Travelers Casualty and Surety Company of America v. BCP Construction of Hawaii, Inc.

CourtDistrict Court, D. Hawaii
DecidedDecember 10, 2019
Docket1:19-cv-00140
StatusUnknown

This text of Travelers Casualty and Surety Company of America v. BCP Construction of Hawaii, Inc. (Travelers Casualty and Surety Company of America v. BCP Construction of Hawaii, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Travelers Casualty and Surety Company of America v. BCP Construction of Hawaii, Inc., (D. Haw. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF HAWAI‘I

TRAVELERS CASUALTY AND Case No. 19-cv-00140-DKW-WRP SURETY COMPANY OF AMERICA,

Plaintiff, ORDER GRANTING IN PART MOTION FOR PARTIAL vs. SUMMARY JUDGMENT

BCP CONSTRUCTION OF HAWAII, INC., et al.,

Defendants.

INTRODUCTION Plaintiff Travelers Casualty and Surety Company of America (“Travelers”) moves for summary judgment on two of its claims on the basis that Defendants have breached a contract between the parties and damages have ensued. Travelers seeks both damages it has already suffered and damages it anticipates suffering due to Defendants’ conduct. In no small part due to Defendants not responding to Travelers’ motion, the facts are undisputed, and those facts show that the parties’ contract has been breached, and Travelers has suffered damages. However, because the Court has questions regarding the damages Travelers anticipates suffering, the motion for partial summary judgment is GRANTED IN PART without prejudice pending clarification of Travelers’ anticipated damages. PROCEDURAL BACKGROUND Travelers initiated this action with the filing of a Complaint on March 18,

2019 against BCP Construction of Hawaii, Inc. (“BCP”), Legacy One Development, LLC, Close Family Trust, Robert N. Close, and Betty Close (collectively, “Defendants”). Dkt. No. 1. In the Complaint, Travelers asserts five

claims for relief, two of which are the subject of the pending motion for partial summary judgment: Claim One – Breach of Contract – and Claim Five – Specific Performance. Essentially, Travelers alleges a breach of contract by Defendants and seeks, inter alia, damages and specific performance of the contract.

On April 12, 2019, Defendants appeared in this action by answering the Complaint. Dkt. No. 15. On July 8, 2019, the parties appeared before the assigned Magistrate Judge for a settlement conference that did not result in a

resolution. Dkt. No. 44. On October 16, 2019, Travelers filed the instant motion for partial summary judgment (“the motion”), along with a concise statement of facts and accompanying exhibits. Dkt. Nos. 48-49. The motion was scheduled for a

hearing on December 2, 2019, meaning that, pursuant to Local Rule 7.2, an opposition was due three weeks before that date. No opposition to the motion was

2 (or has been) filed. On November 18, 2019, Travelers filed a brief reply, and the Court subsequently vacated the December 2, 2019 hearing. Dkt. Nos. 55-56.

FACTUAL BACKGROUND BCP is a contractor licensed to conduct business in the State of Hawai‘i. Concise Statement of Facts (“CSF”) at ¶ 1, Dkt. No. 49. Robert Close and Betty

Close, both individually and as trustees of the Close Family Trust, and BCP entered into a General Agreement of Indemnity (“GAI”) with Travelers dated May 20, 2013. Id. at ¶ 2. On December 12, 2014, Legacy One Development, LLC was added as an indemnitor under the GAI. Id. at ¶ 3. Pursuant to the GAI,

Defendants agreed to (1) indemnify Travelers against all “Loss” and (2) deposit, upon demand, an amount determined by Travelers to be sufficient to discharge any “Loss” or anticipated “Loss.” GAI at ¶¶ 3, 5, Dkt. No. 48-4. The GAI defines

“Loss” as “[a]ll loss and expense of any kind or nature, including attorneys’ and other professional fees, which [Travelers] incurs in connection with any Bond or [the GAI]….” Id. at ¶ 1. After execution of the GAI, BCP entered into a contract with the State of

Hawai‘i Department of Accounting and General Services (“DAGS”) for BCP to upgrade the security electronics at the Halawa Correctional Facility (“the Halawa Project”). CSF at ¶¶ 6, 9. In connection therewith, Travelers issued bonds for

3 BCP’s work on the Halawa Project (“the Halawa Bonds”). Decl. of Paul Harmon at ¶ 10, Dkt. No. 48-3; 12/15/15 Performance Bond, Dkt. No. 48-5 at 7; 12/15/15

Labor and Material Payment Bond, Dkt. No. 48-5 at 9. Travelers also issued numerous other bonds on behalf of BCP. Harmon Decl. at ¶ 10. A notice to proceed on the Halawa Project was issued on February 16, 2016.

CSF at ¶ 8. Most of the work for the Halawa Project was to be completed by two BCP subcontractors: Sierra Detention Systems (“SDS”) with respect to hardware supply and programming; and Hawaiya Technologies, Inc. (“HTI”) as the electrician. Id. at ¶ 9. The Halawa Project was scheduled for completion on

September 7, 2017, but this date was subsequently extended to August 31, 2018. Id. at ¶ 8. Construction was complicated due to the Halawa Correctional Facility (“HCF”) being fully occupied with inmates in four cell modules at the time of the

work. Id. at ¶ 11. To accommodate construction activities, 248 inmates were temporarily sent from HCF to a private prison in Arizona. Id. at ¶ 12. Due to the high cost of re-housing inmates, a penalty clause was included in the contract between DAGS and BCP, charging BCP $16,829.00 per day for every day the

Halawa Project was late. Id. at ¶ 13. At various points during the Halawa Project, SDS went out of business, and HTI was terminated after installing defective electrical work. Id. at ¶ 14. As a

4 result of these and other issues, the Halawa Project was delayed by over two years, with DAGS alleging that it had incurred over $7.2 million in delay damages. Id.

at ¶ 16. On approximately February 15, 2019, Travelers received a payment bond claim from one of BCP’s subcontractors, CML RW Security, LLC (“CML”),

which had been hired to complete SDS’ remaining work. Id. at ¶ 17. Travelers paid CML’s claim in the amount of $315,353.89, after being informed by BCP that, although the claim was valid, BCP did not have the money to pay it. Id. at ¶ 19. BCP subsequently failed to pay other subcontractors and suppliers, resulting

in additional claims being made against the bonds Travelers had issued. Id. at ¶ 20. After conducting its own investigations, Travelers paid the claims it determined were valid, but has not been reimbursed by Defendants under the GAI.

Id. at ¶ 21. On February 14, 2019, Travelers made a formal written demand to Defendants to deposit cash or other property in the amount of $7.6 million to indemnify Travelers from the losses potentially resulting from the claims made

against the Halawa Bonds. Id. at ¶ 22. Defendants did not comply with this demand. Id. at ¶ 23.

5 On or about April 10, 2019, DAGS provided formal written notice to BCP that it was in default on the Halawa Project, after Robert Close sent an email to

DAGS indicating that BCP would “demobilize” with respect to the Halawa Project. 4/10/19 Letter from Curt Otaguro to Robert Close and BCP, Dkt. No. 48- 9. At about the same time, BCP voluntarily defaulted on all other bonded

projects, with demands made upon Travelers to complete the relevant projects. CSF at ¶ 25. Subsequently, BCP went out of business. Id. at ¶ 26. As of May 9, 2019, Travelers entered into a Takeover Agreement with DAGS, pursuant to which, inter alia, Travelers agreed to (1) complete the

remaining work on the Halawa Project, and (2) pay DAGS $2.5 million for claims related to inmate re-housing and liquidated damages. Id. at ¶ 27; 5/9/19 Takeover Agreement, Dkt. No. 48-10. In connection therewith, Travelers hired Kitsap

Construction (“Kitsap”) to replace BCP as the contractor on the Halawa Project, CML to finish SDS’ work, and Rhema Electric (“Rhema”) to finish HTI’s work. CSF at ¶ 28. As a result, the Halawa Project is expected to be completed by February 13, 2020. Id. at ¶ 29.

As of September 17, 2019, Travelers has paid claims, net of recoveries, in the amount of $3,362,410.96. Id. at ¶ 30. The breakdown of Travelers’ paid claims is as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henderson Duval Houghton v. Carroll v. South
965 F.2d 1532 (Ninth Circuit, 1992)
Lee v. Aiu
936 P.2d 655 (Hawaii Supreme Court, 1997)
Scotella v. Osgood
659 P.2d 73 (Hawaii Intermediate Court of Appeals, 1983)
Genzler v. Longanbach
410 F.3d 630 (Ninth Circuit, 2005)
Ledesma v. Jack Stewart Produce, Inc.
816 F.2d 482 (Ninth Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Travelers Casualty and Surety Company of America v. BCP Construction of Hawaii, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/travelers-casualty-and-surety-company-of-america-v-bcp-construction-of-hid-2019.