Tradesmen International, Inc. v. Lockheed Martin Corp.

241 F. Supp. 2d 1337, 2003 U.S. Dist. LEXIS 1254, 2003 WL 194471
CourtDistrict Court, D. Kansas
DecidedJanuary 27, 2003
Docket02-2183-JWL
StatusPublished

This text of 241 F. Supp. 2d 1337 (Tradesmen International, Inc. v. Lockheed Martin Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tradesmen International, Inc. v. Lockheed Martin Corp., 241 F. Supp. 2d 1337, 2003 U.S. Dist. LEXIS 1254, 2003 WL 194471 (D. Kan. 2003).

Opinion

MEMORANDUM & ORDER

LUNGSTRUM, District Judge.

This is an action by a subcontractor to recover amounts due for labor provided by it on a federal postal facility construction project. The United States Postal Service (“Postal Service”) entered into a $73 million contract with Lockheed Martin Corporation (“Lockheed Martin”) to supply and install automated parcel sorting equipment, known as Singulator Scan Induction Units (“SSIUs”), at various locations including Springfield, Massachusetts and Kansas City, Missouri. Lockheed Martin subcontracted with WestPac Electric, Inc. (“WestPac”) to install a portion of the equipment. WestPac, in turn, sub-subcontracted with Tradesmen International, Inc. (“Tradesmen”) to provide labor to West-Pac. Tradesmen asserts that it provided labor for WestPac, yet WestPac failed to pay Tradesmen the $86,624.32 it allegedly owes under their contract. According to Tradesmen, WestPac is now insolvent and judgment proof. Thus, Tradesmen brought this action against Lockheed Martin and the Postal Service in an attempt to recover the $86,624.32.

On August 1, 2002, Tradesmen filed its first amended complaint, which included an unjust enrichment claim against the Postal Service and Lockheed Martin, a third-party beneficiary breach of promise claim against Lockheed Martin, and a claim seeking an equitable lien on funds retained by the Postal Service and Lockheed Martin. Lockheed Martin and Tradesmen subsequently filed motions to dismiss each of the claims in the first amended complaint. On November 1, 2002, this court issued an order granting Lockheed Martin’s and the Postal Service’s motions to dismiss plaintiffs first amended complaint. Specifically, the court held that the doctrine of sovereign immunity barred Tradesmen’s claims *1339 against the Postal Service, and Tradesmen failed to state a claim with regard to each of its three claims against Lockheed Martin. This court, however, granted Tradesmen leave to amend its unjust enrichment and equitable lien claims against Lockheed Martin in an attempt to cure certain deficiencies in the claims. Following this ruling, Tradesmen elected to file a second amended complaint alleging an equitable lien claim against Lockheed Martin.

The matter is now before the court on Lockheed Martin’s motion to dismiss Tradesmen’s equitable lien claim pursuant to Rule 12(b)(6) for failure to state a claim upon which relief can be granted (Doc. 42). Specifically, Lockheed Martin argues that Tradesmen has failed to establish that Lockheed Martin has retained funds owed to WestPac and, alternatively, that the equities do not favor granting Tradesmen an equitable lien. Because the court finds that Tradesmen has alleged that Lockheed Martin has retained funds owed to WestPac, and Tradesmen’s allegations do support an equitable lien on the funds retained by Lockheed Martin, the court denies its motion to dismiss.

I. Standard for Rule 12(b)(1) Motion to Dismiss

The court will dismiss a cause of action for failure to state a claim only when “it appears beyond a doubt that the plaintiff can prove no set of facts in support of his claims which would entitle him to relief,” Poole v. County of Otero, 271 F.3d 955, 957 (10th Cir.2001) (quoting Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)), or when an issue of law is dispositive. Neitzke v. Williams, 490 U.S. 319, 326, 109 S.Ct. 1827, 104 L.Ed.2d 338 (1989). The court accepts as true all well-pleaded facts, as distinguished from con-clusory allegations, and all reasonable inferences from those facts are viewed in favor of the plaintiff. Smith v. Plati, 258 F.3d 1167, 1174 (10th Cir.2001). The issue in resolving a motion such as this is “not whether [the] plaintiff will ultimately prevail, but whether the claimant is entitled to offer evidence to support the claims.” Swierkiewicz v. Sorema N.A., 534 U.S. 506, 122 S.Ct. 992, 997, 152 L.Ed.2d 1 (2002) (quoting Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 40 L.Ed.2d 90 (1974)).

II. Analysis

The court’s November 1, 2002 order dismissed Tradesmen’s equitable lien claim because Tradesmen failed to allege that Lockheed Martin retained funds earmarked for WestPac. Tradesmen argues that its second amended complaint cures this deficiency because it alleges that Lockheed Martin wrongfully failed to secure a payment bond despite its knowledge that it should have been required to obtain such a bond; that Lockheed Martin knew of WestPac’s serious financial difficulties; that the Postal Service paid Lockheed Martin all or substantially all of the monies owed to it under the parties’ contract; that Lockheed Martin actively encouraged Tradesmen’s continued services on the project; that Lockheed Martin has failed and refused to compensate Tradesmen, despite Tradesmen’s repeated demands for compensation and Lockheed Martin’s knowledge that Tradesmen conferred benefits upon it; that Lockheed Martin has “failed and refused to pay WestPac the full amounts WestPac is owed under the subcontract;” that Lockheed Martin “is willfully and deliberately withholding funds owed to WestPac under the subcontract in excess of $2,750,000, which amount includes all amounts owed to Tradesmen for its work performed on the Projects and claimed herein.” 1 Relying on these alle *1340 gations, Tradesmen contends that it is entitled to an equitable lien, in an amount of not less than $86,624.32, against the funds retained by Lockheed Martin.

Tradesmen argues that its claim is supported by the case of Kennedy Elec. Co. v. United States Postal Serv., 508 F.2d 954 (10th Cir.1974). In Kennedy, a subcontractor who performed work on a post office building, but who was not paid because the contractor was insolvent and no Miller Act bond was posted, brought a “two pronged” equitable lien cause of action against the Postal Service for labor and material furnished. Id. at 955. The first prong of his equitable lien related to $35,739.47 that the Postal Service retained, and the second prong related to $190,747.00 that the Postal Service paid to the contractor’s assignee in violation of various regulations. Id. After considering the equities of the parties’ circumstances, the Tenth Circuit held that the subcontractor was entitled to an equitable lien both on the funds retained by the Postal Service and the money wrongfully disbursed to the contractor’s assignee. Id. at 960.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Scheuer v. Rhodes
416 U.S. 232 (Supreme Court, 1974)
Neitzke v. Williams
490 U.S. 319 (Supreme Court, 1989)
Swierkiewicz v. Sorema N. A.
534 U.S. 506 (Supreme Court, 2002)
Smith v. Plati
258 F.3d 1167 (Tenth Circuit, 2001)
Poole v. County of Otero
271 F.3d 955 (Tenth Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
241 F. Supp. 2d 1337, 2003 U.S. Dist. LEXIS 1254, 2003 WL 194471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tradesmen-international-inc-v-lockheed-martin-corp-ksd-2003.