Trans-County Water, Inc. v. Central Colorado Water Conservancy District

727 P.2d 60, 1986 Colo. LEXIS 647
CourtSupreme Court of Colorado
DecidedNovember 3, 1986
Docket84SA412
StatusPublished
Cited by16 cases

This text of 727 P.2d 60 (Trans-County Water, Inc. v. Central Colorado Water Conservancy District) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trans-County Water, Inc. v. Central Colorado Water Conservancy District, 727 P.2d 60, 1986 Colo. LEXIS 647 (Colo. 1986).

Opinion

*62 ERICKSON, Justice.

Trans-County Water, Inc. (Trans-County) appeals a decision of Water Division I of the District Court (water court) denying Trans-County’s application for a quadren-nail finding of reasonable diligence in the development of a conditional appropriation. We affirm.

I.

On June 8, 1978, Trans-County was awarded a conditional water right to divert, store, and refill 466,800 acre-feet of water and direct flow rights totalling 2,060 cubic feet per second from the South Platte River near Julesburg, Colorado. The amount to be diverted exceeds in most years the measured flow of the South Platte River at the Julesburg gauging station. The purpose of the diversion was to provide irrigation for northeastern Colorado and to supplement and recharge the declining Ogalla-la Aquifer. The 1978 decree called for Trans-County to divert the water at five separate diversion facilities, and to store the water in eleven proposed reservoirs.

Section 37-92-301(4), 15 C.R.S. (1973), requires that the owner of a conditional water right must obtain quadrennial findings of reasonable diligence in the development of the conditional appropriation. Accordingly, the 1978 decree required Trans-County to file an application with the court “on or before November 1981” for a determination that Trans-County had exercised reasonable diligence in the development of the South Platte River project. As a guide to Trans-County, the water court set forth the following five “minimum criteria” of reasonable diligence that Trans-County was required to meet to obtain its first quadrennial finding of reasonable diligence:

(1) Formation of a taxing district to develop and operate the project;
(2) Execution of agreements or initiation of condemnation proceedings for the use of the Prewitt Reservoir;
(3) Preparation and submission of a comprehensive work schedule;
(4) Commencement of land surveying and soil tests of dam sites, recharge areas, and construction sites; and
(5) Procurement of interim and permanent financing commitments for the lower river phase and the development of a plan for financing the entire system.

In November of 1981, Trans-County requested an extension of time within which to file its application for a quadrennial finding of reasonable diligence. The water court granted the extension to January 29, 1982, and the application was filed within the extended time period.

Objections to the application were filed by the Central Colorado Water Conservancy District, the Management Subdistrict, of the Central Colorado Water Conservancy District, the Cache La Poudre Water Users Association, the City of Broomfield, the Irrigationists Association, the Lower South Platte Water Conservancy District, and the Prewitt Operating Committee (Objectors). The Objectors asserted that Trans-County had not been diligent in developing the conditional appropriation, and that the water court lacked jurisdiction to grant an extension of time.

The issues were tried to the court on April 25-27, 1983. The evidence presented at trial established that Trans-County had spent the bulk of the preceding diligence period attempting to procure financing to conduct a feasibility study of the project. Trans-County’s proof of diligence included general educational efforts to promote the project, general discussions and talks with public officials, and various attempts to solicit donations and pledges to finance the feasibility study. Although Trans-County expended approximately $30,000 on efforts to obtain financing for the feasibility study, Trans-County’s efforts were unsuccessful.

In 1980, in an effort to obtain funds from another source, Trans-County petitioned the Yuma County District Court to form, a taxing district to develop and operate the project. Trans-County paid for the costs of the petition by issuing $51,586.25 in promissory notes that were payable only upon the *63 successful formation of the taxing district. The petition was denied because Trans-County failed to establish the feasibility of the project, and because a taxing district could not be formed for the purpose of obtaining funds to conduct a feasibility study.

Trans-County failed to produce evidence that it complied with the “minimum criteria” of reasonable diligence set forth in the conditional decree. Trans-County’s attempt to form a taxing district was unsuccessful, and Trans-County made no effort to effect an agreement with the owners of the Prewitt Reservoir. Although Trans-County did prepare a work program that, if followed, would meet the minimum criteria set forth in the 1978 decree, it failed to comply with that schedule. Finally, Trans-County conducted no on-site activity, performed no land surveying or soil tests, obtained no easements for on-site work, and failed to obtain interim or permanent financing for the project.

On June 17, 1983, the court entered a memorandum decree finding that Trans-County had not exercised reasonable diligence in the development of its conditional appropriation. The water court relied primarily on Trans-County’s lack of progress in developing the project, and on Trans-County’s failure to meet the “minimum criteria” of reasonable diligence set forth in the 1978 decree. The memorandum decision and decree entered by the water judge after reviewing the minimum criteria and the evidence presented stated:

The Court does not consider these requirements absolutely binding on the Court. The Court must determine each application on an ad hoc basis in light of all the factors present in each particular case. Colorado River Water Conservation District v. Denver, 642 P.2d 510, 513 (1982). The Court does, however, give considerable weight to these requirements set out in the conditional decree as they state the judgments of the Water Judge who heard the original Application for Conditional Water Right. The purpose of the Water Court in establishing these requirements as minimum evidence is apparent. A conditional water right must amount to something more than a dream or a vision. The Court in granting the conditional water right determined that these five minimum criteria were necessary to establish, four years later, if the dream had progressed sufficiently that it could become a reality. All of the evidence added together whether judged by these five criteria or “all the facts and circumstances” relating to the development of the project, Colorado River Water Conservation District v. Denver, 640 P.2d 1139, 1141 (1982), demonstrate that this project is no more a reality or less of a dream that it was upon the entry of the conditional decree. No one knows if the project will work or if it will provide a benefit to its intended beneficiaries.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Upper Yampa Water Conservancy District v. Wolfe
255 P.3d 1108 (Supreme Court of Colorado, 2011)
City of Lafayette v. New Anderson Ditch Co.
962 P.2d 955 (Supreme Court of Colorado, 1998)
Dallas Creek Water Co. v. Huey
933 P.2d 27 (Supreme Court of Colorado, 1997)
Tulkisarmute Native Community Council v. Heinze
898 P.2d 935 (Alaska Supreme Court, 1995)
Northern Colorado Water Ass'n v. Three Peaks Water, Inc.
859 P.2d 836 (Supreme Court of Colorado, 1993)
Public Service Co. of Colorado v. Blue River Irrigation Co.
829 P.2d 1276 (Supreme Court of Colorado, 1992)
Darby v. All J Land and Rental Co.
821 P.2d 297 (Supreme Court of Colorado, 1991)
City of Florence v. Board of Waterworks of Pueblo
793 P.2d 148 (Supreme Court of Colorado, 1990)
Talco, Ltd. v. Danielson
769 P.2d 468 (Supreme Court of Colorado, 1989)
Application for Water Rights
731 P.2d 665 (Supreme Court of Colorado, 1987)
Vail Valley Consolidated Water District v. City of Aurora
731 P.2d 665 (Supreme Court of Colorado, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
727 P.2d 60, 1986 Colo. LEXIS 647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trans-county-water-inc-v-central-colorado-water-conservancy-district-colo-1986.