Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission

907 F.2d 1211, 285 U.S. App. D.C. 205, 1990 U.S. App. LEXIS 11857
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 17, 1990
DocketNo. 88-1741
StatusPublished
Cited by1 cases

This text of 907 F.2d 1211 (Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission, 907 F.2d 1211, 285 U.S. App. D.C. 205, 1990 U.S. App. LEXIS 11857 (D.C. Cir. 1990).

Opinion

Opinion filed PER CURIAM.

PER CURIAM:

Transcontinental Gas Pipe Line Corporation (“Transco”) petitions for review of two orders of the Federal Energy Regulatory Commission (“FERC” or “the Commission”). The Commission’s order of August 3, 1988, Order Affirming Initial Decision, Transcontinental Gas Pipe Line Corp., 44 FERC ¶ 61,216 (1988) (“August 3 Order”), and its order of October 3, 1988, Order Denying Rehearing and Clarifying Prior Order, Transcontinental Gas Pipe Line Corp., 45 FERC ¶ 61,001 (1988) (‘‘October 3 Order ”), found Transco’s minimum bill to be unreasonably anticompetitive and ordered it removed from Transco’s tariff, effective April 1, 1987. Transco challenges the Commission’s elimination of its minimum bill and the effective date of the Commission’s order. Finding that the Commission has failed to state a reasonable basis for its decision to eliminate Transco’s minimum bill, we vacate the orders under review and remand the case to the Commission. Accordingly, we do not reach the timing issue.

Background

In 1982 Transco filed for a rate increase under section 4 of the Natural Gas Act, 15 U.S.C. § 717c. A settlement between the parties was approved by the Commission. Transcontinental Gas Pipe Line Corp., 22 FERC ¶ 61,146 (1983). This settlement specifically reserved for hearing the issue of Transco’s minimum bill. The minimum bill requires Transco’s partial requirements customers to purchase 65% of their annual contract demand or to pay 15 cents for every dekatherm by which they are deficient.

After a hearing on this issue, the ALJ approved the minimum bill. Initial Decision, Transcontinental Gas Pipe Line Corp., 28 FERC ¶ 63,086 (1984). The Commission rejected the ALJ’s finding in Opinion No. 260, Transcontinental Gas Pipe Line Corp., 37 FERC ¶ 61,328 (1986). In its order on rehearing, Opinion No. 260-A, the Commission determined that Transco had not had adequate opportunity to present evidence and vacated its Opinion No. 260 minimum bill decision. Transcontinental Gas Pipe Line Corp., 40 FERC ¶ 61,188 (1987).

After a further hearing on Transco’s minimum bill, the AU issued a second Initial Decision, this time finding the minimum bill anticompetitive. Transcontinental Gas Pipe Line Corp., 43 FERC ¶ 63,017 (1988). The Commission affirmed this decision and ordered Transco to eliminate its minimum bill effective from April 1, 1987. August 3 Order. The Commission denied rehearing of this order, in its October 3 Order, and Transco brought this petition for review.

Analysis

I. Minimum Bill

A. Anticompetitiveness

FERC has established a presumption that minimum bills are anticompetitive and therefore prima facie unlawful under section 5 of the Natural Gas Act, 15 U.S.C. § 717d. We upheld this presumption in East Tennessee Natural Gas Co. v. F.E.R.C., 863 F.2d 932, 935-40 (D.C.Cir.1988). See also Tennessee Gas Pipeline Co. v. F.E.R.C., 871 F.2d 1099, 1104 (D.C.Cir.[207]*2071989). Transco attempted to rebut the presumption of anticompetitiveness and to justify its minimum bill by showing that its minimum bill “is no more onerous” than the purchase obligations into which its customers have voluntarily entered. To this end Transco introduced into the record a stipulation that some of its contract demand customers are entering into long-term firm contracts with producers and that these contracts contain take-or-pay obligations.1 FERC responded:

Irrespective of the quality or sufficiency of this evidence, it is not relevant to rebut the presumptive anticompetitiveness of Transco’s minimum bill. Transco submits that the purposes and effects of a minimum bill and a take-or-pay obligation are the same. However, it ignores the fact that a contractual obligation with a non-pipeline supplier is voluntary, whereas a pipeline minimum bill is not.

October 3 Order, 45 FERC ¶ 61,001 at 61,-001 (1988). The Commission properly explained that Transco’s stipulation shed no light on the competitiveness of Transco’s minimum bill. That some of Transco’s customers have entered voluntarily into contracts with third party producers containing provisions which in some respects resemble minimum bills does not in any way demonstrate that a minimum bill imposed as part of a mandatory rate schedule is anything other than anticompetitive. Customers desiring service under Transco’s CD rate schedule would be obligated to accept the minimum bill. This would, in effect, prevent them from entering into those contracts with producers that Transco finds analogous unless they were willing to pay a deficiency charge for falling below 65% of their contract demand. Such a provision is demonstrably anticompetitive and Transco has admitted as much by stating that “the function of a minimum bill is to provide a measure of discipline on customers’ purchasing decisions____” Brief for Petitioners at 25. A decision by a customer to voluntarily bind itself to take- or-pay obligations bears only the most superficial resemblance to the imposition of an involuntary minimum bill.

B. Third Seaboard Criterion

FERC has previously determined that a pipeline, such as Transco, with a modified fixed variable rate design, may rebut the presumption of anticompetitiveness under what is known as the third Seaboard criterion. Opinion No. 260-A, Transcontinental Gas Pipe Line Corp., 40 FERC ¶ 61,188 at 61,590-91 (1987) (citing Atlantic Seaboard Corp., 38 FPC 91 (1967), aff'd, Atlantic Seaboard Corp. v. F.P.C., 404 F.2d 1268 (D.C.Cir.1968)). The third Seaboard criterion allows a minimum bill if it “links cost-incurrence with cost-causation, i.e., if it assists in collecting take-or-pay costs from those customers that have caused the costs by reducing their purchases.” Tennessee Gas Pipeline Co., 871 F.2d at 1105. Although this Court in both Tennessee Gas Pipeline Co., id. at 1106, and Trunkline Gas Co. v. F.E.R.C., 880 F.2d 546, 551 (D.C.Cir.1989), professed being “disturbed” by the Commission’s “narrow technical focus” on the mechanics of the minimum bill under the third Seaboard criterion, it upheld both of the Commission’s decisions to delete the minimum bills.

Evidence in the record establishes that Transco faces take-or-pay obligations nearly equal to the capacity of its system. August 3 Order, 44 FERC ¶ 61,216 at 61,808 n. 41 (1988) (citing record evidence that Transco’s system take obligation is approximately 2.7 Bcf/day, or 87% of its certificated sales obligation of 3.1 Bcf/day). Consequently, even taking a narrow technical focus, it is a matter of logical necessity that those customers that purchase less than their contract demand will cause the incurrence of take-or-pay liability. Because liability is nearly equal to capacity, any significant drop in demand will cause the incurrence of take-or-pay liability. Take-or-pay costs are attributable to those customers who take less than their con[208]*208tract demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
907 F.2d 1211, 285 U.S. App. D.C. 205, 1990 U.S. App. LEXIS 11857, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-corp-v-federal-energy-regulatory-cadc-1990.