), an engineering firm hired to design and supervise repairs to the existing lagoon and the construction of a new lagoon at the City’s wastewater treatment plant, and W&O Construction Company, Inc. (“W&O”), which had been engaged to complete the improvements; the complaint also sought a declaratory judgment construing the terms of the May 6, 2008, contract between the City and W&O.2 By late 2008, the project had progressed to the point where the facility could be put into operation for purposes of testing and startup. In an amended complaint filed March 17, 2011 (the “amended complaint”), the City alleged that a hole developed in the liner of the existing lagoon in February 2009 causing the wastewater to drain completely and that, three days later, a hole developed in the liner of the new lagoon, as did a sinkhole.

A dispute arose between the City and W&O regarding responsibility to repair the damage; Tracy Wooden, counsel for the City, sent a letter to Travelers Casualty and Surety Company of America (“Travelers”), which had issued a performance bond in the amount of $1,719,700.00, and W&O on June 24, 2009, stating in part:

This letter will serve as a follow up to my telephone discussions with Mr. Michael Burkhardt with [Travelers] (“Surety”) today. Although we have previously provided written notice of our positions to you, Mr. Burkhardt requested that I provide this additional correspondence.

As we have previously indicated, and as we hereby affirm, [W&O] (“Contractor”) is obligated pursuant to Contract 106 to complete the construction of the sewer treatment plant project so that it will operate in a

1 Unless otherwise noted, the factual background in this opinion is taken from the pleadings. 2 The complaint alleged that the existing and new lagoons failed, as a result of which the expansion of the facility was not completed, and that the City incurred additional fees and expenses, including $55,000 in fines, and penalties and other restrictions imposed by the Tennessee Department of Environment and Conservation. On March 16, 2010, the City amended the complaint to include a claim for negligence and a second claim for breach of contract against W&O, and on January 5, 2011, the City amended the complaint to add Bituminous Casualty Corporation (“Bituminous”), which had issued a builder’s risk policy to W&O. Bituminous moved for summary judgment, contending that construction on the wastewater facility was completed in late 2008 and that coverage under the policy ended at that time; the court granted the motion. On appeal, this court held that there was a genuine issue of material fact regarding the date at which construction was completed and reversed the grant of the motion. City of South Pittsburg v. Hailey, No. M2012-01185-COA-R3-CV, 2013 WL 3355658, at *5 (Tenn. Ct. App. June 27, 2013).

2 functional manner. Contractor is contractually obligated to complete such project within the contracted price. The responsibilities of Contractor are clear pursuant to the language of Contract 106 and based on at least one decision issued by the Tennessee Supreme Court against [W&O].

We hereby request a meeting with representatives of both of your companies in the offices of our client within fifteen days (as explained below, an earlier meeting is appropriate under the circumstances) of the date of this letter to receive from you your plan for performing the Contract.

Upon receiving confirmation from Surety that Contractor and/or Surety will complete the project for the contracted price, Owner will pay to Surety the balance of the contract price.

Representatives of the City, Travelers, and W&O met on July 9, and on July 22 Mr. Wooden sent a letter to Tim Huddleston, Vice President of W&O, stating in part:

Prior to such July 9, 2009, meeting, and again during the July 9, 2009, meeting [W&O] refused to complete the project for the bid price. We have since been informed by [Travelers] that further discussions between [W&O] and [Travelers] have not led to [W&O] being willing to perform. Based upon the refusal of [W&O], [Travelers] insisted that we issue a Contractor Default notice pursuant to section 3.2 of the performance bond before [Travelers] will proceed with its obligations under the performance bond. This letter will serve as such Contractor Default notice as required by [Travelers] as explained above. If W&O has since reconsidered its position and has become willing to complete the project, please let me know in writing immediately, as our goal continues to be for [W&O] or [Travelers] to complete the project consistent with the Contract.

The March 17, 2011, amended complaint added Travelers as a party; the City alleged that Travelers breached the terms of the bond by failing to ensure that the project was completed and that Travelers was liable for funds expended to repair the damaged plant.3

3 Neither the motion to amend to add Travelers as a party nor the order allowing the amendment are included in the record on appeal; the record before us shows that counsel for the City signed the amended complaint on March 17, 2011, and that it was filed with the court on August 15, 2011. At oral argument, counsel for Travelers acknowledged that the amended complaint related back to March 17, 2011.

3 On June 20, 2012, Travelers moved for summary judgment on four grounds: (1) that the City’s agreement with W&O did not require W&O to insure against sinkholes; (2) that the City failed to submit its claim to Hailey, thereby barring the action 4 ; (3) that the City’s action was barred by the two year period to institute an action under the bond; and (4) that the City suffered no damages. The court denied the motion, holding that grounds one and four presented questions of fact and, with regard to the second ground, that the City was not required to submit a claim to Hailey prior to instituting the suit. Of particular import to this appeal, as to ground three, the court held the following:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Draper v. Westerfield
181 S.W.3d 283 (Tennessee Supreme Court, 2005)
Finister v. Humboldt General Hospital, Inc.
970 S.W.2d 435 (Tennessee Supreme Court, 1998)
Rainey v. Stansell
836 S.W.2d 117 (Court of Appeals of Tennessee, 1992)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
Sutton v. First National Bank of Crossville
620 S.W.2d 526 (Court of Appeals of Tennessee, 1981)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Travelers Casualty And Surety Company of America v. City of South Pittsburg,Tennessee, Counsel Stack Legal Research, https://law.counselstack.com/opinion/travelers-casualty-and-surety-company-of-america-v-tennctapp-2015.