Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC

CourtDistrict Court, N.D. Oklahoma
DecidedAugust 8, 2019
Docket4:18-cv-00445
StatusUnknown

This text of Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC (Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC, (N.D. Okla. 2019).

Opinion

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OKLAHOMA TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC, ) ) Plaintiff, ) ) v. ) Case No. 18-CV-0445-CVE-FHM ) KIBBY WELDING, LLC, ) ) Defendant. ) OPINION AND ORDER Now before the Court are the following motions: Plaintiff Transcontinental Gas Pipe Line Company, LLC’s Partial Motion to Dismiss Defendant’s First Amended Counterclaim for Failure to State a Claim and Brief in Support (Dkt. # 26); Plaintiff Transcontinental Gas Pipe Line Company, LLC’s Motion to Strike Defendant’s Jury Demand and Brief in Support (Dkt. # 27); and Defendant’s Motion for Leave to Amend Counterclaim (Dkt. # 31). I. On August 28, 2018, Transcontinental Gas Pipe Line Company, LLC (Transco) filed this case alleging that Kibby Welding, LLC (Kibby) breached a construction contract. Dkt. # 2. Transco has filed an amended complaint (Dkt. # 22) and this is now the operative pleading. The amended complaint alleges claims of breach of contract (counts one and two) and indemnification (count three), and Transco also seeks declaratory and injunctive relief (count four) and an accounting of amounts paid to subcontractors by Kibby (count five). Transco states that it is an interstate pipeline company, and Transco entered a contract with Kibby for work on a section of pipeline located in Virginia. Dkt. # 22, at 2. Transco agreed to pay Kibby $4,058,500 to make modifications and replace components on a section of pipeline. Id. The contract required Kibby to submit a performance and payment bond upon a written request by Transco. Id. Transco claims that it submitted written requests for a performance and payment bond from Kibby on January 2, 8, and 17, 2018, but Kibby failed to furnish a bond as required by the

contract. Id. at 3. The contract requires Kibby to “keep the property and Work free and clear of all liens, claims, security interests and encumbrances arising from the performance of the Work and this Contract.” Dkt. # 22-1, at 27. Numerous liens have been filed against Transco by subcontractors of Kibby totaling $2,894,600.97, and Transco believes that Kibby has failed to pay other subcontractors who have not yet filed liens. Dkt. # 22, at 4. In addition, Kibby has also filed liens against Transco’s property in the amount of $4,421,849.28, and Transco claims that these liens were filed in breach of the parties’ contract. Id. Transco has demanded that Kibby release its lien and

Kibby has refused. Id. The contract provides a final completion date of June 17, 2018 and requires Kibby to meet certain “Key Milestone Performance Dates.” Id. Transco alleges that Kibby failed to meet any of the performance deadlines and that the work remains uncompleted as of the filing of the amended complaint. On August 7, 2018, Transco sent a letter notifying Kibby of Transco’s intent to terminate the contract for cause. Id. at 5. Transco acknowledges that Kibby has submitted requests for payments for extra work, but Transco claims that the extra work “was not consistent with the Contract requirements, was not supported by appropriate documentation and was due to Kibby’s

self-inflicted wounds, including its own delays, inefficiencies and inability to perform the Work.” Id. at 5-6. Transco states that the parties were unable to informally resolve their dispute, and Transco filed this case seeking damages in excess of $75,000 and injunctive and declaratory relief. 2 Kibby filed an answer to the original complaint and also asserted counterclaims against Transco. Transco filed an amended complaint and Kibby filed an amended answer and counterclaims. Kibby’s original and amended answers both contain a jury demand. Kibby states that it is a welding company and has periodically worked for Transco for about eight years. Dkt. # 25,

at 2. Kibby states that the contract required it to “provide welding services needed in conjunction with several trap modifications, valve replacements, [Department of Transportation] retesting, tap abandonments, and pipeline replacements” in Charlottesville, Virginia. Id. In more general terms, Kibby claims that it performed welding at tie-ins along the pipeline and connected various pieces of the pipeline. Id. Kibby made a bid of $4,058,500 based on its understanding of the work to be performed, and Kibby claims that its bid was based on a belief that there were no bends in the pipeline and that there would be no matching of different types of pipe. Id.

Kibby claims that it began its work and encountered a bend in the pipeline at the first tie-in it was asked to weld, and Kibby claims that Transco delayed in directing Kibby how to proceed. Id. at 3. Kibby blames Transco for any delays in completing the work required by the parties’ contract, and Kibby claims that the scope of work was more time-consuming and expensive than contemplated in its bid for the contract. Id. Kibby disputes Transco’s assertion that Kibby failed to complete the contract work, and Kibby claims that it achieved “mechanical completion” in July 2018. Id. at 4. Kibby further claims that Transco tacitly or impliedly approved extra work requests and allowed Kibby to go forward with work outside the scope of the contract. Id. Kibby alleges that Transco has

denied its extra work requests and change orders, even though Transco impliedly approved such request or change orders. Id. Kibby asserts counterclaims of breach of contract, fraud, unjust enrichment, and interference with business relationships. 3 II. Transco argues that Kibby’s counterclaims for fraud and unjust enrichment should be dismissed, because the parties’ relationship is governed by an enforceable contract and these alternative claims seek the same relief that Kibby could recover for breach of contract. Dkt. # 26.

Kibby responds that it is permitted to plead alternative claims of breach of contract and unjust enrichment, and Kibby asserts that it has alleged a plausible claim of constructive fraud based on the non-disclosure of material facts. Dkt. # 33. A. Kibby argues that it is permitted to plead alternative claims of fraud and breach of contract, even though it acknowledges that it may not receive double recovery on both claims. Dkt. # 33, at 8. Kibby cites Specialty Beverages, LLC v. Pabst Brewing Co., 537 F.3d 1165 (10th Cir. 2008), for

the proposition that Oklahoma law permits a party to proceed with claims for breach of contract and fraud at the pleading stage. However, a party may not allege breach of contract and fraud claims based on identical facts, and the claims must be sufficiently distinct in order for a party to simultaneously maintain claims for breach of contract and fraud. Horton v. Bank of America, 189 F. Supp. 3d 1286, 1290-91 (N.D. Okla. 2016); Atkinson, Haskins, Nellis, Brittingham, Gladd & Fiasco, P.C. v. Oceanus Ins. Group, 2014 WL 3891267, *5 (N.D. Okla. Aug. 7, 2014); McGregor v. National Steak Processors, Inc., 2012 WL 314059, *3 (N.D. Okla. Feb. 1, 2012). A party who elects to sue for breach of contract cannot bring a fraud claim unless the “tortious act is sufficiently

independent of the breach of contract.” McKnight v. Marathon Oil Co., 2017 WL 1628981, *2 (W.D. Okla. May 1, 2017). In addition, “the fraud must have resulted in damages greater than those

4 caused by the breach of contract alone.” West v. Ditech Financial LLC, 2016 WL 3200296, *4 (W.D. Okla. June 8, 2016). Kibby alleges that it made a bid of $4,058,500 for the contract work based on its “belief that there were no bends in the pipe or matching different types of pipe together . . . .” Dkt. # 25, at 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bradley v. Val-Mejias
379 F.3d 892 (Tenth Circuit, 2004)
Duncan v. Manager, Department of Safety
397 F.3d 1300 (Tenth Circuit, 2005)
Minter v. Prime Equipment Co.
451 F.3d 1196 (Tenth Circuit, 2006)
Burlington Northern & Santa Fe Railway Co. v. Grant
505 F.3d 1013 (Tenth Circuit, 2007)
Specialty Beverages, L.L.C v. Pabst Brewing Co.
537 F.3d 1165 (Tenth Circuit, 2008)
Harvell v. Goodyear Tire and Rubber Co.
2006 OK 24 (Supreme Court of Oklahoma, 2007)
County of Orange v. United States District Court
784 F.3d 520 (Ninth Circuit, 2015)
Horton v. Bank of America, N.A.
189 F. Supp. 3d 1286 (N.D. Oklahoma, 2016)
Telum, Inc. v. E.F. Hutton Credit Corp.
859 F.2d 835 (Tenth Circuit, 1988)
Hulsey v. West
966 F.2d 579 (Tenth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Transcontinental Gas Pipe Line Company, LLC v. Kibby Welding, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-company-llc-v-kibby-welding-llc-oknd-2019.