Transocean Offshore Deepwater Drilling, Inc. v. Eni U.S. Operating Co.

957 F. Supp. 2d 836, 2013 WL 5913245, 2013 U.S. Dist. LEXIS 160578
CourtDistrict Court, S.D. Texas
DecidedOctober 1, 2013
DocketCivil Action No. H-12-1366
StatusPublished

This text of 957 F. Supp. 2d 836 (Transocean Offshore Deepwater Drilling, Inc. v. Eni U.S. Operating Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transocean Offshore Deepwater Drilling, Inc. v. Eni U.S. Operating Co., 957 F. Supp. 2d 836, 2013 WL 5913245, 2013 U.S. Dist. LEXIS 160578 (S.D. Tex. 2013).

Opinion

ORDER OF ADOPTION

DAVID HITTNER, District Judge.

On September 10, 2013, Magistrate Judge Stephen Wm. Smith issued a Memorandum and Recommendation (Dkt. 48). Plaintiff has filed objections (Dkts. 50, 51).

After due consideration of the entire record and the applicable law, the Court hereby ADOPTS the Memorandum and Recommendation as this Court’s Memorandum and Order. It is therefore

ORDERED that defendant’s motion for summary judgment (Dkt. 25) is granted.

The court will issue a separate final judgment.

Memorandum and Recommendation

STEPHEN WM. SMITH, United States Magistrate Judge.

The crux of this maritime dispute is to decide which contractual lease rate applies to a drilling vessel while its operations were interrupted by the federal government’s regulatory response to the 2010 Gulf of Mexico oil spill. For the seven month period in dispute, Defendant Eni challenged the amount of plaintiff Trans-ocean’s invoices, which were based on the “Standby Rate”, and paid them at a lesser rate, the “Repair Rate.” Transocean has sued for breach, seeking to recover the nearly $78 million difference in the two rate calculations.

The parties have filed cross motions for summary judgment (Dkt. 24, 25), agreeing that there is no material issue of fact but vigorously disputing how to interpret the contract at issue. Oral argument on these motions was heard on July 11, 2013. For reasons explained below, the Court finds that the Repair Rate applies to the disputed time period. Eni’s motion for summary judgment should be • granted and Trans-ocean’s partial motion for summary judgment denied.

I. Facts

A. The Drilling Contract

On November 17, 2006 the parties signed a Drilling Contract under which Transocean would lease to Eni the vessel Transocean Amirante, together with its equipment, personnel, and insurance, for a multi-year period.1 The vessel was to [838]*838perform operations and services at Eni’s drilling sites in the Gulf of Mexico. The Drilling Contract refers to Eni as the “Operator”, Transocean as the “Contractor”, and the vessel as the “Drilling Unit.” The basic Operating Rate that Eni paid to Transocean was $350,000 per day. That rate would remain in effect “unless it is replaced by another rate” specified in the contract.2

Among the various rates specified in the contract is the Repair Rate, which is to be paid “for any period during which operations are suspended to permit necessary replacement, regulatory inspection, repair or maintenance of the Drilling Unit.”3 The Repair Rate starts at 98% of the Operating rate ($343,000 per day), but if repairs extend beyond a specified time, it reverts to Zero Rate ($0 per day) until operations are resumed. For the vessel’s subsea equipment (which is at issue here), Trans-ocean could charge the Repair Rate for a maximum of 48 hours per month or 288 hours cumulatively; after that, the Zero Rate kicked in. Eni argues that this Repair Rate should apply to the disputed time period, July 10, 2010 to February 11, 2011, because the vessel was undergoing a regulatory inspection and repairs required by federal safety rules issued after the 2010 Gulf oil spill.

By contrast, the Standby Rate applies “during any period of delay as a direct result of an act, instruction, or omission of Operator including, but without limitation, the failure of any of Operator’s Items, or the failure of Operator to issue instructions, provide Operator Items or furnish services.”4 The Standby Rate is also 98% of the Operating Rate ($343,000), but it does not revert to Zero Rate after a certain period of time, unlike the Repair Rate. Transocean argues that the Standby Rate applies to the period in question, because Eni failed to provide all of Operator’s Items under the contract, and failed to issue instructions to Transocean during that time.5

B. Events Giving Rise to the Rate Dispute

In April 2010, the Amirante was drilling at Green Canyon block 254# 3 (“Allegheny Well # 3”), 80 miles south of New Orleans.6 On the night of April 20, another vessel in the Gulf of Mexico, the Deepwater Horizon, experienced a blowout at BP’s Macondo well. In response, the federal government announced that it would issue new safety regulations. The Amirante continued to drill Allegheny Well #3, reaching total depth (14,768 feet) on May 6, 2010. By May 27, the casing was set, marking the end of the drilling process. The next step was “completion” of the well, which would prepare the well for hydrocarbons to flow. On May 28, Eni applied for a permit from the U.S. Department of the Interior Minerals Management Service (“MMS”) to conduct this phase of the operation.7

[839]*839Two days later on May 30, the MMS issued NTL No. 2010-N04 (“NTL-04”),8 which imposed a six-month moratorium on drilling deepwater wells and ordered abandonment of all wells then being drilled in the Gulf of Mexico. On June 2, the MMS returned Eni’s application “for future resubmittal due to deepwater moratorium,”9 effectively denying the application. In accordance with NTL-04, Eni temporarily abandoned the well by plugging it. With no other available projects in the Gulf permissible under the NTL-04 moratorium, the Amirante departed the well site on June 9, 2010, and headed to Mobile Middle Bay Port shipyard.10

While en route to the shipyard, Eni sent a letter to Transocean explaining that its “inability to utilize the Drilling Unit for operations in the Gulf of Mexico following the completion of Allegheny # 3 Well constitutes a Force Majeure____”11 Trans-ocean did not necessarily agree that the Force Majeure rate was applicable, but because the Standby Rate and Force Majeure rates were the same dollar amount— $343,000 per day — Transocean did not dispute the rate.

The Amirante arrived at the shipyard on June 11, 2010. The crew immediately began conducting routine maintenance. During that time, Eni learned that on June 8 the MMS had issued NTL No. 2010-05 (“NTL-05”). NTL-05 created a new requirement that drilling vessels such as the Amirante “must have an independent third party conduct a detailed physical inspection and design review of the BOP [ (Blowout Preventer) ].”12 Eni hired West Engineering to provide the required inspection and certification. Routine maintenance continued until July 9, 20 10, when West arrived to begin its inspection.13 West uncovered multiple problems with the BOP.14

Over the next several months, the necessary repairs were made. Meanwhile, the moratorium imposed by NTL-04 was officially lifted on October 12, 2010.15 On January 21, 2011, West issued a certificate of compliance, and three days later Eni obtained a permit to use the Amirante.16 Transocean conducted additional, unrelated repairs for several days, and on February 11, 2011, the Amirante finally left the shipyard and resumed operations.17

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
957 F. Supp. 2d 836, 2013 WL 5913245, 2013 U.S. Dist. LEXIS 160578, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transocean-offshore-deepwater-drilling-inc-v-eni-us-operating-co-txsd-2013.