Trainor Co. v. Ætna Casualty & Surety Co.

49 F.2d 769, 1931 U.S. Dist. LEXIS 1337
CourtDistrict Court, E.D. Pennsylvania
DecidedFebruary 2, 1931
DocketNo. 15318
StatusPublished
Cited by2 cases

This text of 49 F.2d 769 (Trainor Co. v. Ætna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trainor Co. v. Ætna Casualty & Surety Co., 49 F.2d 769, 1931 U.S. Dist. LEXIS 1337 (E.D. Pa. 1931).

Opinion

KIRKPATRICK, District Judge.

This is a suit by an obligee against the surety upon a bond for the completion of a building operation. The trial was to the court without a jury.

Findings of Fact.

1. The Trainor Company, plaintiff, on October 13, 1927, conveyed certain real estate to Copley Homes, Inc., a corporation organized to carry out a proposed house buffering operation. The details are unimportant, but it may be taken (a) that as a result of the transaction Copley Homes owed the Trainor Company $28,000; (b) that this sum was a part of the purchase price of the real estate; and (c) that it was all profit to the Trainor Company, accruing to it without any capital investment on its part,' simply by turning the land' over to Copley Homes at an advance over the price at which it was able to buy it for itself. This last fact was not disclosed to the defendant at any time prior to the execution of the bond in suit.

2. In order to finance its building operation, Copley Homes borrowed inoney from the Sun Mortgage- Company and its subsidiary, Realty Bond & Finance Corporation, two corporations organized to finance building operations, giving to the Sun Mortgage Company as collateral security a separate first mortgage of $4,500 upon each of the 52 lots comprising the operation; and, to Realty Bond & Finance Corporation, a blanket second mortgage of $88,000 covering the entire tract, which mortgage had a release clause of $2,000 per house'. The amounts borrowed were less than the amounts of the mortgages placed and assigned as collateral security, so that the net result of the financing was, in substance and without entering into all of the details, that each of the lots had against it a first mortgage of $4,500 and what amounted to a second mortgage of $2,-000, and that there was a small equity in the first mortgage (which may be disregarded) and an equity in the second mortgage over and above the amount borrowed upon it amounting to approximately $636 per lot. Copley Homes paid the Trainor Company the $28,000 due it by giving to the Trainor Company its note for that amount and assigning to it as collateral the equity in the second mortgage.

3. On the day of the general settlement (October 13, 1927) the bond in suit was executed by Copley Homes as principal and the ¿Etna Casualty & Surety Company, the defendant, as surety. The obligees were the Land Title & Trust Company (through (he medium of which the Sun Mortgage Company made its loan, and which was to act as its agent in handling the funds and paying contractors as the work progressed), Realty Bond & Finance Corporation, and the Trainor Company, the plaintiff. The bond had three conditions, the first of which was, in substance, “that, if within ten months , within the date hereof each of the lots * * * shall be fully improved and completed with a building, together with the other improvements (such as paved streets, sidewalks, driveways, gas, water, sewerage, etc.,), in keeping with and as shown by the aforesaid Plans, Specifications, and Conditions, Building Plats and Surveys, * * * then, in the event that all of the above-and below-mentioned conditions are fully performed, this Bond shall be Void; otherwise it shall remain in full force and effect in law.”

4. Copley Homes immediately began building 52 houses on the lots. On August 13, 1928, the date for completion fixed by the bond, 24 houses had been fully completed. The remaining 28 were not far from completion, but sufficient work remained to be done upon them to require a finding (and I so find) that they had not .been completed in accordance with the plans and specifications either fully or substantially.

5. Neither the plaintiff nor Copley Homes nor the defendant ever completed the operation. It was, however, ultimately completed on December 27, 1929, by the Sun Mortgage Company, holder of the first mortgages.

6. The value of the 28 uncompleted houses, as of August 13, 1928, was $6,700 each. This amount is in excess of the sum of the amount of the plaintiff’s mortgage on each house and all prior liens. In arriving at this value, in addition to the testimony of expert witnesses, the following facts were considered and may be taken as found:

[771]*771(a) The work actually remaining to be done consisted principally of installation of plumbing accessories such as spigots and shower curtains and rods, painting (which was about 75 per cent, complete), papering, installation of gas ranges and minor details in connection with carpenter work, plastering, and brickwork. The record of work remaining to be done made by the representative of the Land Title Company about August 13, 1928, is accepted as substantially correct.
(b) The original contract price for full completion of all the houses amounted to about $4,200 for each house (disregarding the slightly larger price for the comer houses). This was the price of building and did not include cost of land or financing.
(c) The price of the land without the houses to the Trainor Company was $76,000 or about $1,461 for each lot, and to Copley Homes $104,000' or $2,000 for each lot.
(d) Subsequent to August 13, 1928, the total sum of $26,071 was spent in completing the operation. Of this amount $4,000 went for street improvements and the balance, or $22,071, was spent in completing the houses. This would amount to approximately $788 for each house. How much of the total amount as expended went for work contracted for or actually installed prior to August 13, 1928, the testimony does not disclose. In addition, it is probable that some of the expenditures went for repairs to or replacement of work already done, since an operation which is allowed to stand uncompleted for so long a period is bound to deterioriate to some extent. It is also probable that the amount spent for completion under the new contract represents a smaller proportion of the whole work than an equal amount in the original contract price would have represented.
(e) Twenty of the completed houses were sold for the price of $7,950 each, 10 before August 13, 1928, and 10 after. The plaintiff concedes that the completed houses as of that date were worth $7,950 each.
(f) During 1928, 1929, and 1930 the value of real estate, generally and in the locality in which this operation was, declined steadily.

7. On July 24, 1929, 28 houses being still uncompleted, the defendant made an agreement with the Sun Mortgage Company, which effected the settlement of a number of matters arising out of various surety bonds which the defendant had written for operations in which the Sun Mortgage Company and its subsidiaries were interested, including the Copley Homes operation. One of the terms of that agreement was that the Sun Mortgage Company would complete the Copley Homes operation in accordance with plans and specifications. Thereafter the Sun Mortgage Company did complete the operation, as has been found. In entering into the settlement and in completing the houses the Sun Mortgage Company did not act as agent or in any other capaeitv for the plaintiff.

8. On January 25, 1930, the Sun Mortgage Company foreclosed its first mortgages buying in all the properties for .the sum of $50 and thus wiping out the second blanket mortgage of the Realty Bond & Mortgage Company and the equity of the Train- or Company therein.

9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hunt Bros. Construction, Inc. v. Wolcott
580 P.2d 418 (Idaho Supreme Court, 1978)
American Surety Co. of New York v. Franciscus
127 F.2d 810 (Eighth Circuit, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
49 F.2d 769, 1931 U.S. Dist. LEXIS 1337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trainor-co-v-tna-casualty-surety-co-paed-1931.