TransCanada Hydro Ne. Inc. v. Town of Vernon

CourtVermont Superior Court
DecidedAugust 8, 2011
Docket544
StatusPublished

This text of TransCanada Hydro Ne. Inc. v. Town of Vernon (TransCanada Hydro Ne. Inc. v. Town of Vernon) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TransCanada Hydro Ne. Inc. v. Town of Vernon, (Vt. Ct. App. 2011).

Opinion

TransCanada Hydro Ne. Inc. v. Town of Vernon, No. 544-10-10 Wmcv (Wesley, J., Aug. 8, 2011)

[The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the accompanying data included in the Vermont trial court opinion database is not guaranteed.] STATE OF VERMONT

SUPERIOR COURT CIVIL DIVISION Windham Unit Docket No. 544-10-10 Wmcv

TransCanada Hydro Northeast Inc. Plaintiff

v.

Town of Vernon Defendant

Order Denying Plaintiff’s Motion for Summary Judgment

Plaintiff, TransCanada Hydro Northwest Inc. (“TransCanada”), appeals a property assessment made by the Town of Vernon (“the Town”) of the hydropower facility it owns in Vernon, Vermont. TransCanada owns and operates a power plant located partially in Vernon, Vermont and partially in Hinsdale, New Hampshire. The Town determined the listed value of the property to be $32,075,500 as of April 1, 2010. TransCanada challenges this valuation, and asserts that the value was established by a determination made by the Director of the Division of Property and Review as $25,169,800 as of April 1, 2009. The Director made this valuation following an appeal of the Town’s 2009 appraisal.

TransCanada has moves for summary judgment claiming that the so-called “Freeze Act” (32 V.S.A. § 4468) requires that the listed value of the property as of April 1, 2010 be set at the value determined by the Director as of April 1, 2009. The Freeze Act provides, in relevant part, that:

“… [an] appraisal so fixed by the director… shall become the basis for the grand list of a taxpayer for the year in which the appeal is taken and … for the two next ensuing years. … The appraisal however may be changed in the ensuing two years if the taxpayer’s property is materially altered, changed, damaged, or if the municipality, city or town in which it is located has undergone a complete reevaluation of all taxable real estate.”

32 V.S.A. § 4468 (emphasis added).

TransCanada claims, and the Town does not dispute, that no material change to the physical structure of the property occurred between April 1, 2009 and April 1, 2010, nor did the Town undertake a revaluation of all taxable real estate in Vermont. In the absence of such changed circumstances, TransCanada maintains that the 2010 revaluation was in violation of the Freeze Act and must be set aside by the Court as a matter of law. However, the Town maintains that the Freeze Act is inapplicable here, and that the reappraisal was valid and justified. The Town acknowledges that no material change to the generating capacity of TransCanada’s power plant has taken place since April 1, 2009, nor does it attack the Director’s decision as to the 2009 valuation appeal. Rather, the Town asserts that, although significant improvements to the plant’s generating capacity were completed by the time of the 2009 appeal, the recognized methodology for fully accounting for the revenue anticipated associated with those improvements included a “lag”, such that those anticipated revenues increased significantly between April 1, 2009 and April 1, 2010, resulting in a higher assessment using the income approach to valuation. The Town insists that this “lag” effect must be recognized as a material change that prevents the application of the Freeze Act. The Court agrees.

Factual Background

The Town supports its claims for disputed and uncontested facts with the affidavit of George E. Sansoucy, a licensed engineer and licensed appraiser, who has been employed by the Town of Vernon to appraise and assess the power facility for the last fifteen years. Mr. Sansoucy explains that the most recent and final phase of an overall site upgrade project, in the works for many years, was TransCanada’s replacement of four turbines. The replacement resulted in an increase in power generating capacity for the plant. The method of accounting for the value to the plant added by the improved generating capacity is at the heart of the current dispute.

As observed in the Director’s opinion as to TransCanada’s appeal of the 2009 assessment, (“Director’s opinion”), issued on Nov. 16, 2010: “The income approach to value is the most appropriate since information on an income stream is available and the cost and market approaches are not appropriate for use in this evaluation.” Neither party disputed the use of the income approach, then or now; thus, the crux of any dispute as to value turns upon variations in the data that are used to generate projected income streams associated with the manufacture of electricity. Once projected, those income streams are discounted to present value to establish the value of the facilities that produce them. See US Gen New England, Inc. v. Town of Rockingham, 177 Vt. 193, 195-97 (2004) (examining the income capitalization approach to valuing a hydro-electric plant).

Mr. Sansoucy further attests that the universal and customary convention for the valuation of public utility property is to base the valuation on the data available as of December 31st of the next-to-previous year. Thus, with respect to the two years at issue in this case, the Town based its assessment for April 1, 2009 on projections from data on the books as of December 31, 2007; the Town based its assessment for April 1, 2010 on projections from data on the books as of December 31, 2008. This is done for a number of reasons: first, the lag permits more effective alignment with quarterly and end of year reporting requirements for utility companies, many of which are subsidiaries of larger companies; second, and particularly during periods of expansion in capital investment, the lag guards against over-estimating future income streams, which may lead to the need for later correction. Mr. Sansoucy states that the convention of using data from December 31st of the next-to-previous year is not isolated to TransCanada,

2 but is applied to all utilities and power generation facilities in Vernon equally, including the Vermont Yankee nuclear plant.

It is apparent from the Director’s opinion that neither party contested the methodology involving reliance on lagged data in the appeal of the 2009 assessment. The Town had assessed the plant at $24,779,300 for the generating facilities, plus $390,500 for the value of the land, using the income capitalization approach based on an analysis undertaken by Mr. Sansoucy. As he indicates in his current affidavit, that analysis relied on income and expense data posted as of December 31, 2007. The basis for TransCanada’s appeal, however, was claimed error in: 1) failing to properly account for personal property; 2) failing to include certain expected costs for relicensing in the income capitalization analysis; and 3) failing to exempt the value of fish ladder structures from the taxable property. The Director rejected each of these challenges, finding “that the appellant was not able to overcome the presumption of value determined by the Town of Vernon for the real property.” Thus, the assessed value established as of April 1, 2009, as upheld by the Director, was based on Mr. Sansoucy’s methodology, incorporating the convention of reliance on lagged data for revenues and expenses which he claims is standard for the industry, and reflected in the history of assessments of the plant by the Vernon listers.

In making its assessment for April 1, 2010, the listers relied on Mr. Sansoucy’s new capitalization analysis, which incorporated revenues and expenses as posted on Dec. 31, 2008. Mr. Sansoucy acknowledges that, as compared with the 2007 data used for the 2009 assessment, the ISO annual rated capacity of the plant was reduced to 34.4 megawatts from the previous rating of 36.79 megawatts. The reduced capacity was employed in the 2010 capitalization analysis. As further observed, however:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shetland Properties, Inc. v. Town of Poultney
484 A.2d 929 (Supreme Court of Vermont, 1984)
Kremer v. Lawyers Title Ins. Corp.
2004 VT 91 (Supreme Court of Vermont, 2004)
USGen New England, Inc. v. Town of Rockingham
2004 VT 90 (Supreme Court of Vermont, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
TransCanada Hydro Ne. Inc. v. Town of Vernon, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcanada-hydro-ne-inc-v-town-of-vernon-vtsuperct-2011.