TransAlta Centralia Generation, L.L.C. v. Sicklesteel Cranes, Inc.

142 P.3d 209, 134 Wash. App. 819
CourtCourt of Appeals of Washington
DecidedAugust 29, 2006
DocketNos. 33210-8-II; 33520-4-II
StatusPublished
Cited by12 cases

This text of 142 P.3d 209 (TransAlta Centralia Generation, L.L.C. v. Sicklesteel Cranes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TransAlta Centralia Generation, L.L.C. v. Sicklesteel Cranes, Inc., 142 P.3d 209, 134 Wash. App. 819 (Wash. Ct. App. 2006).

Opinion

Penoyar, J.

¶1 TransAlta Centraba Generation, L.L.C., TransAlta Corporation, and TransAlta Energy Corporation1 appeal from two grants of summary judgment for (1) failure to mitigate damages by not enforcing a force majeure clause2 in a contract between TransAlta Centraba Generation, L.L.C., and TransAlta Energy Marketing, Inc., and (2) dismissing claims for economic damages for foreign exchange losses because pure economic damages are unrecoverable in tort. We reverse and remand in part and affirm in part.

[822]*822FACTS

I. TransAlta’s Corporate Structure

¶2 TransAlta Centralia Generation, L.L.C. (LLC), and TransAlta Energy Marketing, Inc. (TEMUS), are both wholly owned subsidiaries of TransAlta Corporation (TAC). The LLC and TEMUS are sister entities and entered into a contract in which the LLC agreed that it desired to sell to TEMUS all available energy, capacity, and ancillary services generated at the Centralia Power Plant (the plant). TEMUS is a power marketer authorized to buy and sell electric power at wholesale negotiated rates. Under the contract, TEMUS agreed that it would resell the LLC’s energy output on the open market.

¶3 The LLC and TEMUS agreed that the LLC would provide TEMUS with energy output and that TEMUS would pay the LLC the net power revenue (NPR) minus TEMUS’s marketing fees. NPR is:

the total aggregate net power revenue from all transactions for the sale of [energy] Output by TEMUS minus the sum of all costs incurred by TEMUS in connection with the sale of the [energy] Output, including without limitation: i) the total aggregate net cost of all energy or capacity purchase transactions by TEMUS that were required to fulfil [sic] the outstanding contractual commitments due to Centralia having been derated for any reason ....

Clerk’s Papers (CP) at 722.

¶4 Further, the parties agreed that:

(a) Unless otherwise agreed, on or before the tenth (10th) day of each calendar month, TEMUS will provide the LLC with a statement of payment covering the prior calendar month. The statement of payment will set forth the Sale Price, the quantity of [energy] Output and ancillary services that were sold, together with any other relevant transactions.
(c) To the extent that the Sale Price is a negative number (such negative Sale Price to be defined as the “Deficit Amount”), [823]*823then the LLC will within 10 Business Days following LLC’s receipt of a statement from TEMUS for such Deficit Amount, remit to TEMUS the Deficit Amount by wire transfer pursuant to instructions for such wire transfer provided by TEMUS.

CP at 725.

¶5 The contract also included a force majeure clause, providing that the LLC’s and TEMUS’s performance under the contract could be suspended during a force majeure event, or an event outside the parties’ control. It read:

(a) Except with regard to a Party’s obligation to make payments under this Agreement, in the event either Party hereto is rendered unable, wholly or in part, by Force Majeure to carry out its obligations, upon such Party’s giving notice and full particulars of such Force Majeure as soon as reasonably possible, such notice to be confirmed in writing or by facsimile to the other Party, such obligations of said Party will, to the extent they are affected by such Force Majeure, be suspended during the continuance of said inability.
(c) “Force Majeure” means an event that (i) is not within the control of the Party relying thereon and (ii) could not have been prevented or avoided by such Party through the exercise of due diligence.

CP at 724 (emphasis added).

II. The Crane Accident and Resulting Lawsuit

¶6 TransAlta purchased an agreement in which a construction and engineering consortium had been hired to install equipment at the plant. The consortium subcontracted with PSF Industries, Inc., to perform the work, and PSF subcontracted with Sicklesteel.

¶7 On February 27, 2001, there was a crane accident at the plant; a Sicklesteel crane rolled over and damaged two conveyor belts. The conveyor belts were essential to the plant’s operation because they transported coal into the plant that was used to generate the plant’s energy.

[824]*824¶8 The plant was shut down from February 27 to March 3, while the conveyor belts were repaired. During this time, the LLC’s contractual obligation to provide power to TEMUS continued. The LLC did not attempt to evoke the force majeure clause in the LLC and TEMUS’s agreement and did not make any other attempt to halt its contractual obligation to provide power to TEMUS. TEMUS purchased replacement power on the open market. It incurred substantial costs in purchasing the replacement power. If the LLC had not provided TEMUS with power, it could have been in breach of its contractual obligation to sell power to TEMUS and would have left TEMUS with a deficient power supply. TEMUS, then, would likely have been unable to meet its contractual obligations with other entities outside the TransAlta corporate structure.

¶9 After incurring the costs of the replacement power, the LLC, TAC, and TransAlta Energy Corporation sued Sicklesteel et al. for negligence, violations of the Washington products liability act, breach of contract, and foreign exchange losses resulting from the crane damage at the plant. TEMUS is not a party to this action.

¶10 Sicklesteel et al. moved for partial summary judgment, arguing that TransAlta failed to mitigate its damages because the LLC could have invoked the force majeure clause in the LLC and TEMUS’s contract. If it had done so, Sicklesteel et al. argued, TransAlta would not have had to purchase the replacement power and would not have incurred the damages for suspension of the power supply when the plant was shut down. The trial court granted summary judgment in favor of Sicklesteel et al. regarding force majeure and dismissed TransAlta’s damage claims related to the cost of the replacement power.

¶11 Next, Sicklesteel et al. moved for partial summary judgment, arguing that TransAlta’s claims for damages based on foreign exchange losses were improper and should have been dismissed. The trial court granted summary judgment in favor of Sicklesteel et al. regarding foreign [825]*825exchange losses and dismissed TransAlta’s claims based on foreign exchange losses. TransAlta now appeals both summary judgment rulings.

ANALYSIS

I. Standard of Review

¶12 On review of an order for summary judgment, we perform the same inquiry as the trial court. Hisle v. Todd Pac. Shipyards Corp., 151 Wn.2d 853, 860, 93 P.3d 108 (2004). The standard of review is de novo and we consider all facts in the light most favorable to the nonmoving party. Vallandigham v. Clover Park Sch. Dist. No. 400, 154 Wn.2d 16, 26, 109 P.3d 805 (2005).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woessner v. Home Depot USA Inc
W.D. Washington, 2023
Allstate Insurance Company v. Efleda Paz
Court of Appeals of Washington, 2016
Shawn Greenhalgh, James Pfaff, V State Dept Of Corr
Court of Appeals of Washington, 2014
Greenhalgh v. Department of Corrections
324 P.3d 771 (Court of Appeals of Washington, 2014)
Affiliated FM Insurance v. LTK Consulting Services, Inc.
15 F. Supp. 3d 1116 (W.D. Washington, 2014)
Maziar v. Department of Corrections
327 P.3d 1251 (Court of Appeals of Washington, 2014)
Newport Yacht Basin Ass'n of Condominium Owners v. Supreme Northwest, Inc.
168 Wash. App. 86 (Court of Appeals of Washington, 2012)
Marshall v. Thurston County
267 P.3d 491 (Court of Appeals of Washington, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
142 P.3d 209, 134 Wash. App. 819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transalta-centralia-generation-llc-v-sicklesteel-cranes-inc-washctapp-2006.