Transcontinental Gas Pipe Line Co. v. Permanent Easement for 2.59 Acres, Temporary Easements for 5.45 Acres & Temporary Access Easement for 2.12 Acres in Pine Grove Township

709 F. App'x 109
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 12, 2017
Docket17-1829
StatusUnpublished
Cited by22 cases

This text of 709 F. App'x 109 (Transcontinental Gas Pipe Line Co. v. Permanent Easement for 2.59 Acres, Temporary Easements for 5.45 Acres & Temporary Access Easement for 2.12 Acres in Pine Grove Township) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Co. v. Permanent Easement for 2.59 Acres, Temporary Easements for 5.45 Acres & Temporary Access Easement for 2.12 Acres in Pine Grove Township, 709 F. App'x 109 (3d Cir. 2017).

Opinion

OPINION *

PER CURIAM

Ryan J. Regec appeals the District Court’s order granting Appellee Transcontinental Gas Pipe Line Company’s motion for partial summary judgment and request for a preliminary injunction. For the reasons below, we will affirm the District Court’s order as to the preliminary injunction.

The procedural and factual history of this case are well known to the parties, set forth in the District Court’s opinion, and need not be discussed at length. Briefly, in February 2017, the Federal Energy Regulatory Commission (FERC) granted Ap-pellee a certificate of public convenience and necessity (certificate), authorizing it to construct a natural gas pipeline. In order to build the pipeline, Appellee requires rights of way on a piece of property Regec owns. The certificate was issued after a lengthy administrative review process which included notice to property owners affected and an opportunity to respond. Regec did not participate in the administrative proceedings.

After Regec and Appellee could not agree on the compensation to be paid for the needed property interests, Appellee filed a complaint in condemnation for temporary and permanent easements against Regec and his land. Appellee moved for partial summary judgment, seeking condemnation of the rights of way and leaving the issue of just compensation for later litigation. It also filed a motion for a preliminary injunction for immediate possession of the rights of way. After a hearing at which Regec was represented by counsel, the District Court granted both motions, giving Appellee possession of the rights of way at issue. Regec filed a pro se notice of appeal.

The District Court had jurisdiction pursuant to 15 U.S.C. § 717f(h), which provides for jurisdiction in the District Court for eminent domain actions under the Natural Gas Act. We have jurisdiction over the grant of the preliminary injunction pursuant to 28 U.S.C. § 1292(a)(1). The grant of partial summary judgment, however, is not before us as the order did not end the litigation as to all claims and all parties. See Andrews v. United States, 873 U.S. 334, 340, 83 S.Ct. 1236, 10 L.Ed.2d 383 (1963). Nor was the order certified by the District Court pursuant to Fed. R. Civ. P. 54(b), which provides that the District Court may direct entry of judgment as to fewer than all claims if it “expressly determines that there is no just reason for delay.” Fed. R. Civ. P. 54(b). 1

We review the denial of a motion for a preliminary injunction for an abuse of discretion but review the District Court’s underlying legal conclusions de novo. Brown v. City of Pittsburgh, 586 F.3d 263, 268 (3d Cir. 2009). To obtain injunctive relief, a party must show a likelihood of success on the merits, irreparable harm if the injunction is not granted, that relief will not cause greater harm to the nonmoving party, and that relief is in the public interest. Miller v. Mitchell, 598 F.3d 139, 147 (3d Cir. 2010).

Likelihood of success on the merits

In order to bring suit in federal court under the Natural Gas Act, the plaintiff must have been granted a certificate by the FERC, it must have been unable to acquire the rights of way by a contract with the property owner, and the value of the property interest as claimed by the owner must be more than $3000.15 U.S.C. § 717f(h). Regec does not dispute any of these elements. The Act provides that if the holder of a certificate is unable to acquire the needed rights of ways by contract with the landowner, it may automatically acquire the rights of way through eminent domain in a United States District Court. See 15 U.S.C. § 717f(h); Columbia Gas Transmission, LLC v. 1.01 Acres, 768 F.3d 300, 304 (3d Cir. 2014). The only remaining issue to be decided by the District Court is the com: pensation the landowner receives in return for the condemnation. Columbia Gas Transmission, LLC, 768 F.3d at 304. As Appellee fulfilled the requirements under § 717f(h) for taking the property interests by eminent domain, it has demonstrated a likelihood of success on the merits of its condemnation claim.

While Regec claims that several statutes and rules relied on by the District Court violated the United States and Pennsylvania constitutions, the argument underlying these claims is that the condemnation of his property interests violated his constitutional right to due process. However, Regec received notice that Appellee was seeking a certificate that included necessary rights of way on his property. He had the opportunity to comment on and intervene in the administrative process before the FERC. He did not do so. Because he received notice and the opportunity to respond in the FERC proceedings and will have the opportunity to litigate just compensation in the District Court, Regec has received the process he was due. See Williamson Cty. Reg’l Planning Comm’n v. Hamilton Bank of Johnson City, 473 U.S. 172, 194, 105 S.Ct. 3108, 87 L.Ed.2d 126 (1985) (“The Fifth Amendment does not proscribe the taking of property; it proscribes taking without just compensation. Nor does the Fifth Amendment require that just compensation be paid in advance of, or contemporaneously with, the taking; all that is required is that a ‘reasonable, certain and adequate provision for obtaining compensation’ exist at the time of the taking.”) (internal citation omitted); Mullane v. Cent. Hanover Bank & Trust Co., 339 U.S. 306, 314, 70 S.Ct. 652, 94 L.Ed. 865 (1950) (fundamental requirements of due process are notice and opportunity to be heard); Elterich v. City of Sea Isle City, 477 F.2d 289, 290 (3d Cir. 1973) (exercise of eminent domain power does not violate due process). Regec’s arguments do not undermine Appellee’s likelihood of success on the merits.

Regec argues that Appellee’s taking of his property goes beyond the reach of the FERC certificate because the permanent right of way for the pipeline will cut off his access to part of the property not covered by the certificate. Regec also claims that the taking of the property constitutes an unreasonable seizure in violation of the Fourth Amendment because he will be unable to access the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
709 F. App'x 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-co-v-permanent-easement-for-259-acres-ca3-2017.