Township of Plymouth v. County of Montgomery

531 A.2d 49, 109 Pa. Commw. 200, 1987 Pa. Commw. LEXIS 2453
CourtCommonwealth Court of Pennsylvania
DecidedSeptember 8, 1987
DocketAppeals, 3312 C.D. 1986 and 3313 C.D. 1986
StatusPublished
Cited by19 cases

This text of 531 A.2d 49 (Township of Plymouth v. County of Montgomery) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Township of Plymouth v. County of Montgomery, 531 A.2d 49, 109 Pa. Commw. 200, 1987 Pa. Commw. LEXIS 2453 (Pa. Ct. App. 1987).

Opinion

Opinion by

Judge Craig,

In this case, where a proposed county refuse disposal plant feces prohibition by township enactments, we *203 must recognize statutory and judicial distinctions between ordinance provisions governing where the location of the facility may be (zoning provisions) and, on the other hand, how it may be technically designed and operated (operational regulations).

Such an analysis, mindful of a meaningful classification of local enactments, is necessary to resolve this cases two chief issues:

1. Did the trial court, in an equity and declaratory judgment proceeding, have subject matter jurisdiction to decide ordinance validity questions without requiring the county first to exhaust administrative remedies for the invalidation of zoning provisions under the Pennsylvania Municipalities Planning Act (MPC)? 1
2. Has the Solid Waste Management Act 2 preempted the townships power to enact and enforce both the operational regulations and the zoning provisions on which it seeks to rely?

The Proceedings

In the Court of Common Pleas of Montgomery County, Plymouth Township simultaneously filed declaratory judgment and equity actions against Montgomery County, seeking a declaration that the county’s proposed 1200-ton-per-day resource recovery facility, a trash-to-steam refuse disposal plant, would violate township ordinances, and also seeking an injunction to bar the county from further action to effectuate that project.

*204 After Judge Corso denied the townships request for a temporary restraining order, the county responded to the complaints and, in the equity action, by counterclaim sought to have the court invalidaté the ordinances and enjoin the township from blocking construction and operation of the proposed plant.

Following the courts rejection of the townships preliminary objections to the counterclaim, the parties stipulated to the consolidation of the two cases and agreed to an initial trial phase limited to evidence pertinent to the issues of jurisdiction and preemption.

After a thorough hearing, the trial judge, Judge Bucher, issued an adjudication in which he adopted numerous detailed findings of fact and conclusions of law, pursuant to which he ruled the questioned ordinance provisions to be unenforceable with respect to the county’s proposed plant. He granted the county’s counterclaim by enjoining the township from taking any action against the county’s project other than comments and objections to the Department of Environmental Resources (DER) and the Environmental Hearing Board. He confirmed that decision following post-trial motions.

Following the township’s appeals to this court, the county sought, the application of extraordinary jurisdiction by the Supreme Court, which remanded the case to this court for expédited disposition.

Facts

This court, after reviewing the record, discerns no abuse of discretion by the trial judge with respect to the findings of fact, in that the record contains substantial evidence supporting all of them. Reference to specific findings will follow, as pertinent.

A condensed chronology of events, drawn from those findings, can provide the factual background for analysis. In October, 1982, the township, by resolution, au *205 thorized the county to develop a countywide waste management plan under the SWMA. After the county, in 1983 and 1984, in consultation with the municipalities, considered the establishment of an 1800-ton-per-day plant in the township for the district in which the township was located, a Montgomery County Solid Waste Management Committee, on which the township was represented, proceeded in 1985 to prepare a request for proposals (RFP) for a 1200-ton-per-day plant to be located on county-owned property in the township. In February of that year, a letter of the township solicitor indicated that there would be “no problem” with that size of plant.

On April 15, 1985, the township adopted an amendment to its zoning ordinance, establishing a 121-acre resource recovery district and allowing a plant of 1200-ton (throughput) capacity, with height maximum at 165 feet.

However, after the development of community opposition to such a plant in the township, the township council proceeded on April 29, 1985 to repeal that zoning amendment, only two weeks after its enactment. Although the stated reason for the repeal was inadequate advertising, the township did not attempt to readvertise it.

After the county had issued the RFP for the 1200-ton facility on May 7, 1985, the township council issued a- public declaration on May 29 that they were “unanimously opposed” to any type of solid waste disposal facility within the township.

Thereafter, in connection with township deliberations, the township solicitor advised the council that “limitation of tonnage for trash transfer stations” could be illegal, and also that this court had decided that zoning could not be used to regulate the method of operation of a landfill or trash transfer station.

*206 On July 8, 1985, the township passed the three ordinances chiefly at issue here, Nos. 934, 936 and 937.

In December, 1985, the county completed and adopted its Municipal Waste Management Plan calling for development of the 1200-ton facility within the district designated by the township for a resource recovery facility. After DER issued preliminary approval of the plan, the county entered into contracts with private companies to construct and operate the plant in question. Seventeen of the twenty-four municipalities in the district have contracted with the county to take their municipal waste for disposal at the plant. The County Industrial Development Authority has also issued bonds to finance the construction costs.

While the DER approval process was underway in 1986, the township advised the county that the township regarded the proposed facility as “illegal” and that the township would not issue a permit for it unless a court invalidated the township ordinances.

This litigation followed.

Provisions of the Ordinances

Ordinance No. 934, the Solid Waste Management Ordinance, is not part of the townships Zoning Ordinance. It regulates the processing and disposal of waste by requiring operators to obtain permits, pay permit application fees up to $100,000 and pay user fees of $.50 per ton for waste processed. That ordinance also regulates the disposal of waste at the facility, and the transportation of waste with respect to details of routing and route cleaning, vector control, vehicle > size and emergency operational plans.

Ordinance No. 936, a zoning ordinance amendment, reestablishes the district regulations for the resource recovery district. It sets the maximum height of *207

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaler Twp. v. ZHB of Shaler Twp.
Commonwealth Court of Pennsylvania, 2025
R. & Y. Burd v. Borough of Brentwood ZHB
Commonwealth Court of Pennsylvania, 2023
Penn Street, L.P. v. East Lampeter Township Zoning Hearing Board
84 A.3d 1114 (Commonwealth Court of Pennsylvania, 2014)
Geryville Materials, Inc. v. Planning Commission of Lower Milford Township
74 A.3d 322 (Commonwealth Court of Pennsylvania, 2013)
Atherton Development Co. v. Township of Ferguson
29 A.3d 1197 (Commonwealth Court of Pennsylvania, 2011)
BPG Real Estate Investors-Straw Party II, L.P. v. Board of Supervisors
990 A.2d 140 (Commonwealth Court of Pennsylvania, 2010)
Arbor Resources Ltd. Liability Co. v. Nockamixon Township
973 A.2d 1036 (Commonwealth Court of Pennsylvania, 2009)
Hoffman Mining Co., Inc. v. ZONING HEARING BD. OF ADAMS TOWNSHIP
958 A.2d 602 (Commonwealth Court of Pennsylvania, 2008)
Synagro-WWT, Inc. v. RUSH TP., PENNSYLVANIA
299 F. Supp. 2d 410 (M.D. Pennsylvania, 2003)
Baker v. Chartiers Township Zoning Hearing Board
677 A.2d 1274 (Commonwealth Court of Pennsylvania, 1996)
Kasper Bros., Inc. v. Falls Township
672 A.2d 1386 (Commonwealth Court of Pennsylvania, 1996)
Klein v. Shadyside Health, Education & Research Corp.
643 A.2d 1120 (Commonwealth Court of Pennsylvania, 1994)
Pennsylvania Coal Co. v. Township of Conemaugh
612 A.2d 1090 (Commonwealth Court of Pennsylvania, 1992)
Palermo Land Co. v. Planning Com'n of Calcasieu Parish
561 So. 2d 482 (Supreme Court of Louisiana, 1990)
T.R.A.S.H., Ltd. v. Commonwealth
574 A.2d 721 (Commonwealth Court of Pennsylvania, 1990)
Knight v. Lynn Township Zoning Hearing Board
568 A.2d 1372 (Commonwealth Court of Pennsylvania, 1990)
Abbey v. Zoning Hearing Board
559 A.2d 107 (Commonwealth Court of Pennsylvania, 1989)
Township of Plymouth v. County of Montgomery
550 A.2d 1033 (Commonwealth Court of Pennsylvania, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
531 A.2d 49, 109 Pa. Commw. 200, 1987 Pa. Commw. LEXIS 2453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/township-of-plymouth-v-county-of-montgomery-pacommwct-1987.