Toxco Inc. v. Chu

CourtDistrict Court, District of Columbia
DecidedAugust 11, 2011
DocketCivil Action No. 2009-1925
StatusPublished

This text of Toxco Inc. v. Chu (Toxco Inc. v. Chu) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toxco Inc. v. Chu, (D.D.C. 2011).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

TOXCO, INC., : : Plaintiff, : Civil Action No.: 09-1925 (RMU) : v. : Re Document Nos.: 27, 33 : STEVEN CHU et al., : : Defendants. :

MEMORANDUM OPINION

GRANTING THE DEFENDANTS’ MOTION TO DISMISS OR, IN THE ALTERNATIVE, FOR SUMMARY JUDGMENT; GRANTING THE DEFENDANTS’ MOTION TO STRIKE THE PLAINTIFF’S SUR-REPLY

I. INTRODUCTION

This case is before the court on the defendants’ motion to dismiss as moot or, in the

alternative, for summary judgment. The plaintiff, Toxco, Inc., commenced this action against

the Department of Energy and the Secretary of the Department of Energy, alleging that the

defendants’ actions violated the Administrative Procedure Act (“APA”) and the Due Process

Clause of the Fifth Amendment. The defendants move to dismiss these claims pursuant to

Federal Rule of Civil Procedure 12(b)(1), alleging that the court lacks jurisdiction because the

plaintiff’s claims are moot. In the alternative, the defendants move for summary judgment under

Rule 56. Because the plaintiff’s APA claim is moot, the court grants the defendants’ motion to

dismiss as to that claim. With respect to the plaintiff’s remaining Due Process claim, the court

grants the defendant’s motion for summary judgment. II. BACKGROUND

A. Factual Background

The Department of Energy (“DOE”) oversees the disposal of radioactive waste at nuclear

waste facilities across the country. See 42 U.S.C. § 7133(a)(8)(A)-(E). One such facility is the

Separations Process Research Unit (“SPRU”), which operated from 1950 to 1953 as a pilot plant

to research the chemical extraction of uranium and plutonium from irradiated uranium. A.R. at

69.1 These operations contaminated the SPRU facility and the surrounding environment with

radioactive material, resulting in the need to remediate the site. Id.

In October 2004, the DOE awarded a contract for several waste disposal operations to

Accelerated Remediation Company (“ARC”), with individual projects to be specified in task

orders. See id. at 1-62. The contract permitted ARC to subcontract with other entities, provided

that the DOE formally consented to each individual subcontract. Id. at 47 (incorporating by

reference 48 C.F.R. § 52.244-2, which requires an agency’s Contracting Officer to consent

before a contractor may enter into a subcontract). In September 2007, the DOE issued Task

Order No. DE-AT30-07CC60013, SP15 (“Task Order SP15”), requiring ARC to engage in

environmental remediation of approximately fifteen acres in the SPRU land areas. See generally

A.R. at 63-105. Specifically, Task Order SP15 required the cleanup of radioactively and

chemically contaminated soil from two areas at SPRU: the Lower Level Railbed and the Lower

Level Parking Lot. Id. at 69.

In keeping with the terms of the DOE-ARC contract, in the summer of 2008 ARC

subcontracted with EnergySolutions, a Utah company, to complete the waste disposal work

under Task Order SP15. See generally id. at 346-48. Later that summer, ARC sought and

1 Citations to “A.R.” refer to the Administrative Record.

2 received the DOE’s permission to exit its subcontract with EnergySolutions as part of a cost-

savings initiative. See generally id. at 349-51, 401-05; see Defs.’ Mot. to Dismiss or, in the

Alternative, for Summ. J. (“Defs.’ Mot.”) at 8-9. ARC then solicited bids from other

subcontractors that wished to engage in the Task Order SP15 remediation work at SPRU. A.R.

at 402. In June 2009, Toxco, Inc. (“Toxco” or “the plaintiff”), a Tennessee company, submitted

a bid to perform the Task Order SP15 work. See generally id. at 397-411. Pursuant to federal

acquisition regulations and DOE guidelines, ARC required the DOE’s consent before it could

enter into a subcontract with Toxco. Id. at 47. On August 11, 2009, the DOE issued a letter

giving its formal consent to the subcontract. Id. at 450 (“Consent Order”). The Consent Order

included the following provision:

This consent shall in no way relieve the prime contractor of any obligations or responsibilities it may otherwise have under the contract or under law, shall neither create any obligation of the Government to, nor privity of contract with, the subcontractor or vendors, and shall be without prejudice to any right or claim of the Government under the prime contract. This consent does not constitute a determination as to the acceptability of the subcontract or the allowability of costs.

Id.

On August 12, 2009, having received the DOE’s formal consent, ARC entered into a

Purchase Order subcontract for the Task Order SP15 remediation work with Toxco. See

generally id. at 451-63. The period of performance for the subcontract ran through December

31, 2009. Id. at 452. The subcontract also incorporated by reference a federal regulation titled

“Termination for Convenience of the Government,” which allowed the government to “terminate

performance of work under this contract in whole or, from time to time, in part if the Contracting

Officer determines that a termination is in the Government’s interest.” See id. at 454.

A week later, on August 19, 2009, the DOE reversed course and withdrew its consent for

the ARC-Toxco subcontract. See id. at 498-500. Swiftly thereafter, ARC cancelled its

3 subcontract with Toxco. Id. at 501-03. ARC subsequently re-contracted with EnergySolutions

for completion of the remainder of Task Order SP15’s remediation project at SPRU. Def.’s Mot.

at 12. By June 12, 2010, EnergySolutions had completed the work contemplated by Task Order

SP15. Id.

B. Procedural History

The plaintiff commenced this action in October 2009, asserting that the DOE’s

withdrawal of consent to the ARC-Toxco subcontract was both an arbitrary and capricious

agency action in violation of the APA and a deprivation of property in violation of the Due

Process Clause of the Fifth Amendment. See generally Compl. Upon filing its complaint, the

plaintiff also moved for a preliminary injunction requiring the DOE to reinstate its consent to the

subcontract so that it could continue with work on the subcontract. See generally Pl.’s Mot. for

Preliminary Injunction. The defendants moved to dismiss the complaint. See generally Defs.’

Mot. to Dismiss. In July 2010, the court issued a memorandum opinion denying the defendants’

motion to dismiss and denying the plaintiff’s motion for a preliminary injunction. See generally

Mem. Op. (July 20, 2010).

In September 2010, the defendants filed a second motion to dismiss under Rule 12(b)(1),

asserting that the plaintiff’s claims are moot. See Defs.’ Mot. at 15-20. In the alternative, the

defendants move for summary judgment on all of the plaintiff’s claims. Id. at 20-30. With the

defendants’ motion now ripe for review, the court turns to the applicable legal standards and the

4 parties’ arguments.2

III. ANALYSIS

A. The Court Grants the Defendants’ Rule 12(b)(1) Motion to Dismiss the Plaintiff’s APA Claim for Mootness

1. Legal Standard for a Motion to Dismiss for Mootness

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Enplanar, Inc. v. Marsh
11 F.3d 1284 (Fifth Circuit, 1994)
Lynch v. United States
292 U.S. 571 (Supreme Court, 1934)
United States v. W. T. Grant Co.
345 U.S. 629 (Supreme Court, 1953)
Flast v. Cohen
392 U.S. 83 (Supreme Court, 1968)
Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Perry v. Sindermann
408 U.S. 593 (Supreme Court, 1972)
Weinstein v. Bradford
423 U.S. 147 (Supreme Court, 1975)
County of Los Angeles v. Davis
440 U.S. 625 (Supreme Court, 1979)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lewis v. Continental Bank Corp.
494 U.S. 472 (Supreme Court, 1990)
Norman v. Reed
502 U.S. 279 (Supreme Court, 1992)
City of Erie v. Pap's A. M.
529 U.S. 277 (Supreme Court, 2000)
Columbian Rope Co. v. West, Togo D.
142 F.3d 1313 (D.C. Circuit, 1998)
Arrington, Derreck v. United States
473 F.3d 329 (D.C. Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Toxco Inc. v. Chu, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toxco-inc-v-chu-dcd-2011.