Trans-Allegheny Interstate v. Lyle W. and Brenda P. Daugherty

CourtWest Virginia Supreme Court
DecidedNovember 22, 2013
Docket13-0253
StatusPublished

This text of Trans-Allegheny Interstate v. Lyle W. and Brenda P. Daugherty (Trans-Allegheny Interstate v. Lyle W. and Brenda P. Daugherty) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trans-Allegheny Interstate v. Lyle W. and Brenda P. Daugherty, (W. Va. 2013).

Opinion

STATE OF WEST VIRGINIA

SUPREME COURT OF APPEALS

Trans-Allegheny Interstate Line Company, FILED Plaintiff Below, Petitioner November 22, 2013 RORY L. PERRY II, CLERK SUPREME COURT OF APPEALS vs) No. 13-0253 (Hardy County 09-C-70) OF WEST VIRGINIA

Lyle W. Daugherty and Brenda P. Daugherty, Defendants Below, Respondents

MEMORANDUM DECISION Petitioner Trans-Allegheny Interstate Line Company (“TAILC”), by counsel John Philip Melick, Elizabeth A. Amandus, and Richard Grady Ford, appeals the February 7, 2013, order of the Circuit Court of Hardy County denying its motion for new trial following a jury trial. Respondents Lyle W. Daugherty and Brenda P. Daugherty, by counsel Robert L. Bays and Charles F. Printz Jr., filed a response, asserting cross-assignments of error stemming from the circuit court’s denial of their motion for new trial. Petitioner also submitted a reply.

This Court has considered the parties’ briefs and the record on appeal. The facts and legal arguments are adequately presented, and the decisional process would not be significantly aided by oral argument. Upon consideration of the standard of review, the briefs, and the record presented, the Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision is appropriate under Rule 21 of the Rules of Appellate Procedure.

In 2008, the Public Service Commission of West Virginia (“PSC”) certified Petitioner TAILC’s construction of the Trans-Allegheny Interstate Line, a 500 kV electric transmission line from southwest Pennsylvania, across northeast West Virginia, and into Virginia (“the line”). An easement was condemned for a portion of the certified route across two parcels of respondents’ land in Hardy County when it was unable to negotiate an agreement with respondents. The line was then constructed and energized in May of 2011, and the only issue remaining for the circuit court was to decide the appropriate amount of compensation due to respondents. The matter went to trial in October of 2012.

Respondents’ land was used largely for raising chickens for Pilgrim’s Pride, and they were concerned that the line would interfere with those activities. Petitioner contends that respondents failed to produce any competent evidence of such interference and that the circuit court repeatedly ruled that such unproven assertions could not be made at trial. During the trial, Mike Ellington, a long-time employee of Pilgrim’s Pride, testified as to the impact of the line on respondents’ property as it relates to respondents’ contract with Pilgrim’s Pride.

1 At the conclusion of the trial, the jury awarded compensation for the decrease in the fair market value of respondents’ property in the amount of $54,000 and for residual damages in the amount of $321,000. The circuit court entered its “Order of Judgment on Jury Verdict” on November 1, 2012, setting forth those awards and ordering petitioner to pay $375,000 to respondents, plus interest and court costs. Both parties then filed motions for a new trial, and by order entered February 7, 2013, the circuit court denied those motions. TAILC appeals the denial of its motion for new trial, and respondents submit cross-assignments of error appealing the denial of their motion for new trial.

This Court reviews the rulings of the circuit court concerning a new trial and its conclusion as to the existence of reversible error under an abuse of discretion standard, and we review the circuit court’s underlying factual findings under a clearly erroneous standard. Questions of law are subject to a de novo review.

Syl. Pt. 1, Burke-Parsons-Bowlby Corp. v. Rice, 230 W.Va. 105, 736 S.E.2d 338 (2012). Further:

“‘the ruling of a trial court in granting or denying a motion for a new trial is entitled to great respect and weight, [and] the trial court’s ruling will be reversed on appeal [only] when it is clear that the trial court has acted under some misapprehension of the law or the evidence.’ Syl. pt. 4, in part, Sanders v. Georgia-Pacific Corp., 159 W.Va. 621, 225 S.E.2d 218 (1976).” Syllabus point 2, Estep v. Mike Ferrell Ford Lincoln-Mercury, Inc., 223 W.Va. 209, 672 S.E.2d 345 (2008).

Syl. Pt. 2, Peters v. Rivers Edge Min., Inc., 224 W.Va. 160, 680 S.E.2d 791 (2009).

On appeal, petitioner asserts three assignments of error and respondents assert four cross- assignments of error.

I. Petitioner’s assignments of error

Petitioner asserts three assignments of error, which have a great deal of overlap. First, petitioner asserts that the evidence “of Mr. Ellington” was irrelevant under the circuit court’s pretrial orders and was unfairly prejudicial. As part of that alleged error, petitioner contends that the circuit court erred by overruling petitioner’s repeated objections to Mr. Ellington’s testimony. In its second assignment of error, petitioner contends that the circuit court compounded its erroneous rulings related to Mr. Ellington’s testimony by admitting Mr. Ellington’s unqualified, speculative memorandum as documentary evidence. Finally, petitioner contends that the circuit court erred in denying petitioner’s motion for a new trial, based on the erroneous rulings on the evidence related to Mr. Ellington and the unfairly prejudicial, surprise testimony of Respondent Mr. Daugherty, each orchestrated by counsel for respondents and exploited throughout the trial, including in closing argument.

During Mr. Ellington’s testimony, the circuit court allowed the admission of an undated memorandum authored by Mr. Ellington. That memorandum states, in relevant part, that “[i]f the power line to be constructed through [respondents’] property . . . follows the path that

2 [respondents] showed [him that day], then any future expansion of their poultry operation would be prohibited by the power line right of way. Poor performance due to any electrical or controller issues could result in the termination of [the contract between Pilgrim’s Pride and respondents.]” Petitioner claims that counsel for respondents consistently represented, both before and at the outset of trial, that Mr. Ellington would testify that respondents could not expand their chicken farming operations due to the installation of the line. On the first day of trial, the circuit court ruled that Mr. Ellington could testify, despite petitioner’s contention that the testimony would be a waste of time, would potentially confuse the jury, and would unfairly prejudice petitioner by inviting an additional award reflecting a loss of a particular business that had not been evacuated. Petitioner argues that Mr. Ellington was not an expert qualified to address the impact of the line. Petitioner contends that the memorandum drafted by Mr. Ellington was inadmissible and was not material evidence in its own right. Petitioner, therefore, contends that it was materially prejudiced by the erroneous introduction of this unqualified, speculative memorandum.

Petitioner also asserts that counsel for respondents elicited inadmissible testimony about electrical problems in the existing poultry houses, in violation of the pre-trial rulings of the circuit court. Petitioner objected to such testimony, and the circuit court sustained that objection. During cross-examination, petitioner asked Mr. Daugherty to admit that his chicken barns had remained in full and successful operation since energization, just as he had in pretrial discovery responses verified under oath.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laslo v. Griffith
102 S.E.2d 894 (West Virginia Supreme Court, 1958)
McDougal v. McCammon
455 S.E.2d 788 (West Virginia Supreme Court, 1995)
Peters v. Rivers Edge Mining, Inc.
680 S.E.2d 791 (West Virginia Supreme Court, 2009)
West Virginia Division of Highways v. Butler
516 S.E.2d 769 (West Virginia Supreme Court, 1999)
Sanders v. Georgia-Pacific Corp.
225 S.E.2d 218 (West Virginia Supreme Court, 1976)
Wilt v. Buracker
443 S.E.2d 196 (West Virginia Supreme Court, 1994)
Estep v. Mike Ferrell Ford Lincoln-Mercury, Inc.
672 S.E.2d 345 (West Virginia Supreme Court, 2009)
Helmick v. Potomac Edison Co.
406 S.E.2d 700 (West Virginia Supreme Court, 1991)
Wilkinson v. Bowser
483 S.E.2d 92 (West Virginia Supreme Court, 1996)
Gentry v. Mangum
466 S.E.2d 171 (West Virginia Supreme Court, 1995)
Burke-Parsons-Bowlby Corp. v. Rice
736 S.E.2d 338 (West Virginia Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Trans-Allegheny Interstate v. Lyle W. and Brenda P. Daugherty, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trans-allegheny-interstate-v-lyle-w-and-brenda-p-d-wva-2013.